Northern Coalfields Limited-NCL has published Fabricating 01 No. Water Tank Body From Dump Body Of Bh100 Dumper And Installation Of Pump Motor Combination With Necessary Water Pipe Connection At Block-B Project . Submission Date for this Tender is 03-10-2022. Water Tank Tenders in singrauli Madhya Pradesh. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Scope of Job: 1. Removal of Dump Body from Dumper 2. Cleaning of Dump body 3. Cutting of MS Plates as per required size 4. Welding of plates in the Dump body to make different compartments 5. Painting of compartments 6. Mounting of tanker body 7. Fabrication of Pipe line network as desired 8. Installation of Pump-Motor Assembly 9. Connecting all pipelines 10. Painting of full Dumper 11. Testing of the sprinkling system by water filling. Terms & Conditions: 1. Work to be carried out at company workshop 2. All safety materials required during job are to be provided by the party 3. No child labour will be engaged in the job Material to be provided by company: 1. MS plate 10mm size as per requirement 2. MS Angle 75 X 75 X 6 mm as per requirement 3. GI Pipe 25 Metre, 4 mm thickness 4. Crane when required 5. DA & Oxygen gas |
2 | Cleaning of Dump body by wire brush, cutting of uneven steel material, Area 341.25 Sqft including skilled welder 03 men X 02 shifts X 03 days, unskilled 03 men X 02 shifts X 03 days with CMPF/EPF, contractor"s profit on labour charges @10% & grinding of surface by grinding machine approx. 24 hours |
3 | Fabrication of tank body chamber, cutting of plates as per below sizes (in feet) 16.25 X 3.25 - 01 no. 16.25 X 3.50 - 01 no. 16.25 X 5.00 - 01 no. 7.50 X 3.25 - 03 nos. 7.50 X 2.25 - 03 nos. including skilled welder 02 men X 02 shifts X 02 days, unskilled 02 men X 02 shifts X 02 days with CMPF/EPF, contractor"s profit on labour charges |
4 | Making of V groove by gas cutting including skilled welder 02 men X 02 shifts X 03 days, unskilled 02 men X 02 shifts X 03 days with CMPF/EPF, contractor"s profit on labour charges |
5 | Complete welding of chamber plate by 4mm electrodes 7016 & total cover 268.96 Sqft = 8199.12 Sqmm, Total welding deposit = 0.0078 X 1.2 X 8199 cm = 76 Kg (65% deposit efficiency = 118 Kg) including skiled welder 02 Men X 02 shifts X 06 days, unskilled 02 men X 02 shifts X 06 days with CMPF/EPF, contractor"s profit on labour charges |
6 | Fabrication of & installation of Sprinkler unit containing valve & GI pipe, drilling of 6 mm dia holes on pipe size 6 metres length X 4 inch dia (920 holes approx.) including drill machining charges with drill bit for 23 mandays and cost of manpower including skilled fitter 01 man X 01 shift X 23 days, unskilled 01 man X 01 shift X 23 days (drilling @5 holes per hour per shift =40 holes) with CMPF/EPF, contractor"s profit on labour charges |
7 | Fabrication & Alignment of bed plate for installation of pump & motor station including skilled fitter 01 man X 02 shifts X 05 days, skilled welder 01 man X 02 shifts X 05 days, unskilled 02 men X 02 shifts X 05 dayswith CMPF/EPF, contractor"s profit on labour charges |
8 | Painting of tank body approx. 1018.20 Sqft |
9 | Painting of complete machine with green paint, environment friendly approx. 1506.94 Sqft |
10 | Dump body removal from chassis including skilled fitter 02 men X 02 shift X 02 days, unskilled 02 men X 02 shifts X 02 days with CMPF/EPF, contractor"s profit on labour charges |
11 | Mounting of Dump body on the chassis including skilled fitter 02 men X 02 shift X 02 days, unskilled 02 men X 02 shifts X 02 days with CMPF/EPF, contractor"s profit on labour charges |
12 | Hiring of two nos welding machines alongwith welding accessories, gas cutting set for 25 days, 02 shifts = 50 Mandays |
13 | Cost of electrodes approx. 110 Kgs and Supervisor for 24 Mandays with CMPF/EPF, contractor"s profit on labour charges |
14 | Total impact of GST for the purpose of CTC |