| 1 | Providing and laying in position ready mixed or site batched design mix cement concrete for plain cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana/Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering and finishing as per direction of the engineer-in-charge; for the following grades of concrete. Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the minimum specified cement content, the contractor shall have discretion to either redesign the mix or bear the cost of extra cement. |
| 2 | All works upto plinth level : |
| 3 | Concrete of M10 grade with minimum cement content of 220 kg /cum |
| 4 | Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge; for the following grades of concrete.Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the specified minimum cement content, the contractor shall have discretion to either redesign the mix or bear the cost of extra cement. |
| 5 | All works upto plinth level |
| 6 | Concrete of M25 grade with minimum cement content of 330 kg /cum |
| 7 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in : |
| 8 | Cement mortar 1:4 (1 cement : 4 coarse sand) |
| 9 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. |
| 10 | In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
| 11 | 12 mm cement plaster finished with a floating coat of neat cement of mix : |
| 12 | 1:3 (1 cement: 3 fine sand) |
| 13 | 15 mm cement plaster on rough side of single or half brick wall finished with a floating coat of neat cement of mix : |
| 14 | 1:3 (1 cement: 3 fine sand) |
| 15 | Providing and placing in position 100 mm thick factory made machine batched & machine mixed Precast RCC Rectangular Covers on drains of footpath of various sizes, of M-25 or more grade cement concrete for RCC work, including cost of centering, shuttering, reinforcement of 8 mm dia TMT bars of Fe 500 grade @ maximum 100mm c/c on both ways , neat cement punning on finished surface, properly encased on all edges with 1.6 mm thick , 100 mm wide MS sheet duly painted over priming coat , reinforcement to be welded at edges with MS sheet and providing 2 Nos. 12 mm dia bar for hooks etc i/c cost of cartage, all leads & lift, handling at site etc. all complete as per direction of Engineer-in-Charge. Note- Size of the drain conver shall be decided by Engineer - in - Charge. |
| 16 | Deduct Correction Factor on DSR Item @ 0.973 |
| 17 | Add Cost Index @4.03% |
| 18 | Disposal of silt, sludge, building rubbish, earth mixed malba, plastic bags, all type of floating, solid and semi- solid malba/ rubbish / similar unserviceable dimantled or waste materials by mechanical means/including loading, transporting and unloading the same at any authorized Municipal/ any other Dumping Ground including weighing at plant etc. complete as per direction of Engineer-in-charge. Weighing and unloading at the plant shall be as per procedures/ rules of the Dumping Ground Management. The rates are inclusive of all operations, labours, leads and lifts from site of work to the authorized Municipal/ any other Dumping Ground. (Processing fees at prescribed rate of dumping ground will be deposited by the agency and shall be reimbursed by the department on production of only original cash receipts). (Payments for disposal under this item will be made on production of original Municipal dumping ground receipts), the agency shall also submit pre & post photograph in soft/hard copy.(Mandatory Note- Malba should be removed from site instantly within hours after cleaning of drain) |
| 19 | Hiring and operation of hydraulic excavator (3D)/JCB Machine for 8 Hours per day for dressing of katcha portion and removal of malba i/c loading, unloading of dismantled material in trucks or dumpers (water tight trolley), levelling and dressing of ground etc. including all risk involved in demolition operations etc. i/c cost of driver, helper, diesel, lubricants etc. complete as per direction of Engineer-in- Charge. |
| 20 | Providing services of Hydraulic Mobile Pick and carry Crane Capacity up to 15.00 Tan for 8 Hours per day for removing Jersey Barriers from one place to another place, aligning the same, lifting the vehicles, heavy materials etc including the cost of driver, supervisor all complete as per directions of Engineer-in-Charge. |
| 21 | Providing services of Beldar/ Sewerman for 8 hours working period (1 shift) for the purpose of cleaning drain, removing water logging etc. day to day work as per direction of Engineer-in-Charge. |
| 22 | Providing the service for supervisor, having knowledge of road maintenance and civil work, equipped with Motorcycle, android mobile at list 5.0” screen i/c internet & Data transfer facility, conversant in Hindi and English for daily inspection/Supervision of roads under the jurisdiction of PWD Division SRD-2 as per direction of Engineer-in-Charge for working hours of 8 hours shift. (No extra payment will be admissible, rates are inclusive of all expenses). Please Enable Macros to View BoQ information |