| 1 | Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 (3.4).(Excluding GST) |
| 2 | Cement Treated Sub Base (2% Cement OPC)Providing,laying and spreading material on a prepared Sub grade adding cement @ 2% by wet to the spread material manually mixing in place Rotavator and compacting with the road roller at OMC to achieve the desired unconfined Compressive strength and to form a Layer of Sub Base.(Excluding GST) |
| 3 | Cement Treated Base (4% Cement OPC)Providing,laying and spreading material on a prepared Sub Base, cement @ 4% by wet to the spread material manually mixing in place Rotavator and compacting with the road roller at OMC to achieve the desired unconfined Compressive strength and to form a Layer of Base.(Excluding GST) |
| 4 | Providing and applying tack coat with bitumen VG-10 using emulsion pressure distributor at the rate of 0.35 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Speicification Clause 503.(Excluding GST) |
| 5 | Providing, laying and rolling of open-graded premix carpet of 20mm thickness composed of 13.2 to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line grade and level to serve as wearing coarse on a previously Prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100kN static roller capacity finished to required lavel and grades to be followed by seal coat as per Techincal Specification clause 508.(Excluding GST) |
| 6 | Providing and applying seal coat type \\"C\\" comprising of a layer of bituminous binder followed by a cover of stone chipping of specified grading and rolling with power roller 8-10 tonne kN Static roller and finishing to required level and grades as per Technical Specification Clause 510.(Excluding GST) |
| 7 | Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections.(Excluding GST) |
| 8 | Plain cement concrete M10(1:3:6 nominal mix) in levelling course below open foundation of head wall as per drawing and technical specification clause 1109.(Excluding GST) |
| 9 | Laying (40mm SSB)Bedding on well compacted sand,moorum or approved granular material as per Clause 1105(ii).(Excluding GST) |
| 10 | Brick Masonry Work in cement mortar (1:4) in foundation of head walls complete excluding poining and plastering as per rawing and technical specification Clause 1109.(Excluding GST) |
| 11 | Providing and laying R.C.C.Pipe NP3 for culverts on first class bedding of granular material in sigle row including fixing collar with 1:2 cement mortar but excluding excaation protection work,back filling,concrete ad masonry wok in head wall and parapet Clause 1106.(Excluding GST) |
| 12 | Pointing with cement mortar (1:3) on brick work as per technical specification clause 613.3.(Excluding GST) |
| 13 | Backfilling from local sand in foundation trenches as per drawing and technical specification Clause 1108. 30% of Item no. 9.(Excluding GST) |
| 14 | (Construction of subgrade and Earthen shoulders)Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.(Excluding GST) |
| 15 | Maintenance of constructed road for next five year after completion of work shall be paid. as per GO No 17/2024 /lk0-113/23-1-2024-23-1099-113/2023 yksd fuekZ.k foHkkx vuqHkkx&1 fnuakd 16-01-2024 ,oa dk;kZy; izeq[k vfHk;Urk ;krk;kr oxZ yks0fu0fo0 y[kuÅ dk i=kad&3689lh&vks0ih0vkj0,e0lh0@ewy&23&24 fnuakd 17-02-2024- Payment shall be done as per satisfaction of engineer in chage regarding maintenance work carried out by contractor (Including Labour Cess but GST will paid extra as applicable). 1st year Maintenance cost total construction of cost Item No. 1 to 14 Rs. 5303583.72 @ Zero percent on 1st year & for 2nd year @ 0.75% |
| 16 | Maintenance Charge for 3rd Year @ 1.5% |
| 17 | Maintenance Charge for 4th Year @ 2.25% |
| 18 | Maintenance Charge for 5th Year @ 3% Please Enable Macros to View BoQ information |