Fabricating 01 No. Water Tank Body From Dump Body Of Bh100 Dumper And Installation Of Pump Motor Combination With Necessary Water Pipe Connection At Block-B Project , singrauli-Madhya Pradesh

Northern Coalfields Limited-NCL has published Fabricating 01 No. Water Tank Body From Dump Body Of Bh100 Dumper And Installation Of Pump Motor Combination With Necessary Water Pipe Connection At Block-B Project . Submission Date for this Tender is 03-10-2022. Water Tank Tenders in singrauli Madhya Pradesh. Bidders can get complete Tender details and download the document.




Tender Notice

34052395
Fabricating 01 No. Water Tank Body From Dump Body Of Bh100 Dumper And Installation Of Pump Motor Combination With Necessary Water Pipe Connection At Block-B Project
Open Tender
Indian
Madhya Pradesh
singrauli
03-10-2022

Tender Details

Fabricating 01 No. Water Tank Body From Dump Body Of Bh100 Dumper And Installation Of Pump Motor Combination With Necessary Water Pipe Connection At Block-B Project

Key Value

Document Fees
Refer document
EMD
INR 3420.0 /-
Tender Value
INR 2.72 Lakhs /-

BOQ Items

Name of the Work / Contract No:
Sl. No. Item Description
1Scope of Job: 1. Removal of Dump Body from Dumper 2. Cleaning of Dump body 3. Cutting of MS Plates as per required size 4. Welding of plates in the Dump body to make different compartments 5. Painting of compartments 6. Mounting of tanker body 7. Fabrication of Pipe line network as desired 8. Installation of Pump-Motor Assembly 9. Connecting all pipelines 10. Painting of full Dumper 11. Testing of the sprinkling system by water filling. Terms & Conditions: 1. Work to be carried out at company workshop 2. All safety materials required during job are to be provided by the party 3. No child labour will be engaged in the job Material to be provided by company: 1. MS plate 10mm size as per requirement 2. MS Angle 75 X 75 X 6 mm as per requirement 3. GI Pipe 25 Metre, 4 mm thickness 4. Crane when required 5. DA & Oxygen gas
2Cleaning of Dump body by wire brush, cutting of uneven steel material, Area 341.25 Sqft including skilled welder 03 men X 02 shifts X 03 days, unskilled 03 men X 02 shifts X 03 days with CMPF/EPF, contractor"s profit on labour charges @10% & grinding of surface by grinding machine approx. 24 hours
3Fabrication of tank body chamber, cutting of plates as per below sizes (in feet) 16.25 X 3.25 - 01 no. 16.25 X 3.50 - 01 no. 16.25 X 5.00 - 01 no. 7.50 X 3.25 - 03 nos. 7.50 X 2.25 - 03 nos. including skilled welder 02 men X 02 shifts X 02 days, unskilled 02 men X 02 shifts X 02 days with CMPF/EPF, contractor"s profit on labour charges
4Making of V groove by gas cutting including skilled welder 02 men X 02 shifts X 03 days, unskilled 02 men X 02 shifts X 03 days with CMPF/EPF, contractor"s profit on labour charges
5Complete welding of chamber plate by 4mm electrodes 7016 & total cover 268.96 Sqft = 8199.12 Sqmm, Total welding deposit = 0.0078 X 1.2 X 8199 cm = 76 Kg (65% deposit efficiency = 118 Kg) including skiled welder 02 Men X 02 shifts X 06 days, unskilled 02 men X 02 shifts X 06 days with CMPF/EPF, contractor"s profit on labour charges
6Fabrication of & installation of Sprinkler unit containing valve & GI pipe, drilling of 6 mm dia holes on pipe size 6 metres length X 4 inch dia (920 holes approx.) including drill machining charges with drill bit for 23 mandays and cost of manpower including skilled fitter 01 man X 01 shift X 23 days, unskilled 01 man X 01 shift X 23 days (drilling @5 holes per hour per shift =40 holes) with CMPF/EPF, contractor"s profit on labour charges
7Fabrication & Alignment of bed plate for installation of pump & motor station including skilled fitter 01 man X 02 shifts X 05 days, skilled welder 01 man X 02 shifts X 05 days, unskilled 02 men X 02 shifts X 05 dayswith CMPF/EPF, contractor"s profit on labour charges
8Painting of tank body approx. 1018.20 Sqft
9Painting of complete machine with green paint, environment friendly approx. 1506.94 Sqft
10Dump body removal from chassis including skilled fitter 02 men X 02 shift X 02 days, unskilled 02 men X 02 shifts X 02 days with CMPF/EPF, contractor"s profit on labour charges
11Mounting of Dump body on the chassis including skilled fitter 02 men X 02 shift X 02 days, unskilled 02 men X 02 shifts X 02 days with CMPF/EPF, contractor"s profit on labour charges
12Hiring of two nos welding machines alongwith welding accessories, gas cutting set for 25 days, 02 shifts = 50 Mandays
13Cost of electrodes approx. 110 Kgs and Supervisor for 24 Mandays with CMPF/EPF, contractor"s profit on labour charges
14Total impact of GST for the purpose of CTC
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail