Shifting Of 33 Kv And Overhead And Underground Lines At Ganga X Press Way On Row In The Area Of Edd Iv Meerut, Meerut-Uttar Pradesh

Paschimanchal Vidyut Vitran Nigam Limited has published Shifting Of 33 Kv And Overhead And Underground Lines At Ganga X Press Way On Row In The Area Of Edd Iv Meerut. Submission Date for this Tender is 10-12-2021. Transmission Line Tenders in Meerut Uttar Pradesh. Bidders can get complete Tender details and download the document.




Tender Notice

30144655
Corrigendum : Shifting Of 33 Kv And Overhead And Underground Lines At Ganga X Press Way On Row In The Area Of Edd Iv Meerut
Open Tender
Indian
Uttar Pradesh
Meerut
10-12-2021

Tender Details

Shifting Of 33 Kv And Overhead And Underground Lines At Ganga X Press Way On Row In The Area Of Edd Iv Meerut

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 04-Dec-2021 TENDER NO. 98/2021-22 Other 10-12-2021

Key Value

Document Fees
INR 5900 /-
EMD
INR 300000.0 /-
Tender Value
INR 3 Crore /-

BOQ Items

Name of Work: Shifting of 33 KV & Overhead/Underground Lines at Ganga X-press Way on ROW in the area of EDD-IV, Meerut
Sl. No. Item Description
1PART-A (SHIFTING OF 33 KV LINE)
2Cartage of following material from store center Meerut to JE Store including loading & unloading at both ends maximum distance up to 40 Km. :-
3ST Pole 13 Mtr. Long.
4Line material such as MS Channel 125x65x3200 forTop 5 Nos. + 100x500x2600 Dropper25 Nos.) 33 KV V Type Cross arms (09 no.), 33 KV pin insulator (100 No.), 33 KV Disc insulator (90 No.) Disc fitting (90 No.), T-Off channel 100x50x13 (09 No.), MS Flat iron (90 kg), Flat chennel iron (250 Kg.), Guarding cross arm (156 No.), Stay set Complete (100 No.), ACSR dog conductor (2200 mtr.), GI Wire 6/ 8 SWG(80+900 Kg.), MS angle iron (04 no.), Armour Rod (12 Set), 33 KV Cable Jointing Kit (08 No.)CableJointing Kit StraightThrough 04 No), Disc insulator for stay (100 No.), MS angle pole support stay (20 No.), Earthing rod complete(19 No.), Aluminim binding wire 6-SWG(80 kg.), GI wire 6-SWG(790 kg), Barbed wire (800 kg), Pipe joint coupler (74 No.)
533 KV XLPE Cable 3x300 sq.mm
6Cartage of following material from JE, Store to site of work on day to day basis as per requirement of site ( including loading & unloading at both ends maximum distance up to 10-15 Km.) :-
7ST Pole 13 Mtr. Long.
8Line material such as MS Channel 125x65x3200 forTop 5 Nos. + 100x500x2600 Dropper25 Nos.) 33 KV V Type Cross arms (09 no.), 33 KV pin insulator (100 No.), 33 KV Disc insulator (90 No.) Disc fitting (90 No.), T-Off channel 100x50x13 (09 No.), MS Flat iron (90 kg), Flat chennel iron (250 Kg.), Guarding cross arm (156 No.), Stay set Complete (100 No.), ACSR dog conductor (2200 mtr.), GI Wire 6/ 8 SWG(80+900 Kg.), MS angle iron (04 no.), Armour Rod (12 Set), 33 KV Cable Jointing Kit (08 No.)CableJointing Kit StraightThrough 04 No), Disc insulator for stay (100 No.), MS angle pole support stay (20 No.), Earthing rod complete(19 No.), Aluminim binding wire 6-SWG(80 kg.), GI wire 6-SWG(790 kg), Barbed wire (800 kg), Pipe joint coupler (74 No.)
933 KV XLPE Cable 3x300 sq.mm
10Erection of Four Pole 13 mtr long after digging a pit of size 1.20 x 0.60 x 1.6 mtr in all type of Soil by providing of stone pad including back filling of the pole with proper ramming after completion of work.
11Fabrication and fixing of Four pole suitable for 33 KV line accessories Complete.
12Erection of Double Pole 13 mtr long after digging a pit of size 1.20 x 0.60 x 1.6 mtr in all type of Soil by providing of stone pad including Fabrication and fixing of double pole suitable for 33 KV line accessories Complete.
13Erection of Single Pole 13 mtr long after digging a pit of size 1.20 x 0.60 x 1.6 mtr in all type of Soil by providing of stone pad including back filling of the pole with proper ramming after completion of work.
14Fabrication and fixing of Single pole suitable for 33 KV line accessories Complete.
15Grouting of ST Pole 13 mtr. Long as per respo norms
16Laying lifting stringing of proper sagging of ACSR Dog conductor for 3 phase, 3 wire 33 KV line including binding & jumpering properly.
17Stay Set complete for 33 KV line
18Grouting of stay rod with BB concreating in ratio 1:4:8 in block of size 0.30x0.30x0.6 mtr as per RESPO.
19Fixing of MS angle pole support stay
20Fabrication and fixing of Gaurding angle of 33 KV Line size MS angle 65x65x6 mm. (1.6 mtr. long)/Other angles
21Guarding of line with G.I. wire having 2 no. horizontal wire & 3 Mtr distance of laces of 6 SWG/8 SWG G.I. wire complete work in all respect.
22Providing & fixing of HDPE pipe 6"" dia. for laying of underground 33 KV XLPE 3x300 sq.mm.. cable complete work in all respect
23Laying of 33 KV XLPE 3x300 Sq.mm. cable across in HDPE pipe 6"" dia. complete work in all respect
24Providing & fixing of G.I. pipe 6"" dia.( supporting for cable for DP 24 Mtr. each)
25Making a section pole to exist pole after fabrication & fixing of T channel with fixing of all 33 KV accessories.
26Earthing of each 33 KV line Pole after drive of electrodes of size 20mm x 250 mm and connection the earthing point with GI wire.
27Dissmentling of ST pole/R.S. Joist by digging the pits & removal of complete 33 KV line accessories.
28Removal of ACSR Dog Conductor after opening the binding and making coil properly
29Sundry item :- Cutting & chopping tree branches near side of line for making the clearance between line and tree.
30Laying of 33 KV XLPE cable & making loop
31Fixing the cable jointing kit with the end of XLPE cable including mounting the same on pole with proper binding.
32Fixing of straight through cable jointing kit.
33Providing and fixing of stay clamps.
34Providing and fixing of Earth wire clamp.
35Providing and fixing of Eye bolt 12x100 sq.mm.
36Providing and fixing of Holding clamp suitable for T-off channel
37Providing and fixing of Cross arm Holding clamp.
38Providing and fixing F-Bracket for 33 KV
39Providing and fixing E-Bracket for 33 KV
40Providing and fixing of Holding clamps.
41Providing and fixing of Bolt and Nuts.
42Providing and fixing of PG Clamp for dog conductor
43Providing and fixing of Number Plate with clamp
44Providing and fixing of Danger Plate with clamp
45Providing and fixing of Barbed wire
46Providing & painting of Red oxide
47Providing & painting of aluminium paint
48Providing & fixing of pipe jointing coupler
49Providing & fixing of HT tape
50Providing & fixing of Empire tape
51Providing & fixing of Aluminum tape
52Providing & fixing of Aluminum Jointing Sleeves
53Providing & fixing of HOT deep galvanized cable support clamp for 300 sq.mm. 3 core cable
54Back cartage from site of work to JE store/Dump Site including loading & unloading at both ends:-
55A) ST Pole/R.S Joist from work site central to store meerut
56B) Line material such as ACSR dog conductor (15000 mtr.), 33 KV V type cross arm (45 no.), MS Channel Top/Droper/Brasing LS scrap (234 Kg), 33 KV Pin insulator with pin (290 no.), Disc insulator (100 No.), Disc fitting (84 No.)
57Back cartage from JE store/Dump Site to Central Store Meerut including loading & unloading at both ends:-
58A) ST Pole/R.S Joist from work site central to store meerut
59B) Line material such as ACSR dog conductor (15000 mtr.), 33 KV V type cross arm (45 no.), MS Channel Top/Droper/Brasing LS scrap (234 Kg), 33 KV Pin insulator with pin (290 no.), Disc insulator (100 No.), Disc fitting (84 No.)
60PART-B (SHIFTING OF 11 KV LINE)
61Cartage of following material from store center Meerut to JE Store including loading & unloading at both ends maximum distance up to 40 Km. :-
62ST Pole 11 Mtr. Long.
63Line material such as MS Channel 125x65x6x1300 for T-off channel (20 Nos.) + 100x50x2600 Dropper(163 Nos.) + 125x65x2240 for Top channel (241 Nos.) + 125x65x3200 with Clamp for Top (245 Nos.), MS angle 75x75x6x2028 pipe angle(15 No.)+ 65x75x6x2028 TF Base (15 No.) + 65x65x6x2700 for Brassing (39 set), X-arm V type (70 No.), Guarding angle X arm (70 No.), Guarding channel clamp (102 No.), G.I. Thimble (41 No.), 11 KV pin insulator with pin (1100 No.), 11 KV disc insulator T&C type (430 No.), 11 KV disc fitting (430 Kg.), 11 KV disc insulator B&S type (20 No.), 11 KV disc fitting B&S type (20 No.), Stay set Complete (296 No.), ACSR dog conductor (18600 mtr.), 11 KV lightening aresstor (11 no.), 11KV TPMO (11 no.), 11 KV Fuse Set (11 No.), 11 KV cable jointing kit outdoor box (685 no.), 11 KV cable jointing kit straight through (28 No.), MS Earthing Rod complete (192 No.)
6411 KV XLPE Cable 3x185 sq.mm
65Cartage of following material from JE, Store to site of work on day to day basis as per requirement of site ( including loading & unloading at both ends maximum distance up to 10-15 Km.) :-
66ST Pole 11 Mtr. Long.
67Line material such as MS Channel 125x65x6x1300 for T-off channel (20 Nos.) + 100x50x2600 Dropper(163 Nos.) + 125x65x2240 for Top channel (241 Nos.) + 125x65x3200 with Clamp for Top (245 Nos.), MS angle 75x75x6x2028 pipe angle(15 No.)+ 65x75x6x2028 TF Base (15 No.) + 65x65x6x2700 for Brassing (39 set), X-arm V type (70 No.), Guarding angle X arm (70 No.), Guarding channel clamp (102 No.), G.I. Thimble (41 No.), 11 KV pin insulator with pin (1100 No.), 11 KV disc insulator T&C type (430 No.), 11 KV disc fitting (430 Kg.), 11 KV disc insulator B&S type (20 No.), 11 KV disc fitting B&S type (20 No.), Stay set Complete (296 No.), ACSR dog conductor (18600 mtr.), 11 KV lightening aresstor (11 no.), 11KV TPMO (11 no.), 11 KV Fuse Set (11 No.), 11 KV cable jointing kit outdoor box (685 no.), 11 KV cable jointing kit straight through (28 No.), MS Earthing Rod complete (192 No.)
6811 KV XLPE Cable 3x185 sq.mm
69Erection of Double Pole 11 mtr long after digging a pit of size 1.20 x 0.60 x 1.6 mtr in all type of Soil by providing of stone pad including Fabrication and fixing of Top/Droper/Base channel on double pole suitable for all 11 KV line accessories Complete.
70Fixing of TPMO on newly constructed double pole
71Fixing Fuse Set on newly constructed double pole
72Erection of Single Pole 11 mtr long after digging a pit of size 1.20 x 0.60 x 1.6 mtr in all type of Soil by providing of stone pad including back filling of the pole with proper ramming after completion of work.
73Fabrication and fixing of Single pole suitable for 11 KV line accessories Complete.
74Fabrication and fixing of V type X arm
75Grouting of ST Pole 11 mtr. Long
76Earthing of each 11 KV line Pole after drive of electrodes of size 20mm x 250 mm and connection the earthing point with GI wire.
77Laying lifting stringing of proper sagging of ACSR Dog conductor for 3 phase, 3 wire 11 KV line including binding & jumpering properly.
78Stay Set complete for 11 KV line alongwith fixing of 11 kv disc insulator
79Extra stay for angle location alongwith conecreating
80Providing & fixing of HDPE pipe 6"" dia. for laying of underground 11 KV XLPE 3x185 sq.mm.. cable complete work in all respect
81Providing & fixing of G.I. pipe 6"" dia.( supporting for cable for DP 24 Mtr. each)
82Laying of 11 KV XLPE 3x185 Sq.mm. cable across in HDPE pipe 6"" dia. complete work in all respect
83Laying of 11 KV XLPE 3x185 Sq.mm. cable other then under ground cable
84Re-installing of old 25/63 KVA T/f as follows
85Dismentling and dismounting of 25/63 KVA T/F with the help of Chain pully block
86Shifting and cartage of 25/63 KVA T/F from work site to Safe side with loading and unloding etc and back cartage to the newly proposed double pole side
87Mounting/Installation on the newly errected double pole 25/63 KVA T/F with the help of chain pulley block
88Re-installing of old 100/250 KVA T/f as follows
89Dismentling and dismounting of 100/250 KVA T/F with the help of Crain
90Shifting and cartage of 100/250 KVA T/F from work site to Safe side with loading and unloding etc and back cartage to the newly proposed double pole side
91Mounting/Installation on the newly errected double pole 100/250 KVA T/F with the help of Crain
92Water level earthing
93Dissmentling of ST pole/R.S. Joist by digging the pits & removal of complete 11 KV line accessories.
94Removal of ACSR Dog Conductor after opening the binding and making coil properly
95Removal of V type X arm
96Removal of MS Channel & Angle, (Top/Dropper/Base)
97Removal of 11 KV Pin Insulator with Pin
98Removal of 11 KV Disc Insulator with fitting
99Guarding of line with G.I. wire having 2 no. horizontal wire & 3 Mtr distance of laces of 6 SWG/8 SWG G.I. wire complete work in all respect.
100Providing and fixing of Guarding channel clamp
101Providing and fixing of MS clamp suitable for T-off channel
102Providing & fixing of Aluminum Jointing Sleeves
103Providing and fixing of MS clamp suitable for V type X arm
104Providing and fixing F-Bracket for 11 KV
105Providing and fixing E-Bracket for 11 KV
106Providing and fixing of Holding clamp suitable for Top Channel/TPMO/Fuse set off size
107Providing and fixing of MS clamp with Nut & Bolt
108Providing & fixing of Aluminum tape
109Providing & fixing of Empire tape
110Providing & fixing of IIT tape
111Providing & fixing of Fuse wire 16 SWG
112Providing & fixing of Fuse wire 18 SWG
113Providing and fixing of Earth wire clamp.
114Providing and fixing of PG Clamp for dog conductor
115Providing and fixing of Eye bolt 12x100 sq.mm.
116Providing and fixing of Bolt and Nuts.
117Providing and fixing of Danger Plate with clamp
118Providing and fixing of Number Plate with clamp
119Providing and fixing of Barbed wire
120Providing & painting of Red oxide
121Providing & painting of aluminium paint
122Providing and fixing of aluminium lugs long barrel, off size
123Providing and fixing of copper L piece
124Providing and fixing of Earthing strip
125Providing & fixing of pipe jointing coupler
126Back cartage from site of work to JE store/Dump Site including loading & unloading at both ends:-
127A) ST Pole/R.S Joist from work site central to store meerut
128B) Line material such as ACSR weasel conductor (8100 mtr.), 11 KV V type cross arm (150 no.), MS Channel Top/Droper/Brasing LS scrap (400 Kg), 11 KV Pin insulator with pin (56 no.), Disc insulator with fitting (78 No.)
129Back cartage from JE store/Dump Site to Central Store Meerut including loading & unloading at both ends:-
130A) ST Pole/R.S Joist from work site central to store meerut
131B) Line material such as ACSR weasel conductor (8100 mtr.), 11 KV V type cross arm (150 no.), MS Channel Top/Droper/Brasing LS scrap (400 Kg), 11 KV Pin insulator with pin (56 no.), Disc insulator with fitting (78 No.)
132PART-C (SHIFTING OF LT LINE)
133Cartage of following material from store center Meerut to JE Store including loading & unloading at both ends maximum distance up to 40 Km. :-
134PCC pole 9 Mtr. Long.
135Line material such as Cable LT ABC 3x120-1x95+1x16 mm. (1560 mtr.), AL lugs long Barrel of size(90 No.), Dead & clamp with i-hook (47 No.), Suspension clamp with I-hook (81 No.), Distribution Box I phase (30 No.), Distribution Box 3 phase (21 No.), Ms chanel 100x50x2240 for Top (10 Nos.) + 100x50x2240 Dropper(72 Nos.) MS angle 75x75x6x2028 supporting (32 No.)+ 65x75x6 mm bracing (32 No.), LT piercing connector for size 120/95 (112 No.) + size 120/35 (100 No.) + size 95/50 (100 No.) + size 95/95/50 (100 N0.) + size 95/50/35 (100 No.), PG Clamp for neutral charding (201 No.), Ms Flat iron (200 Kg.), Stone pad (145 No.), Stay set Complete (110 No.), ACSR weasel conductor (1560 mtr.), Aluminum Binding wire (212 Kg.), Neutral Cum earth wire (76 Kg.),
136LT XLPE Cable 3.5x240 sq.mm
137Cartage of following material from JE, Store to site of work on day to day basis as per requirement of site ( including loading & unloading at both ends maximum distance up to 10-15 Km.) :-
138PCC pole 9 Mtr. Long.
139Line material such as Cable LT ABC 3x120-1x95+1x16 mm. (1560 mtr.), AL lugs long Barrel of size(90 No.), Dead & clamp with i-hook (47 No.), Suspension clamp with I-hook (81 No.), Distribution Box I phase (30 No.), Distribution Box 3 phase (21 No.), Ms chanel 100x50x2240 for Top (10 Nos.) + 100x50x2240 Dropper(72 Nos.) MS angle 75x75x6x2028 supporting (32 No.)+ 65x75x6 mm bracing (32 No.), LT piercing connector for size 120/95 (112 No.) + size 120/35 (100 No.) + size 95/50 (100 No.) + size 95/95/50 (100 N0.) + size 95/50/35 (100 No.), PG Clamp for neutral charding (201 No.), Ms Flat iron (200 Kg.), Stone pad (145 No.), Stay set Complete (110 No.), ACSR weasel conductor (1560 mtr.), Aluminum Binding wire (212 Kg.), Neutral Cum earth wire (76 Kg.),
140LT XLPE Cable 3.5x240 sq.mm
141Erection of Single Pole 9 mtr long after digging a pit of size 1.20 x 0.60 x 1.6 mtr in all type of Soil by providing of stone pad including back filling of the pole with proper ramming after completion of work.
142Fabrication and fixing of Single pole suitable for LT line accessories Complete.
143Earthing of each Lt line Pole after drive of electrodes if size 20mm x 250 mm and connection the earthing point with GL wire.
144Laying lifting stringing of proper sagging of ACSR weasel conductor for 3 phase, 3 wire LT line including binding & jumpering properly.
145Stay Set complete for LT line alongwith Concreating and fixing of LT disc insulator
146Extra stay for angle location alongwith conecreating
147Providing & fixing of GI pipe 6"" dia. for laying of underground LT XLPE 3.5x240 sq.mm. cable complete work in all respect
148Providing & fixing of H.D.P.E pipe 6"" dia.( supporting for cable for DP 24 Mtr. each)
149Laying of LT XLPE 3.5x240 sq.mm. cable other then under ground cable
150Grouting of ST pole in BB concreting ratio 1:4:8 in block of size 0.45x0.45x1.6 mtr.
151Dissmentling of ST pole/R.S. Joist by digging the pits & removal of complete LT KV line accessories.
152Removal of ACSR weasel Conductor after opening the binding and making coil properly
153Removal of I-hook clamp
154Removal of Dead & clamp
155Removal of Suspension clamp
156Providing and fixing of Holding clamp
157Providing and fixing of Nut & Bolt off size
158Providing & painting of Red oxide
159Providing & painting of aluminium paint
160Providing & fixing of pipe jointing coupler
161Providing & fixing of HT tape
162Providing & fixing of Empire tape
163Providing & fixing of Aluminum tape
164Providing and fixing of Earth wire clamp.
165Providing and fixing of PVC Tape.
166Providing and fixing of J-Hook
167Providing and fixing of Dead & clamp
168Providing and fixing of Suspension clamp
169Providing and fixing of Loop guard
170Providing and fixing of Spacer LT PVC
171Back cartage from site of work to JE store/Dump Site including loading & unloading at both ends:-
172A) ST Pole/R.S Joist from work site central to store meerut
173B) Line material such as ACSR weasel conductor (3000 mtr.), I-hook clamp (20 no.), Dead & Clamp (20 no.), Suspension Clamp (250 no.)
174Back cartage from JE store/Dump Site to Central Store Meerut including loading & unloading at both ends:-
175A) ST Pole/R.S Joist from work site central to store meerut
176B) Line material such as ACSR weasel conductor (3000 mtr.), I-hook clamp (20 no.), Dead & Clamp (20 no.), Suspension Clamp (250 no.)
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail