| 1 | Demolishing R.B. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in- charge. (Including all materials, T&P and labour cess etc. But excluding GST) |
| 2 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In lime mortar with old mughal bricks (Including all materials, T&P and labour cess etc. But excluding GST) |
| 3 | Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead. (Including all materials, T&P and labour cess etc. But excluding GST) |
| 4 | Reinforced cement concrete work in beams, suspended floors, roofshaving slope up to 15° landings, balconies, shelves, chajjas, lintels,bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering,finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). (Including all materials, T&P and labour cess etc. But excluding GST) |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers (Including all materials, T&P and labour cess etc. But excluding GST) |
| 6 | Centering and shuttering including strutting, propping etc. and removal of for Suspended floors, roofs, landings, balconies and access platform with water proof ply 12 mm thick (Including all materials, T&P and labour cess etc. But excluding GST) |
| 7 | Steel reinforcement for R.C.C. work including straightening, cutting,bending, placing in position and binding all complete upto plinth level Thermo-Mechanically Treated bars of grade Fe-500D or more. (Including all materials, T&P and labour cess etc. But excluding GST) |
| 8 | Brick work with common burnt clay machine moulded perforated bricks of class designation 12.5 conforming to IS: 2222 in superstructure above plinth level up to floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) With F.P.S.(non modular) bricks (Including all materials, T&P and labour cess etc. But excluding GST) |
| 9 | 12 mm cement plaster of mix 1:6 (1 cement: 6 fine sand) (Including all materials, T&P and labour cess etc. But excluding GST) |
| 10 | 15 mm cement plaster on the rough side of single or half brick wall of mix : 1:6 (1 cement: 6 fine sand) (Including all materials, T&P and labour cess etc. But excluding GST) |
| 11 | 6 mm cement plaster of mix :1:3 (1 cement : 3 fine sand) (Including all materials, T&P and labour cess etc. But excluding GST) |
| 12 | 15 mm cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating coat of neat cement on the rough side of single or half brick wall. (Including all materials, T&P and labour cess etc. But excluding GST) |
| 13 | Providing and fixing panelled or panelled and glazed shutters for doors, windows and clerestory windows, fixing with butt hinges of required size with necessary screws, excluding panelling which will be paid for separately, all complete as per direction of Engineer-in-charge. (Note:- Butt hinges and necessary screws shall be paid separately) (Second class teak wood 35 mm thick shutters) (Including all materials, T&P and labour cess etc. But excluding GST) |
| 14 | Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete. (Including all materials, T&P and labour cess etc. But excluding GST) |
| 15 | Distempering with oil bound washable distemper of approved brand and manufacture to give an even shade :New work (two or more coats) over and including water thinnable priming coat with cement primer. (Including all materials, T&P and labour cess etc. But excluding GST) |
| 16 | Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required shade: New work (Two or more coats applied @ 1.43 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm) (Including all materials, T&P and labour cess etc. But excluding GST) |
| 17 | Finishing with Deluxe Multi surface paint system for interiors and exteriors using Primer as per manufacturers specifications :Two or more coats applied on walls @ 1.25 ltr/10 sqm over and including one coat of Special primer applied @ 0.75 ltr /10 sqm (Including all materials, T&P and labour cess etc. But excluding GST) |
| 18 | Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved. (Including all materials, T&P and labour cess etc. But excluding GST) Please Enable Macros to View BoQ information |