Agra Municipal Corporation has published Construction Of Road By Interlocking Tiles -Zone 1 Ward 61 Kabirkunj Phase 1 Me Nali Marammat Avm Interlocking Tiles Dwara Sadak Nirman Karya. Submission Date for this Tender is 24-04-2021. Road Work Tenders in AGRA Uttar Pradesh. Bidders can get complete Tender details and download the document.
Name of Work: | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Dismantling of R.C.C./R.B work including stacking of material as directed by E/IC within distance of 60 meters. (SI No. 694) | BI01010001010000000000000515BI0100001112 | 4.84 | cum |
2 | 2 | E/W cutting in or in embankment in ordinary soil excavation to be in the form of a regular pits not exceeding 0.50m in depth and earth work in embankment to be in 20cm layers including ramming and dressing the surface to required levels and slopes and also including 1.5m lift and 30 m lead. The earth in form of cutting (b) to be used as spoil banks within 50m distance as directed by the engineer-in-charge including royalty 9.00 cum. (SI No. 253(A)) | BI01010001010000000000000515BI0100001113 | 56.25 | cum |
3 | 3 | Cartage of silt, sludge kankar and other disposable organic material etc. all complete with labor T&P including cartage of 8 km. (NS) | BI01010001010000000000000515BI0100001114 | 48.87 | cum |
4 | 4 | P/L GSB with graded stone ballast with moram with stone grit size, stone ballast with hand ramming watering including all material labor T&P etc. all complete (NS) | BI01010001010000000000000515BI0100001115 | 70.08 | cum |
5 | 5 | M-150 Brick work in 1:4 with Cement and coarse sand including supply of all material, labor T & P etc. required for proper completion of work. (SI No. 305.1) | BI01010001010000000000000515BI0100001116 | 30.91 | cum |
6 | 6 | 12MM Thick cement plaster in single coat of fair side of single of half brick wall for interior plastering up to floor two level including internal rounded angles chamfers and rounded angles not including 80mm in girth and finished even and smooth. No extra for missing any additive. 1 cement : 4 Coarse Sand (SI No. 582(I) | BI01010001010000000000000515BI0100001117 | 184.8 | sqm |
7 | 7 | Supply & fixing of pre-cast M-30 cement concrete RUBBER MOLD INTERLOCKING TILES over 40mm thick local sand bed, with 3mm thick joints filled with local sand including leveling, tempering and sweeping etc., interlocking bricks will be as description given in direction issued by the IRCSC-03-2004 and should be ISI marked all complete. (N.S.) 80mm thick, Strength should not less than M-30 (NS) | BI01010001010000000000000515BI0100001118 | 876 | sqm |
8 | 8 | Providing and laying cement concrete in 4:2:1 of not less than strength of M-150 stone ballast (20 mm nominal size) approved coarse sand and cement. Curing complete including of cost of form work in foundation and floors. (SI No. 279(A)) | BI01010001010000000000000515BI0100001119 | 2.76 | cum |
9 | 9 | R.C.C. work with cement approved coarse sand and 2 cm (3/4) gauge approved stone ballast in the proportion 1:2:4 for slab work excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 BWGI binding wire and including necessary centering and shuttering etc. and also including supply of all materials labor and tools and plants etc. required for proper completion of the work. Strength of the concrete shall not be less than M-150. (SI No. 284) | BI01010001010000000000000515BI0100001120 | 1.75 | cum |
10 | 10 | Mild Steel or iron in plain work such as reinforced concrete or reinforced brick work (When not included in and an overall rates) brought to required shape as necessary including bending for proper completion of the work and including supply of steel, its wastage bend hooks and authorized over lapping shall be measured up to floor two level. (10 mm to 12mm tor (TMT Bars). | BI01010001010000000000000515BI0100001121 | 1.37 | qtl |
11 | 11 | Supply and fixing of black granite stone board and approved standard matter with brick work, plaster & paint etc. all complete. | BI01010001010000000000000515BI0100001122 | 1 | Nos |
12 | 12 | Sub Total (A) | BI01010001010000000000000515BI0100001157 | 1 | Rs |
13 | 13 | Add 12% G.S.T. of Sub Total (A) | BI01010001010000000000000515BI0100001160 | 1 | Rs |
14 | 14 | Sub Total (B) | BI01010001010000000000000515BI0100001161 | 1 | Rs |
15 | 15 | Add / Deduction For Estimate Figure Amount Match | BI01010001010000000000000515BI0100001162 | 1 | Rs |
16 | 16 | Grand Total | BI01010001010000000000000515BI0100001163 | 1 | Rs |