Archaeological Survey Of India -ASI has published Mw ( Sr ) Restoration And Strengthening Works To The Badli Gate Of Golconda Fort , Hyderabad - Execution Of Work Removal Of Accumulated Debris , Water Tightening The Roof Of The Gateway , Pointing To The Surfaces , Removal Of Disturbed / Bulged Out . Submission Date for this Tender is 06-07-2021. Excavation Work Tenders in Golconda Fort, Hyderabad Telangana. Bidders can get complete Tender details and download the document.
Name of Work: < MW (SR) Restoration and Strengthening works to the Badli Gate of Golconda Fort, Hyderabad – Execution of work > | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Golconda Fort, Hyderabad | item1 | ||
2 | 1.01 | Removal of accumulated debris over the roof of Badli Gate and removal of vegetation on the roof of gateway including cost of labour, conveyance of waste from work spot to the low lying areas including loading, unloading, stone cutting charges, necessary applicable taxes etc. all complete as per the directions of the ASI Department Officials / Site-Incharge. \n(Quantity may vary as per the site condition)\n\n\n\n | item2 | 135 | Cum |
3 | 1.02 | Water Tightening the roof of the Gateway with Lime Surkhi brick jelly concrete (1:1:1) with a thickness of 10 cm including labour charges, material charges, conveyance charges, diesel charges, loading, unloading, applicable taxes, tools and accessories and cleaning the area after completion of works etc. all complete as per the directions of the ASI Department Officials / Site -Incharge. \n(Quantity may vary as per the site condition)\n\n\n | item3 | 676.4 | Sqm |
4 | 1.03 | Pointing to the surfaces of the Badli Gate in Lime Surkhi Mortar (1:1:1) including labour charges, material charges, conveyance charges, diesel charges, loading, unloading, cleaning the area after completion of work and applicable taxes etc. all complete as per the directions of the ASI Department Officials / Site -Incharge. \n(Quantity may vary as per the site condition)\n\n\n | item4 | 1095.65 | Sqm |
5 | 1.04 | Removal of disturbed / bulged out wall at North side of Badli Gateway along the road including cost of dismantling, labour charges, conveyance, diesel charges, loading, unloading, applicable taxes etc. all complete as per the directions of the ASI Department Officials / Site -Incharge. \n(Quantity may vary as per the site condition)\n\n\n\n | item5 | 7.9 | Cum |
6 | 1.05 | Earthwork excavation for masonry wall at North side of Badli gateway along the road including labour charges, conveyance, diesel charges, loading, unloading, applicable taxes etc. all complete as per the directions of the ASI Department Officials / Site -Incharge. \n(Quantity may vary as per the site condition)\n\n\n\n | item6 | 0.675 | Cum |
7 | 1.06 | Providing PCC 1:4:8 as a bed course to the masonry wall including cost of materials, labour charges, conveyance, diesel charges, loading, unloading, compaction charges, applicable taxes etc. all complete as per the directions of the ASI Department Officials / Site -Incharge. \n(Quantity may vary as per the site condition)\n\n\n\n | item7 | 0.675 | Cum |
8 | 1.07 | Construction of CR stone masonry wall and pointing at North side of Badli Gateway along the road in Lime Mortar 1:4 including pointing, cost of materials, labour charges, conveyance, diesel charges, loading, unloading, applicable taxes etc. all complete as per the directions of the ASI Department Officials / Site -Incharge. \n(Quantity may vary as per the site condition)\n\n\n\n | item8 | 9.55 | Cum |