| 1 | Clearing jungle including up rooting of rank, vegetation grass, push, wood trees and samplings of girth up to 30 cms, measured at a height of 1M. above ground level and removal of rubbish up to a distance of 50M. out side the periphery of area cleared. as per SOR No.-259 (i) |
| 2 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. |
| 3 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.) The Contractor has detect different utilities like sewer line, Water Supply Line, Electric Cable, Telephone Cable, Gas Pipe Line(using Utility Detecting MAchine Before Start of Excavation and Shall start Excavation only after getting Permission of Engineer-in-Charge. |
| 4 | Cement Concrete with 4 cm gauge approved stone ballast, coarse sand & Cement in the proportion of 8:4:1 including supply of all materials, labour, Tools & plants etc. required for proper completion of work |
| 5 | Cement concrete with 4 cm gaug approved stone ballast, course sand & cement in proportion of 4:2:1 including supply of all materials labour tools and plant etc. required for proper completion of work Same as above item No. 279 but with 2cm gaug stone grigt insted of 4 cm gauge stone ballast. |
| 6 | RCC work with cement, approved coarse sand & 2 cm gauge approved stone grit in proportions of 1:2:4 in slabs excluding supply of reinforcement and its bending, but including its fixing and binding the same with 24 BWG GI binding wire and including necessary centering and shuttering etc. and supply of all materials, labour, tools & plants etc. required for proper completion of work including cost of binding wire. The rates excludes making of drip course which shall be paid extra. |
| 7 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo- Mechanically Treated bars of grade Fe-500D or more. |
| 8 | M-150 Brick Work in 1:4 Cement & Coarse sand of 2.20 F.M. mortar in foundation and plinth including supply of all materials, labour and T&P etc. required for proper completion of the work |
| 9 | 12 mm cement plaster of mix 1:4(1 cement: 4 coarse sand) |
| 10 | 15 mm cement plaster : 1:4 (1 cement : 4 coarse sand) |
| 11 | Neat Cement punning |
| 12 | Centering and shuttering including strutting, propping etc. and removal of form work for: Foundations, footings, bases for columns |
| 13 | Centering and shuttering including strutting, propping etc. and removal of form for : Suspended floors, roofs, landings, balconies and accessplatform |
| 14 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. : In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
| 15 | Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade : One or more coats on old work |
| 16 | Providing wall Putty on old surface with approved quality material of Berger/J.K./Birla or similar make 2 coats. |
| 17 | Providing and laying damp-proof course 40mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III): 4 graded stone aggregate 12.5mm nominal size) |
| 18 | S/o Wheel Excavator Cum Loader including P.O.L. and Driver complete as per direction of Engineer-in-Charge. |
| 19 | S/o Tractor with Trolley including P.O.L. and Driver complete as per direction of Engineer Incharge.. |
| 20 | Supply of Beldar |
| 21 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) |
| 22 | Finishing wall with waterproof cement paint of approved make and quality on new wood with two coat to give an even shade including suppy of all materials labour, tools & plant etc. required for proper completion of the work. Same as Item 660 but for weathercoat (Asian or Berger brand) Please Enable Macros to View BoQ information |