| 1 | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m |
| 2 | Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2. ( Roller Compaction) |
| 3 | Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical specification clause 301.5 |
| 4 | Construction of Embankment with Material Obtained from Borrow Pits (Carted earth)Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical specification clause 301.5 |
| 5 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401 |
| 6 | Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing. |
| 7 | Construction of reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing. |
| 8 | Supplying, fitting and placing Fe-415 HYSD bar reinforcement in super-structure complete as per drawing and technical specifications (For Dowel bar) |
| 9 | Construction of Subgrade and Earthen Shoulders with approved material obtained from borrow pits with all lifts and loads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m. as per technical specification clause 303.1 |
| 10 | Excavation in foundation in ordinary soil ( Loam clay or sand) including lift up to 1.5 meter (5ft) and lead upto 30m (100ft) and including filling,watering & ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as direction by the Engineer-in-charge upto a distance of 30m(100ft) from the foundation trenches. SI No 251 |
| 11 | Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8km (5 miles) from the side of work & including watering ,dressing etc. Rate to include cost of all materials,labour and tools & plants,etc. required for proper completion of the work. SI No 255 |
| 12 | Cement concrete with 4cm (1/2'') gauge approved stone ballast, approved coarse sand. cement in the proportion 8:4:1 including supply of all materials,labour and tools and plants etc. required for proper completion of the work. SI No 281 |
| 13 | Random course Rubble massonary in 1:4 cement and fine sand mortar in foundation and plinth, including supply of all materials, labour & T&P etc. required for proper completion of the work. (Chapter- 8 (Add item-a) |
| 14 | Providing, laying and fixing of 350mm dia NP3 Hume Pipe in proper position and joining them with coller and filling of joint with jute and cement mortar in 1:2 cement and sand complete. As per PWD Misc.Item S.I. No.-11(a) |
| 15 | Providing and laying reinforced cement concrete 1000 mm pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 1106. |
| 16 | Raised pointing with cement and fine sand of 1.25 fineness modulus mortar on brick work in proportion of 1:2 including supply of all materials, labour and tools and plants etc. required for proper completion of the work SI No 577 |
| 17 | Cement concrete with 20mm gauge approved stone ballast, approved coarse sand. cement in the proportion 4:2:1 including supply of all materials,labour and tools and plants etc. required for proper completion of the work. 279(a) |
| 18 | 12mm thick plaster on brick work minimum thickness not less than 10mm with 1part of cement and 4 part of find sand of 1.25 fineness modulus. SI No 584 |
| 19 | Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause |
| 20 | Reinforcement Cement concrete with 2 cm. gauge approved stone, ballast, approved coarse sand and cement in the proportion of 3:1.5:1 including supply of all materials, labour and T&P etc. required for proper completion of the work. |
| 21 | Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 mad of high intensity grade sheeting type-IV vide clause 801.3, fixed cover aluminum sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x75 mm x6 mm firmly fixed to th ground by means of properly designed foundation with M-15 grade cement conc. 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing The retro reflective sheeting shall be tested for A certificate having the sheeting tested for coefficient of retro reflection day time color and luminance shrinkage fixable liner removal adhesion impact resistance specular glass and fungus resistance 3 year out door weathering and its having passed these tested shall be obtained from international/Government Laboratory/Institute by the manufacture of the sheeting and in case the certificate obtain from international condition it should also be obtain from Indian condition within 3 year of launching of product by the manufacture in aboard Alliteratively a certificate conforming to ASTM Specification (D 4956-09) on arterial accelerated weathering requirements from a reputed laboratory in India can be accepted provisionally in such a situation the Employer/ Client if so desires could seek for a performance guarantee which be released after of certificate meeting the requirement of three year outdoor weathering of the sheeting as per IRC 67 2012 Legends letters numerals and borders etc should be as per MoRTH specification No-801.3-7 proof of the same in form of government report shall be uploaded while quoting tender (as per IRC:67-2012 clause 14.60). Stop Board |
| 22 | Rumble Strip Board |
| 23 | Speed Limit Board |
| 24 | Providing and laying of hot appiled thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, Thickness of 2.5 mm is excluding of surface applied glass beads as per IRC: 35 The finished surface to be level, uniform and free from streak and holes |
| 25 | 1st Years Maintenance Charge 0.00% |
| 26 | 2nd Years Maintenance Charge 0.25% |
| 27 | 3rd Years Maintenance Charge 0.50% |
| 28 | 4th Years Maintenance Charge 0.75% |
| 29 | 5th Years Maintenance Charge 1.00% Please Enable Macros to View BoQ information |