| 1 | [Rates are based on PWD Electrical BSR 2013] |
| 2 | Plate Earthing as per IS:3043 with copper Earth plate of size 600mm x 600mm x 3.0mm by embodying 3 to 4 mtr. below the ground level with 25 mm dia. G.I. 'B' class watering Pipe including all accessories like nut, bolts, reducer, nipple ,wire meshed funnel, and C.C. finished chamber covered with hinged type with locking arrangement C.I. Cover, C.I. Frame of size300mm x 300mm complete with alternate layers of salt and coke/charcoal, testing of earth resistance as required. |
| 3 | Maintenance free Gel Earthing with Pipe in pipe / Pipe in strip technology filled with anti corrosive conductive compound ( CPRI Tested ) below the ground in 150 - 200 mm dia. earth pit & surrounding filled with required mineral filling compound ( MFC should have hygroscopic property to retain the moisture for long time to create low resistance zone ) and C.C. finished chamber covered with hinged type with locking arrangement C.I. Cover, C.I. Frame of size 300mm x 300mm complete testing of earth resistance as required. of following sizes. |
| 4 | With Pipe in Pipe Technology (Inner pipe dia. / Outer pipe dia. ) 80 - 100 micron GI Coating |
| 5 | GI pipe 2000 mm long, 80 / 40 mm, Terminal 12 mm GI Strip |
| 6 | S & Laying following size earth wire/strip in horizontal or vertical run in ground/surface/recess including riveting, soldering, saddles, making connection etc. as required. |
| 7 | 25mm x 3mm copper strip |
| 8 | 20mm x 3mm G.I. ( Hot Dipped ) Strip |
| 9 | Supply & fabrication steel structure with MS channel / angle / joist / ISMB / sheet etc. including welding, rivetting, cutting, nut & bolt , Painting etc. as required. |
| 10 | Random Rubble stone masonry for with hard stone in foundation and plinth in Cement Sand mortar above 30 CM thick wall in: |
| 11 | Cement Mortar 1:6 ( 1-Cement : 6-Sand). |
| 12 | Plaster on new surface on wall in cement sand mortar 1:3 including racking of joints etc. complete fine finish : |
| 13 | 12mm thick |
| 14 | P/Laying P.V.C. / XLPE insulated & P.V.C. sheathed cable of 1.1 KV grade with aluminium conductor of IS:1554 P-I / IS :7098 P - I of Group 1 of approved make in ground as per IS:1255 including excavation of 30cmx75cm size trench, 25 cm thick under layer of sand,IInd class bricks covering, refilling earth,compaction of earth, making necessary connection, testing etc. as required of size. |
| 15 | 25.0 Sq.mm |
| 16 | 4 core |
| 17 | SITC of Auto main failure (AMF) Panel fabricated from CRCA sheet steel 2 mmThick , Powder coated finish , Engine Start & Stop commands, control Relays , selector switches for Ammeter & Voltmeter, Ammeter & Voltmeter , Control & Power Contactors, Timers, Electronic Hooter ,Visual & Alarm indication for faults, UPS, operator interface panel complete in all respect suitable for following capacity DG sets:Grp1 |
| 18 | PLC Based: |
| 19 | 25 to 40 KVA |
| 20 | Elect. BSR 2025 |
| 21 | SITC of Radiator Cooled Silent DG Set (As per latest CPCB-IV+ emission norms) having specifications as per A, B, C, D, E, F & G : |
| 22 | A) Diesel Engine : Turbo charged Diesel Engine ( conforming to BS:649/5514), multi cylinder, dynamically balanced flywheel, electric start of suitable BHP at 1500 rpm capable of taking 10% over loading for one hour after 12 hours of continuous operation., Dry exhaust mainfold with silencer and Diesel oxidation catalyst & selective catalyst reduction system (isolated from main DG chamber), up to 1.50 M exhaust piping (with LRB insulation & Alum. cladding ) as required .Diesel engine should have Precise emission control by treatment with Diesel exhaust fluid (DEF)/Aqueous urea tank (above 82.5 KVA) as per CPCB 4+ norms |
| 23 | B) Alternator : AC Brush less SPDP Synchronous alternator rated of appropriate KVA, 415 volts at 1500 rpm, 3 phase, 50 Hz, ac supply with 0.8 lagging power factor. Alternator conforming to BS 5000 (part 99) or IS/IEC 60034-1. . Alternator shall be self regulated with standard Alternator Protection( Over voltage , over speed & under voltage, under speed warning & shutdown). |
| 24 | C) Canopy : CPCB / ARAI approved Standard canopy with Weatherproof, powder coated Accoustic enclosure for DG set for sound attenuation fabricated from CRCA sheet steel (structure) including sidewals & filled with glasswool (96Kg/m3) /PU Foam. as per IS8183 and the thickness of the doors should be 28/40/50/85 mm as per rating . All doors/opening are sealed with neoprene /EPDN gaskets. The DG Set has Inbuilt / External in fuel tank to run 6 to 8 Hrs along with DEF tank (as per OEM standards). There should be provision of protection and tripping of DG set for temperature greater than 50 degree centigrade. The enclosure should be suitable for following capacity DG sets and alternator. Noise level shall be less than 75 dB at a distance of 1 Mtrs. in open free field environment as per ISO 8528 part 10 duly certified by authorised agency etc. |
| 25 | D) Instruments : Electronic / Mechanical governor, Manual & electric Start ,Batteries with battery charger, Electronic fuel system, advanced after treatment system (ATS), Exhaust gas recirculation(EGR) System along with Diesel oxidation catalyst(DOC) and Selective catalytic reduction (SCR) , supply module and DCU to control and monitor DEF. Engine instruments panel should have microprocessor based Genset monitoring system capable of displaying Running Hour, RPM, lubbrication oil pressure indication, lubrication oil temperature, battery charging indication, overspeed indication, fuel level etc. The control Panel should equipped with MCCB/ACB of suitable rating. |
| 26 | E) Base frame and foundation : Both the engine and alternator shall be mounted on suitable base frame made of MS channel & coupled through a flexible coupling or close coupled which shall be installed on existing cement concrete foundation and vibration isolation arrangements as per recommendation of manufacturer. |
| 27 | F) First filling of the FUEL Tank and DEF tank shall be done by contractor. |
| 28 | G) DG set will be offered for Inspection and Testing at OEM's Works ( as per approved QAP ) in presence of Departmental Engineers .In case of 13 hour running testing at OEM's works, cost of actual consumables will be reimbursed. |
| 29 | Note: 1. During the DLP, the contractor shall arrange for servicing of the DG set through authorized dealer of OEM, as per the manufacturers guidelines. The actual cost of consumables used during servicing will be reimbursed to the contractor by the end user department.2. Manufacturer / OEM must have its authorized service dealer in Rajasthan. Which can provide service within 6 Hours of compalint registration. |
| 30 | 40 KVA at 0.8 pf 415V 50Hz 3-ǿ with 2 Cylinder Engine Please Enable Macros to View BoQ information |