Indian Tenders

Tender Notice

TDR 54698727
Tendering Authority Public Works Department
Tender No 1063/4E-NIVIDA-BASTI CIRCLE/25-26 DATED-27-02-2026
Tender ID 2026_CEUBZ_1126358_1
Tender Brief Tender For New Construction Work Of Tadwariya Samogar Mehdupar (Odr) Road Km 7 To Amarha Bio Plant Link Road
City Basti
State Uttar Pradesh
Document Fees INR 2714 /-
EMD INR 1150000.0 /-
Tender Value INR 1.90 Crore /-
Tender Type Tender
Bidding Type Open Tender
Competition Type Indian

Tender Details

Tender for New Construction Work Of Tadwariya Samogar Mehdupar (Odr) Road Km 7 To Amarha Bio Plant Link Road

Key Dates

Publish Date 17-03-2026
Last Date of Bid Submission 23-03-2026
Tender Opening Date 23-03-2026

Contact Information

Company Name Public Works Department
Contact Person O/F SUPRINTENDING ENGINEER BASTI CIRCLE PWD BASTI
Address O/F SUPRINTENDING ENGINEER BASTI CIRCLE PWD BASTI

BOQ Items

Name of Work:- NEW CONSTRUCTION WORK OF TADWARIYA SAMOGAR MEHDUPAR (ODR) ROAD Km 7 TO AMARHA BIO PLANT LINK ROAD
Sl. No. Item Description
1Earth work in cutting or in embankment in ordinary soil, excavation to be in the form of regular pits not not exceding 0.50 mt. in depth and work in embankmet to be n 20 cm. layers includding ramming and dressing the surface to required level and slope and also including 1.5 mt. lift and 30 mt. lead as per SL. No.253 Embankment work. Technical Specification Complete in all aspects or as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P).
2Providing and Laying 12.50/11.00 cm compacted thickness granular sub-base (G.S.B.) by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Speicification Clause 401 . as per Technical Specification Complete in all aspects or as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P).
3Providing and laying 7.50/10.00cm compacted thickness of stone aggregates of specific sizes 45-63 mm of water bound macadam specification incluidng spreading in uniform thickness hand packing rolling with smooth wheel roller 80-100 KN in stages to proper grade and camber applying and brooming stone dust to fill-up the interstices of coarse aggregate watering and compacting to the required dencity grading -2 as per technical specification clause 405. as per Technical Specification Complete in all aspects or as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P).
4Providing and laying 7.50 cm compacted thickness of stone aggregates of specific sizes 22.4-53 mm of water bound macadam specification incluidng spreading in uniform thickness hand packing rolling with smooth wheel roller 80-100 KN in stages to proper grade and camber applying and brooming stone dust to fill-up the interstices of coarse aggregate watering and compacting to the required dencity grading -3 as per technical specification clause 405as per Technical Specification Complete in all aspects or as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P).
5Providing and applying Primer coat with bitumen emulsion on prepared surface of granular base including clearing of road surface and spraying primer using mechanical means. As per technical specification clause 502 (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P).
6Providing and applying tack coat with Bitumen VG-10 using bitumen distributor at the rate of 3.00 kg/10 sqm on the prepared bituminous surface Cleaned with Hydraulic broom as per Technical Specification Clause 503..as per Technical Specification Complete in all aspects or as per direction of E/l (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.)
7Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates using penetration grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of Type C as per Technical Specification Clause 508. Complete in all aspects or as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.)
8Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C, as per Technical Specification Clause 510 Complete in all aspects or as per direction of E/A (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Materini & T&P.)
9Brick edging on both sides of the road of first class bricks 8 cm (3'') wide and 12 cm. ( 4.5\\") deep laid with mud mortar including labour & supply of bricks finish to the required templeate and in proper alignment and also including dressing ramming the excavated earth as directed by Engineer-in-charge. Complete in all aspects or as per direction of E/1 (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Materini & T&P.)
10Earth work in patries with ordinary soil (loam,clay and sand) excavation to be in the form of regular pits not exceeding 50 cm in depth and earth work in embankment to be in 20 cm layers including the ramming and dressing the surface to required levels, slopes and also including 1.5 m lift and 30 m lead the earth form cutting to be used in making embankment or to be deposited as spoil bank within 30 m distance as directed by the Engineer-In-Charge including mechanically compaction without royalty as per ( S.I. No. 253) Complete in all aspects or as per direction of E/1 (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Materini & T&P.)
11Hume Pipe Culvert 600 mm DiaExcavation in foundation in ordinary soil (Loam clay or sand) including lift upto 1.5 metre (5 fts) and lead upto 30m (100 fts) & including filling watering and ramming of excavation earth into the trenches or into the space between the building and the sides of foundation trenches or into the space between the building and the earth as directed by the Engineer-in-charge upto a distance of 30M (100 fts) from the foundation trenches etc. As per SI Ni. 251 in Complete in all aspects or as per direction of E/l (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.)
12Cement Concrete with 4 cm. (1½\\") gauge approved Bricks ballast ,approved coarse sand and cement in the proportions or 8:4:1 including supply of all materials, labour and T&P etc. required for proper completion of the work with proper curing.(SI No-275) in Complete in all aspects or as per direction of E/l (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.)
13First class brick work in 1:4 cement and fine sand of 1.25 F.M. mortar in foundation and plinth including supply of all materials , labour and T&P etc. required for proper completion of the work with proper curing.SI No-305 in Complete in all aspects or as per direction of E/l (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.)
14Struck pointing with cement mortar consisiting of 1 part cement and 2 part fine sand of F.M 1.25 including supply of all materials labour and T&P etc required for proper completion of the work with proper curing SI No-574 in Complete in all aspects or as per direction of E/l (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.)
15Supply of NP-3 600 mm Hume pipes in Complete in all aspects or as per direction of E/l (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.)
16Laying of NP-3 600 mm Hume pipes in Complete in all aspects or as per direction of E/l (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.)
17Supply and fixing of iron Sign Board in Complete in all aspects or as per direction of E/l (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.)
18Supply and fixing of Km.Hect etc Stone in Complete in all aspects or as per direction of E/l (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P.)
19Executing work of Maintenance Cost 1st Yearmaintenancecharge @0.00% including complete in all aspects Excluding G.S.T but Including All Taxes Labour Cess, Royalty, Labour, Material & T&P.
20Executing work of Maintenance Cost 2stYearmaintenancecharge @0.75% including complete in all aspects Excluding G.S.T but Including All Taxes Labour Cess, Royalty, Labour, Material & T&P.
21Executing work of Maintenance Cost 3stYearmaintenancecharge @1.50% iincluding complete in all aspects Excluding G.S.T but Including All Taxes Labour Cess, Royalty, Labour, Material & T&P.
22Executing work of Maintenance Cost 4stYearmaintenancecharge @2.25% including complete in all aspects Excluding G.S.T but Including All Taxes Labour Cess, Royalty, Labour, Material & T&P.
23Executing work of Maintenance Cost 5stYearmaintenancecharge 3.00% including complete in all aspects Excluding G.S.T but Including All Taxes Labour Cess, Royalty, Labour, Material & T&P.
24GSBProviding and Laying 12.50/11.00 cm compacted thickness granular sub-base (G.S.B.) by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Speicification Clause 401 . as per Technical Specification Complete in all aspects or as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P).
25WBM G-3 Providing and laying 7.50 cm compacted thickness of stone aggregates of specific sizes 22.4-53 mm of water bound macadam specification incluidng spreading in uniform thickness hand packing rolling with smooth wheel roller 80-100 KN in stages to proper grade and camber applying and brooming stone dust to fill-up the interstices of coarse aggregate watering and compacting to the required dencity grading -3 as per technical specification clause 405. as per Technical Specification Complete in all aspects or as per direction of E/I (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Material & T&P).
26Cement Concrete Pavement Construction of un-reinforced, dwel jointed, plain cement concrete pavement over a prepared sub base with approve grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous peration including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per design. including labour ces with proper curing Complete in all aspects or as per direction of E/1 (Rates are Excluding G.S.T but Including All Taxes Royalty, Labour cess, Materini & T&P.)
27Executing work of Maintenance Cost 1st Yearmaintenancecharge @0.00% including complete in all aspects Excluding G.S.T but Including All Taxes Labour Cess, Royalty, Labour, Material & T&P.
28Executing work of Maintenance Cost 2stYearmaintenancecharge @0.25% including complete in all aspects Excluding G.S.T but Including All Taxes Labour Cess, Royalty, Labour, Material & T&P.
29Executing work of Maintenance Cost 3stYearmaintenancecharge @0.50% iincluding complete in all aspects Excluding G.S.T but Including All Taxes Labour Cess, Royalty, Labour, Material & T&P.
30Executing work of Maintenance Cost 4stYearmaintenancecharge @0.75% including complete in all aspects Excluding G.S.T but Including All Taxes Labour Cess, Royalty, Labour, Material & T&P.
31Executing work of Maintenance Cost 5stYearmaintenancecharge 1.00% including complete in all aspects Excluding G.S.T but Including All Taxes Labour Cess, Royalty, Labour, Material & T&P. Please Enable Macros to View BoQ information

Other Detail

Information Source https://etender.up.nic.in
Download FileName File Description File Size
Download 2cff3546-8f34-45e7-8d54-457a644dcaf1.html Tender Documents 0 KB
Download BOQ_2100410.xls Tender Documents 0 KB
Download T2.pdf Tender Documents 0 KB
Download Tendernotice_1 (7).pdf Tender Documents 0 KB
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.