Name of Work:- Site Clearnce And Jungle Cutting At Both Side of Main Roads And Service Roads Of Balesar Durgawata.
Sl. No.
Item Description
1
Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level.In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc.Depth upto 1.5 m
2
Dressing of earth work in surface excavation including cutting and filling upto 30cm depth including disposal of excavated earth upto50m and lift upto 1.5 m.
3
Clearing Grass and Removal of Rubbish (Maximum 150mm) by manual means and disposal at a lead of 50 metres as per MoRT&H specification clause 201.
4
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to a lead of 50 metres from road boundary including removal and disposal of top organic soil not exceeding 150 mm in thickness as directed by Engineer.In area of light jungle
5
Construction of embankment with approved material obtained from borrow pit with all lifts and leads, transporting to site, spreading, grading to required slope and compacting by vibratory roller 8-10 tonne to meet requirement of table 300-2 including cost of compensation for earth taken from private land complete as per MoRT&H specification clause 305. (Lead taken upto 5 km)
6
Providing, laying, spreading and compacting of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per MoRT&H specification clause - 401 including all material, labour, machinery, lighting, guarding and maintenance of diversion.Grading - III Material Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.