Agartala Municipality Corporation has published Tender For Construction Of Cover Drain At 6 Igm Lane From Tripura Times To Singh Para Under Ward No-32. Submission Date for this Tender is 11-11-2022. Drainage Tenders in agartala Tripura. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Cleaning and excavation of slush/ liquid soil, silt etc. from the existing drain bed in/cl. Required lift and lead directly to Hapania dumping ground or any other suitable place by mechanical means as per direction of Engineer in charge. (A/R) |
2 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. -All kinds of soil |
3 | Providing and laying dry flat brick flooring in required pattern complete. |
4 | Supplying and filling in plinth, under floor, foundations etc. with sand (fine) from local quarry with all lifts including spreading in horizontal layers, watering, grading to required slope, ramming, consolidating and compacting each layer by using plate compactor or by any suitable method complete. |
5 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering -All work upto plinth level: -1:3:6 ( 1 Cement: 3 fine sand : 6 graded well burnt brick aggregate 20 mm nominal size) |
6 | First class brick work in foundation and plinth including cost of all materials as required complete:-In cement mortar 1:4 ( 1 cement : 4 fine sand ). |
7 | 12 mm cement plaster in single layer including cost of materials required and finishing even and smooth and curing complete. In cement morter 1:5 (1 cement :5 fine sand) |
8 | Neat cement punning. |
9 | Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centring, shuttering, finishing and reinforcement- All work up to plinth level 1:1½:3 ( 1 Cement: 1½ fine sand : 3 graded stone aggregate 20 mm nominal size) |
10 | Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto floor five level. Thermo-Mechanically Treated bars/ Cold twisted deformed steel bars |
11 | Centering shuttering including struttings, propping etc. and removal of form work for: Foundations, footings, bases for columns etc. for mass concrete with timber plank |
12 | Steel work welded in built up section/framed work including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using steel etc. complete as required: In grating, frames, guard bar, railing, brackets, gates and similar works, all complete. |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy
For Tender Information Services Visit : TenderDetail