| 1 | Construction of Subgrade and Earthen Shoulder with approved soil with all lifts and leads, laying in layers, breaking clods, dressing to required lines, curves, grade and sections, watering and compaction to meet at least 100 % procter density complete to specification requirements.Clause 301.5 (3.3+3.5) (301.5+302 ii) |
| 2 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. |
| 3 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. |
| 4 | Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days, using curing compound (where specified) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501 |
| 5 | Reinforced cement concrete M15 grade kilometre stone/local stone of standard design as per IRC:8 fixing in position including painting and printing, etc as per drawing and Technical Specification Clause 1703.Ordinary Kilometer Stone (Precast) |
| 6 | Reinforced cement concrete M15 grade hectometre stone/local stone of standard design as per IRC:8 fixing in position including painting and printing, etc as per drawing and Technical Specification Clause 1703.200 m Stone (Precast) |
| 7 | Painting lines, dashes, arrows, etc. on roads with hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads in two coats on new work with ready mixed road marking paint conforming to IS:164 on bituminous/concrete surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control as per drawing and Technical Specification Clause 1702 |
| 8 | Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. |
| 9 | Fillling in foundation trenches as per drawing and technical specification Clause 305.3.9 |
| 10 | Laying Cement Concrete 450mm dia Pipe NP3 (burried conduits) on first class bedding of granular material in single row including fixing collar with cement sand mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonary work in head wall and parapet |
| 11 | Providing and laying reinforced cement concrete 1000mm dia pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry (1X1000) |
| 12 | Pointing with cement mortar (1:3) on brickwork as per drawing and technical specification Clauses 613.3 and 1204 |
| 13 | Construction of enmbankment with approved material deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requriment of Table 300.1 and 300.2 as per Technical Specification Clause 301.5 |
| 14 | Painting two coats including primer coat after filling the surface with synthetic enamel paint in all shades on new, plastered / concrete surfaces as per drawing and Technical Specification Clause 1701 |
| 15 | Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. |
| 16 | Brick masonry in 1:4 cement mortar in foundation complete excluding pointing and plastering as per drawing and technical specifications Clauses 600, 1202 & 1203 |
| 17 | Providing PCC (1:3:6) concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 |
| 18 | Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification Clauses 613.4 & 1204 |
| 19 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 P.C.C. grade M 20 |
| 20 | Providing and Fixing Project Informatory Board including all complete as Specified. Please Enable Macros to View BoQ information |