National Aluminium Company Limited-NALCO has published Maintenance Of Pcu Equipments And Ash Slurry Header Of Amd . . Submission Date for this Tender is 19-07-2021. Spare Part Tenders in CPP, NALCO, ANGUL Odisha. Bidders can get complete Tender details and download the document.
Name of Work: MAINTENANCE OF PCU EQUIPMENTS AND ASH SLURRY HEADER OF AMD. | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Dismantling and fitting of dummy/ throug | 75 | each | |
2 | 2 | Removal and/ fixing of clamps 350/320NB | 20 | each | |
3 | 3 | Anchoring of pipes | 100 | Meter | |
4 | 4 | Sleeve coupling leakage attending | 250 | each | |
5 | 5 | Repair/replacement of Tee/Bend/Reducer/Y | 100 | each | |
6 | 6 | Removal/dismantling of pipes 350/320NB | 3400 | Meter | |
7 | 7 | Erection of pipes 350/320NB | 2400 | Meter | |
8 | 8 | Painting | 1000 | Square meter | |
9 | 9 | Gas cutting | 700 | Meter | |
10 | 10 | But welding | 700 | Meter | |
11 | 11 | Asst. in thickness measurement | 120000 | Meter | |
12 | 12 | Febrication of MS Bend/Tee/Reducer | 30 | each | |
13 | 13 | Attending AWR (900mm) leakage | 5 | each | |
14 | 14 | Fabrication /Erection MS and other pipe | 500 | Meter | |
15 | 15 | Removal/Dismantling of MS and other pipe | 500 | Meter | |
16 | 16 | Closing /Opening of knife edge gate valv | 750 | each | |
17 | 17 | Erection of Cast Basalt line pipe 350NB | 150 | each | |
18 | 18 | O/H of Vertical Turbine pump | 3 | each | |
19 | 19 | O/H of Horizontal centrifugal pumps | 12 | each | |
20 | 20 | O/H of Chemical dosing pump | 12 | each | |
21 | 21 | O/H of slurry pump | 4 | each | |
22 | 22 | O/H of flush mixture/ Sludge sump agitat | 4 | each | |
23 | 23 | O/H of Alum Agitator | 6 | each | |
24 | 24 | O/H of lime/ poly agitator | 12 | each | |
25 | 25 | Turbo circulator wheel alignment/ replac | 4 | each | |
26 | 26 | Turbo circulator wheel bearing replaceme | 4 | each | |
27 | 27 | Turbo circulator gear box repaire/ repla | 2 | each | |
28 | 28 | O/H & load testing of 1ton/5ton hoist/cr | 4 | each | |
29 | 29 | O/H & Replacemnt of butterfly valve 500m | 2 | each | |
30 | 30 | O/H & Replacement of Butterfly valve 350 | 2 | each | |
31 | 31 | O/H & Replacement of Butterfly valve 300 | 6 | each | |
32 | 32 | O/H & Replacement butterfly valve 200/15 | 30 | each | |
33 | 33 | O/H of Gate valve 350/300/250mm | 10 | each | |
34 | 34 | O/H of Gate valve 200/150/100mm | 20 | each | |
35 | 35 | Repl. of gate valve of all sizes | 50 | each | |
36 | 36 | O/H of sluice gate of all sizes | 4 | each | |
37 | 37 | Repl. of diaphragm valve 25/40/50/ | 10 | each | |
38 | 38 | O/H of diaphragm valve 25/40/50 | 10 | each | |
39 | 39 | Replacement/O/H of AIR release valve | 4 | each | |
40 | 40 | Erection of moving equipment | 10 | Metric Tonne | |
41 | 41 | Erection of stastic equipment | 10 | Metric Tonne | |
42 | 42 | Dismantling of moving Equipment | 5 | Metric Tonne | |
43 | 43 | Dismantling of stastic Equipment | 5 | Metric Tonne | |
44 | 44 | SS welding | 3.08 | Meter | |
45 | 45 | Erection of scaffolding | 30 | Meter | |
46 | 46 | Oil seal replacement of gear box/ pump | 10 | each | |
47 | 47 | PM of Recycle pump | 24 | each | |
48 | 48 | PM of Horizontal pumps | 24 | each | |
49 | 49 | PM of Screw pumps | 12 | each | |
50 | 50 | PM of chemical pumps | 36 | each | |
51 | 51 | PM of service pumps | 4 | each | |
52 | 52 | PM of Stirrer/ Agitator | 96 | each | |
53 | 53 | PM of Turbocirculator | 6 | each | |
54 | 54 | Attending gland leakage of pump/ valves | 30 | each | |
55 | 55 | PM of 1 t/5t Hoist | 16 | each | |
56 | 56 | PM of ash block making machine | 8 | each | |
57 | 57 | PM of pan mixture | 8 | each | |
58 | 58 | O/H of ash block making machine | 2 | each | |
59 | 59 | O/H of Pan mixture | 2 | each | |
60 | 60 | Replacement of Top/Bottom cylinder | 4 | each | |
61 | 61 | Wear plate replacement | 2 | SET | |
62 | 62 | Replacement/repaire of hydraulic valve | 4 | each | |
63 | 63 | Replacement of Bearing. | 6 | each | |
64 | 64 | Replacement of hydraulic hoses | 5 | each | |
65 | 65 | Replacement of Valve Belts | 6 | SET | |
66 | 66 | O/H of High capacity Sprinkler pumps (Ho | 3 | each |