Military Engineer Services-MES has published Repair Maintenance To Pump Sets Lt Panels Switch Gears Starters Cables Wiring Repair Maintenance To Pump Sets Lt Panels Switch Gears Starters Cables Wiring Security Lights And Connected Accessories At R S Area And Nofra Under Ge ( Nw ) Navy . Submission Date for this Tender is 15-06-2021. Electrification Work Tenders in GE (NW) NAVY NAGAR Maharashtra. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 27-May-2021 | Corrigendum No 1 | Date | 08-06-2021 |
2 | 28-May-2021 | Corrigendum No 2 | Other | 08-06-2021 |
3 | 08-Jun-2021 | Bid Auto Extn Corrigendum | Bid Auto Extn Corrigendum | 15-06-2021 |
Name of Work : REPAIR/MAINTENANCE TO PUMP SETS, LT PANELS, SWITCHGEARS, STARTERS, CABLES, WIRING, SECURITY LIGHTS AND CONNECTED ACCESSORIES AT R S AREA AND NOFRA UNDER GE(NW) NAVY NAGAR, COLABA, MUMBAI. | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Demolition of exisiting concrete supporting block of pumps and motor excedding 15cm of thickness above and below ground level complete all as specfied and as directed by Enginner-in-charge. | 8 | Cum | |
2 | 2 | Material and labour cement concrete 1:2:4, type B-2 (using 40 mm graded stone aggregate) as in support of Base frame with MS bolts placed in concrete and hardstanding finishing even and fair without using extra cement complete all as specfied and as directed by Enginner-in-charge. \nNote: Location of bolts and size of bolts should match the previous one. | 10 | Cum | |
3 | 3 | M& L for Disconnecting centrifugal pump from motor, suction and delivery pipe line of any Make, model and taking down packing for removing and insertion of new shaft sleeves or remove Bearing using bearing puller gear and fix new bearings and greasing all parts, coupling pump to motor and check for proper shaft alignments such that no vibration produce during opertion of following capacity pumps, complete all as specfied and as directed by Engineer-in-charge. \n | |||
4 | 3.01 | Pump coupled with 200 HP motor (Bearing Size NU311-EP & 6311-ZZ) Make:SFC/NBC or equivalent as approved by GE. | 2 | Each | |
5 | 3.02 | Pump coupled with 75 HP motor (Bearing Size 6309-ZZ & 3309) Make:SFC/NBC or equivalent as approved by GE. | 15 | Each | |
6 | 3.03 | Pump coupled with 60 HP motor (Bearing Size 6308 ZZ & 3308) Make:SFC/NBC or equivalent as approved by GE. | 3 | Each | |
7 | 3.04 | Pump coupled with 40 HP motor (Bearing Size 6307 ZZ & 3307) Make:SFC/NBC or equivalent as approved by GE. | 3 | Each | |
8 | 4 | Material and labour for disconnecting motor from pump of any Make, model and remove Bearing using bearing puller gear and fix new bearings at DE /NDE including necessary greasing ,check for proper shaft alignments such that no vibration produce during opertion of following capacity Motors complete all as specfied and as directed by Engineer-in-charge. \n | |||
9 | 4.01 | Pump coupled with 200 HP motor (Bearing size NU 319-C3 & 6319ZZ make SFC/NBC or equivalent as approved by GE. | 2 | Each | |
10 | 4.02 | Pump coupled with 75 HP motor (Bearing size 6313-ZZ & 6312ZZ make SFC/NBC or equivalent as approved by GE. | 6 | Each | |
11 | 4.03 | Pump coupled with 60 HP motor (Bearing size 6312 ZZ & 6311ZZ make SFC/NBC or equivalent as approved by GE. | 3 | Each | |
12 | 4.04 | Pump coupled with 40 HP motor (Bearing size 6311 ZZ & 6308ZZ make SFC/NBC or equivalent as approved by GE. | 3 | Each | |
13 | 4.05 | Pump coupled with 15 HP motor (Bearing size 6307 ZZ & 6309ZZ make SFC/NBC or equivalent as approved by GE. | 6 | Each | |
14 | 4.06 | Pump coupled with 20 HP motor (Bearing size 6309 ZZ & 6308ZZ make SFC/NBC or equivalent as approved by GE. | 13 | Each | |
15 | 5 | Supply and fixing in repair AC-3 type contactor with control voltage of 230V AC with integrated auxillary or Add on block contacts with 1 or 2 NO and NC including connection of control wiring to contactor and testing of starter after repairing complete all as specfied and as directed by Enginner-in-charge. | |||
16 | 5.01 | Contactor rating of 185A Make - L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 4 | Each | |
17 | 5.02 | Contactor rating of 110A Make L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 3 | Each | |
18 | 5.03 | Contactor rating of 70A Make L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 15 | Each | |
19 | 5.04 | Contactor rating of 50A Make L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 5 | Each | |
20 | 5.05 | Contactor rating of 40A Make L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 8 | Each | |
21 | 5.06 | Contactor rating of 32A Make L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 3 | Each | |
22 | 5.07 | Contactor rating of 22A Make L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 4 | Each | |
23 | 5.08 | Contactor rating of 18A Make L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 9 | Each | |
24 | 5.09 | Contactor rating of 12A Make L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 10 | Each | |
25 | 5.1 | Contactor rating of 9A Make L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 9 | Each | |
26 | 6 | Supply and fixing in repair Thermal over load relay with adjustable setting with integrated auxillary or Add on block contacts with 1 or 2 NO and NC including connection of control wiring to OLR and testing of starter after repairing complete all as specfied and as directed by Engineer-in-charge. | |||
27 | 6.01 | OLR of capacity I Min of 135 to I max 225 A with CT Make L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 3 | Each Job | |
28 | 6.02 | OLR of capacity I Min of 36 to I max 60A \nMake L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 6 | Each Job | |
29 | 6.03 | OLR of capacity I Min of 30 to I max 50A \nMake L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 4 | Each Job | |
30 | 6.04 | OLR of capacity I Min of 20 to I max 33A \nMake L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 5 | Each Job | |
31 | 6.05 | OLR of capacity I Min of 09 to I max 15A \nMake L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 6 | Each Job | |
32 | 6.06 | OLR of capacity I Min of 07 to I max 13A \nMake L &T/Havells/C&S/Legrand or equivalent as approved by GE. | 8 | Each Job | |
33 | 7 | Supply and fixing self lubricated asbestoes non metallic and non graphite gland packing to following size | |||
34 | 7.01 | 6mm | 10 | KG | |
35 | 7.02 | 8mm | 20 | KG | |
36 | 7.03 | 10 & 11 mm | 40 | KG | |
37 | 7.04 | 12mm | 50 | KG | |
38 | 8 | Supply and fixing in replacement of Automatic Star Delta starter for 75 HP motor which includes 2 contactors of 70A ,1- contactor of No of 40A ,1-No of Thermal over load relay of capacity 45 t0 75A ,1-No of Timer ,1-N0's of Volatge sensing relay,control wiring ,MCB,push buttons,Indicating lamps, and other necessary control wiring including necessary alterartion to existing panel complete all as specfied and as directed by Engineer-in-charge. | 3 | Each | |
39 | 9 | Supply and fixing in replacement of Automatic Star Delta starter for 200 HP motor which includes 2 contactors of 70A ,1- contactor of No of 40A ,1-No of Thermal over load relay of capacity 45 t0 75A ,1-No of Timer ,1-N0's of Volatge sensing relay,control wiring ,MCB,push buttons,Indicating lamps, and other necessary control wiring including necessary alterartion to existing panel complete all as specfied and as directed by Engineer-in-charge. | 2 | Each | |
40 | 10 | Supply and fixing in replacement of Automatic Star Delta starter for 60 HP motor which includes 2 contactors of 70A ,1- contactor of No of 40A ,1-No of Thermal over load relay of capacity 45 t0 75A ,1-No of Timer ,1-N0's of Volatge sensing relay,control wiring ,MCB,push buttons,Indicating lamps, and other necessary control wiring including necessary alterartion to existing panel complete all as specfied and as directed by Engineer-in-charge. | 2 | Each | |
41 | 11 | Supply and fixing in replacement of Automatic Star Delta starter for 40 HP motor which includes 2 contactors of 70A ,1- contactor of No of 40A ,1-No of Thermal over load relay of capacity 45 t0 75A ,1-No of Timer ,1-N0's of Volatge sensing relay,control wiring ,MCB,push buttons,Indicating lamps, and other necessary control wiring including necessary alterartion to existing panel and all directed by engineer-in -charge. | 3 | Each | |
42 | 12 | Supply and fixing in replacement of Automatic Star Delta starter for 20 HP motor which includes 2 contactors of 70A ,1- contactor of No of 40A ,1-No of Thermal over load relay of capacity 45 t0 75A ,1-No of Timer ,1-N0's of Volatge sensing relay,control wiring ,MCB,push buttons,Indicating lamps, and other necessary control wiring including necessary alterartion to existing panel and all directed by engineer-in -charge. | 3 | Each | |
43 | 13 | Supply and fixing in replacement of Automatic Star Delta starter for 15 HP motor which includes 2 contactors of 70A ,1- contactor of No of 40A ,1-No of Thermal over load relay of capacity 45 t0 75A ,1-No of Timer ,1-N0's of Volatge sensing relay,control wiring ,MCB,push buttons,Indicating lamps, and other necessary control wiring including necessary alterartion to existing panel complete all as specfied and as directed by Enginner-in-charge. | 2 | Each | |
44 | 14 | Material and labour for replacement of MS jaw coupling type-L with spider made of synthetic rubber or gear coupled type of suitable for 200 HP motor complete all as specfied and as directed by Enginner-in-charge. | 4 | Each | |
45 | 15 | Material and labour for replacement of MS jaw coupling type-L with spider made of synthetic rubber or gear coupled type of suitable for 75 HP motor complete all as specfied and as directed by Enginner-in-charge. | 6 | Each | |
46 | 16 | Material and labour for replacement of MS jaw coupling type-L with spider made of synthetic rubber or gear coupled type of suitable for 60 HP motor | 6 | Each | |
47 | 17 | Material and labour for replacement of MS jaw coupling type-L with spider made of synthetic rubber or gear coupled type of suitable for 40 HP motor complete all as specfied and as directed by Enginner-in-charge. | 4 | Each | |
48 | 18 | Material and labour for disconnecting motor power cables of various sizes from electrical motor of different capacities and decoupling from the pump sets,removing and taking down carefully and transporting to authorised workshop ,Dismantaling stator and rotor carefully and rewinding stator assembly with supper enamelled copper winding wire of suitable gauge matching to existing gauge and cleaning of slots ,core with carbon tetra chloride solution and apply two coats of insulation varnish and keep stator assembly in heating chamber to improve insulation strength ,reassemble motor completey and transporation to site ,coupling pump to motor and check for proper shaft alignments such that no vibratiobn produce during opertioncoupling to pump with exact allinment ,connect power cables to motor and testing of following capacity motor complete all as specfied and as directed by Enginner-in-charge. | |||
49 | 18.01 | 200HP | 1 | Each | |
50 | 18.02 | 75HP | 7 | Each | |
51 | 18.03 | 60 HP | 3 | Each | |
52 | 18.04 | 40 HP | 4 | Each | |
53 | 18.05 | 20/15 HP | 12 | Each | |
54 | 19 | Supply and fixing in repair and replacemnt of MCCB with thermal adjustment of 0.8 to 1In and magnetic adjustable 5 t0 10 In and Ics=100% of Icu and replacing burnout copper spreaders of suitable size including nuts and bolts and fixing to existing panel including necessary alternation to existing busbar and panel complete all as specfied and as directed by Enginner-in-charge. | |||
55 | 19.01 | MCCB of 320A ,Breaking capacity 50KA,4P Make L &T /C &S/Havells or equivalent as approved by GE. | 3 | Each | |
56 | 19.02 | MCCB of 400A ,Breaking capacity 50KA,4P Make L &T/C &S/Havells or equivalent as approved by GE. | 4 | Each | |
57 | 19.03 | MCCB of 200A ,Breaking capacity 36KA,4P Make L &T/C &S/Havells or equivalent as approved by GE. | 4 | Each | |
58 | 19.04 | MCCB of 630 A ,Breaking capacity 36KA,4P Make L &T /C &S/Havells or equivalent as approved by GE. | 3 | Each | |
59 | 19.05 | MCCB of 125 A,Breaking capacity 36KA,3P Make L &T/C &S/Havells or equivalent as approved by GE. | 3 | Each | |
60 | 19.06 | MCCB of 100A,Breaking capacity 36KA,3P Make - L &T/C &S/Havells or equivalent as approved by GE. | 4 | Each | |
61 | 19.07 | MCCB of 63A,Breaking capacity 36KA,3P Make - L &T/C &S/Havells or equivalent as approved by GE. | 5 | Each | |
62 | 19.08 | MCCB of 25A,Breaking capacity 36KA,3P Make - L &T/C &S/Havells or equivalent as approved by GE. | 6 | Each | |
63 | 20 | Supply and fixing in repair and replacemnt of burnout aluminium spreaders incoming or outgoing of following size including nuts and bolts complete all as specfied and as directed by Enginner-in-charge. | |||
64 | 20.01 | 250A 4P | 3 | set of 4 | |
65 | 20.02 | 250A 3P | 5 | set of 3 | |
66 | 20.03 | 400A 3P | 4 | set of 3 | |
67 | 21 | Supply and fixing in repair pressure gauge 150mm dia range 0-10Kg /Sqcm. Note: quoted rated should including for providing of adopter /Ferrule/check nut etc required for fixing pressure guage and necessary alterations to MS or CI pipe for taping if required, complete all as specfied and as directed by Enginner-in-charge. | 18 | Each | |
68 | 22 | Supply ,testing,installation in repair of 3 pole 230v automatic street light on/off outdoor panel with IP66 which consists of Digital time switch for switching LED street light on/off lights and other electric devices combination function including necessary MS angle supporting structure for holding panel and foundation for panel complete all as specfied and as directed by Enginner-in-charge. \nMake: INDOASIAN cat ref TLO40DBO or equivalent make in Havells/ L&T as approved by GE. | 10 | Each | |
69 | 23 | Supply and fixing in repair LED street light aluminium pressure die of 100W with toughen glass IP 66 protection with in built 10KV surge protection complete all as specfied and as directed by Enginner-in-charge. \nMake Havells Model No ENDURAPEARLMAGNUMSL100WLED757PASYTOTGA or Equivalent Make:Havells /Syska/Bajaj as approved by GE. | 29 | Each | |
70 | 24 | Supply and fix in repair /Replacement of CI double acting Air release valve of following size complete all as specfied and as directed by Enginner-in-charge. \nNote: Excavation will be measured and paid separately. | |||
71 | 24.01 | 300mm bore | 2 | Each | |
72 | 24.02 | 150mm bore | 2 | Each | |
73 | 25 | Excavation in trenches not exc 1.5 mtr wide and not exc 1.5 mtr in depth for foundation, laying of HDPE pipe . and getting out in hard soil , complete all as specfied and as directed by Enginner-in-charge. | 180 | Cum | |
74 | 26 | Removing the excavated material/ soil exc 250 and not exc 500m out of MoD land complete all as specfied and as directed by Enginner-in-charge. | 50 | Cum | |
75 | 27 | Returning & filling in, including spreading, levelling, watering & well ramming in layers not exc 25 cm as in soil complete all as specfied and as directed by Enginner-in-charge. | 130 | Cum | |
76 | 28 | Supply and fix in repair Heavy duty Exhaust fan of size 375mm including with flap cover necessary connection to existing celing rose,alteration to existing wall and make surface smooth ,testing complete all as specfied and as directed by Enginner-in-charge. | 10 | Each | |
77 | 29 | Earthing complete with galvanised steel earth plate electrode 60 × 60cm.× 6mm thick, buried directly in ground (earth pit not less than 2.25 metres deep below ground level) with top edge of the plate not less'than 1.5 metres below normal ground level, connected to galvanised earth strip 32x6mm by means of bolts, nuts, check nuts and washers of galvanised iron or steel all as shown in electrical plate No. 3 connected to earthing test point all as specified or indicated including testing on completion complete all as specfied and as directed by Enginner-in-charge. | 35 | Each | |
78 | 30 | Supply and laying in replacement of copper unamoured power cable of size 25sqmm from motor starter panel to motor in HDPE pipe in ground complete all as specfied and as directed by Enginner-in-charge. | 100 | RM | |
79 | 31 | Supply and laying in replacement of copper unamoured power cable of size 35sqmm from motor starter panel to motor in HDPE pipe in ground complete all as specfied and as directed by Enginner-in-charge. | 90 | RM | |
80 | 32 | Supply and laying in replacement of copper unamoured power cable of size 50 sqmm from motor starter panel to motor in HDPE pipe in ground complete all as specfied and as directed by Enginner-in-charge. | 90 | RM | |
81 | 33 | Supply and Fix in replacement Rubber insulation mat,anti skid as per IS 15652:2006 with thicknesss of 2mm and class A withstand capacity of 3.3 KV including fixing to ground with necessary strip on all sides complete all as specfied and as directed by Enginner-in-charge. | 48 | SqM | |
82 | 34 | Material and labour for bacteriological and chemical analysis of water sample at govt approved lab (ISO 9001:2008)including collecting sample from pumphouse using labed owned sample jar and testing every month complete all as specfied and as directed by Enginner-in-charge. | 77 | Each | |
83 | 35 | Material and labour for repalcement of MS stuffing box or bushes suitable for 100HP/75HP/50HP pumps including necessary accessories complete all as specfied and as directed by Enginner-in-charge. | 6 | Each | |
84 | 36 | Supply and Lay in repair LT XLPE insulated, armoured heavy duty electric cable with aluminium conductor, 1100 volts grade, cross-sectional area 10sq. mm ,2 core.\nNote : 1. The cost of Al thimbles/lugs and cable gland etc is including in the quoted rate and no extra payment will be made for it. 2. The excavation, earth work, sand cushioning and brick protection etc will be measured and paid separately under respective items complete all as specfied and as directed by Enginner-in-charge. | 240 | RM | |
85 | 37 | S & F in repair looping box of size 130mm x 130mmx77mm weather proof IP66/67 including connector blocks four way having suitable size bolt to connect upto 6sqmm x 2 core cable two Nos with the help of suitable gland, thimble nuts, washers supports by flat aluminium clamps not less than 25 mm x 3mm with suitable size nuts, bolts and washers inside and outside looping box including fixing with electric pole and taking out old one of any type complete as directed. Make : Hansel , Cat ref : KF3535G. or equivalent make as approved by GE complete all as specfied and as directed by Enginner-in-charge. | 11 | Each | |
86 | 38 | Supply and fixing Analog Voltmeter range from 0-500 volts including control wiring complete all as specfied and as directed by Enginner-in-charge. | 20 | Each | |
87 | 39 | Supply and fixing Analog Ammeter range from 0-100 Amp including control wiring complete all as specfied and as directed by Enginner-in-charge. | 12 | Each | |
88 | 40 | Supply and fixing selector switch including control wiring complete all as specfied and as directed by Enginner-in-charge. | 15 | Each | |
89 | 41 | Supply and fixing indication lamps including control wiring complete all as specfied and as directed by Enginner-in-charge. | 24 | Each | |
90 | 42 | Supply,installation,testing and comissioning in replacement of soft starter of 55KW with operating volatge of 430V complete all as specfied and as directed by Enginner-in-charge. \nMake:ABB/L&T/Schinder/Seimens. | 3 | Each | |
91 | 43 | Supply,installation,testing and comissioning in replacement of soft starter of 45KW with operating volatge of 430V complete all as specfied and as directed by Enginner-in-charge. \nMake:ABB/L&T/Schinder/Seimens. | 3 | Each | |
92 | 44 | supply,installation,testing and comissioning in replacement of soft starter of 30KW with operating volatge of 430V complete all as specfied and as directed by Enginner-in-charge. \nMake:ABB/L&T/Schinder/Seimens. | 3 | Each |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy