Construction Of Two Lane Road Over Bridge ( Rob ) With Bow String Steel Beam In Lieu Of Level X-Ing No . 127-C3-T At Km 270/25-27 In Between Ambala City And Shambhu Railway Stations On Umb-Ldh Section On Dfcc Route ( Clear Span 60 . 0M ) In District , Ambala Cantt.-Haryana

Public Works Department-PWD has published Construction Of Two Lane Road Over Bridge ( Rob ) With Bow String Steel Beam In Lieu Of Level X-Ing No . 127-C3-T At Km 270/25-27 In Between Ambala City And Shambhu Railway Stations On Umb-Ldh Section On Dfcc Route ( Clear Span 60 . 0M ) In District . Submission Date for this Tender is 22-01-2021. Highway Construction Tenders in Ambala Cantt. Haryana. Bidders can get complete Tender details and download the document.




Tender Notice

26540855
Construction Of Two Lane Road Over Bridge ( Rob ) With Bow String Steel Beam In Lieu Of Level X-Ing No . 127-C3-T At Km 270/25-27 In Between Ambala City And Shambhu Railway Stations On Umb-Ldh Section On Dfcc Route ( Clear Span 60 . 0M ) In District
Open Tender
Indian
Haryana
Ambala Cantt.
22-01-2021

Tender Details

Construction Of Two Lane Road Over Bridge ( Rob ) With Bow String Steel Beam In Lieu Of Level X-Ing No . 127-C3-T At Km 270/25-27 In Between Ambala City And Shambhu Railway Stations On Umb-Ldh Section On Dfcc Route ( Clear Span 60 . 0M ) In District Ambala

Key Value

Document Fees
INR 20000 /-
EMD
INR 4320000.0 /-
Tender Value
INR 21.59 Crore /-

BOQ Items

Name of Work: Construction of two lane Road Over Bridge (ROB) with Bow String Steel Beam in lieu of Level X-ing No.127-C3-T at Km 270/25-27 in between Ambala City and Shambhu Railway Stations on UMB-LDH Section on DFCC Route (Clear Span = 60.0M) in District Ambala
Sl. No. Item Description Item Code / Make Quantity Units
1 1 Bored cast-in-situ M35 grade with minimum cement content 350 kg per cum, RCC piles of 1200 mm diameter in all kinds of soil (including hard & boulders ) with Hydraulic Rig excluding cost of steel reinforcement but including the cost of Shoe and the length of pile to be embedded in the pile cap etc, (Length of pile for payment shall be measured from top of shoe to the bottom of the pile cap). All complete as per drawing and conforming to section 1100 and 1700 of MORTH specifications of latest edition and clause 709 of IRC: 78-2000/latest edition including cost of bentonite slurry, initial vertical and lateral load tests, routine load tests and removal of excavated earth with all lifts and lead etc. complete in all respect.\n\n(i) 1200 dia piles\n(A) The scope of work in the above items include:\n(1) The cost of all initial layout of piles and setting out, initial excavation, if any\n(2 a) The cost of boring through all types of soils/existing road/ pavement, removal of all obstruction like boulders, old foundation concrete or rock to be paid in relevant item above by chiseling or any other method as approved by the Engineer-in-charge. If a bore is abandoned for any reason no payment shall be made for such incomplete boring and shifting of the equipments\n(2 b) The cost of filling up of the empty bore, if required\n(3) The cost of preparation, circulation and handling of bentonite slurry.\n(4) The cost of disposal of all spoil, bentonite waste to keep the work area neat.\n(5) The cost of providing temporary liner and its withdrawal, if required below adjoining ground level (irrespective of the R.L of the adjoining ground level) for vertical piles)\n(6) The cost of providing and mixing all ingredients of cement concrete (except reinforcement steel) including admixtures, with batching plant, transportation, placement of concrete by tremie pipe for the required lengths of pile including providing cover blocks, stiffeners, handling bars etc. for safe handling of reinforcement cage.\n(7) The cost of breaking of pile head not earlier than 3 days after concreting and to remove spoil concrete to bring the pile head to the socketing level including cleaning and arranging the extended reinforcement bars as per drawings.\n(8) The cost of working for all leads, lifts, pumping / bailing out of water, labour, material and equipment etc.\n(9) The cost of mobilizing to site, installation at different locations transferring / dismantling, shifting, reinstalling and removal from site of the piling rigs and / or other equipments and all accessories including working plateforms\n(10) The cost of identification, protection and maintenance of existing services, if any, which in the opinion of Engineer-in-charge are likely to be affected by piling operation incl. temporary shifting of such services to facilitate piling job shall also have to be done, if so required by the Engineer-in-charge and the cost for the same as assessed by the engineer-in-charge shall be reimbursable.\n(11) The cost of barricading and all traffic safety requirements as specified in the tender document.\n(12) The cost of all incidentals, labour, material, equipment and works required to execute the job. The item also includes any other incidental expenditures for completing the job as per the direction of the engineer-in-charge\n(13) The item includes the cost of testing of all the materials involved in the execution of the item as per QAP.\n(B) Mode of measurement:\n(14) Initial vertical load testing, horizontal load testing, routine load testing required as per IS : 2911 part (iv) and as per MoRT&H specification\n(i) Length of pile shall be measured from cut off level to the tip of the pile correct to a cm in case where the pile is terminated. \n(ii) Reinforcement steel shall be measured & paid separately \n BI01010001010000000000000515BI0100001113 3528 P.Mtr. (per running metre)
2 2 Integrity testing of pile using Low Strain/Sonic Integrity test/Sonic Echo Test method in accordance with IS 14893 including surface preparation of pile top by removing soil,mud, dust and chipping lean concrete lumps etc. and use of computerised equipment and high skill trained personnel for conducting the test and submission of results, all complete as per direction of Engineer in charge. Note:- The inclusion of above item in the schedule of work shall be judiciously decided by the technical sanctioning authority, keeping in view the quality control, type of soil strata and importance of the project BI01010001010000000000000515BI0100001114 60 per test
3 3 Earth work in excavation for Pier Pile caps. Abutment pile caps, in all type of soils, weathered rock, existing footings, removal of boulders, concrete, ballast, stone etc including protecting the excavated sides, if required, till concreting, bailing out water to keep the area clean and dry during placement of reinforcement and concrete till the concrete sets finally. The item includes the cost of disposal of all spoils, dismantled materials, surplus earth for all leads and lifts as per clause No. 304 of MoRT&H Specifications 5th revision 2013 and to keep the work area neat and tidy during the work and thereafter. Payment shall be made based on approved plan dimensions for PCC below pile cap. The cost of backfilling around the pile cap and restoration of road, if required shall be included (MORT&H 304). BI01010001010000000000000515BI0100001115 2500.47 P.Cum (per cubic metre)
4 4 Providing and laying plain cement concrete M15 grade minimum with cement content 240 kg per cum,(aggregate 20mm nominal size) leveling course below the pile cap, etc. using Ordinary Portland Cement of grade 43, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel). As per MORT&H specification for road and bridges works (5th revision) / latest edition as per Payment shall be made based on approved plan dimensions for PCC as per clause No. 1500 and 1700 of MoRT&H Specifications 5th revision 2013. BI01010001010000000000000515BI0100001116 131.7 P.Cum (per cubic metre)
5 5 Providing and laying reinforced cement concrete M-35 grade minimum with cememt content 350 kg per cum for construction of pier pile caps, abutment pile caps, etc. using Ordinary Portland Cement of grade 43, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel). As per MORT&H specification for road and bridges works (5th revision) / latest edition as per clause No. 1500, 1700 & 2100 of MoRT&H Specifications - 2013\n\n(A) The scope of work in the items include:\n(1) The cost of all initial layout and setting out work including identification of existing services, if any.\n(2) The cost of all pumping/bailing out of water, including its labour, mateiral and equipments.\n(3) The cost of providing centering and shuttering including its erection, dismantling and removal of formwork including all leads and lifts with all required tools and plants to the required line and level.\n(4) The cost of providing and mixing all ingredients (except reinforcement steel) including admixtures etc. with batching plant, transportation, placement, finishing and curing of concrete.\n(5) The cost of maintenance and protection of existing services, if any which in the opinion of Engineer-in-charge are likely to be affected by any related activities including temporary shifting of such services to facilitate construction of pile cap work shall also have to be done, if so required by the Engineer-in-charge, and the cost for the same as assessed by the Engineer-in-charge shall be reimbursable.\n(6) The cost of installation of any fixture into the pile cap (cost of fixture to be paid separately)\n(7) The cost of barricading and all safety requirements as specified elsewhere in the tender document.\n(8) The cost of testing of all the materials, involved in the execution of items as per QAP.\n(9) The cost of all incidental labour, materials, equipment and works required to execute the job as per directions of engineer-in-charge.\n(B) Mode of measurement:\n(1) Measurements shall be made for the finished volume of reinforced cement concrete restricted to volume as per approved drawing (excluding cost of reinforcement steel only). Quantity of concrete of piles, which has gone into the pile caps shall be deducted. Reinforcement shall be measured & paid separately \n BI01010001010000000000000515BI0100001117 1677.19 P.Cum (per cubic metre)
6 6 Steel Reinforcement: Supply, cutting, bending with all leads, lifts and depths, fixing in position reinforcement of any diameter, TMT Fe- 500 EQR/Fe 500 D grade or more for RCC work as per relevant BIS specification and drawing in RCC works in Foundations,sub structure , super structure and any other work in the BOQ .The rate shall include cost of all material including galvanizing / epoxy coating tying wire, binding wire, cover block, provision of stools, chairs, spacer bars, overlaps, support bars , labour, transportation, storing and all other incidental charges, tools & plants etc complete. as per clause No. 1600 &2200 of MORT&H specification 2013 / Latest edition for road and bridges works (MORT&H 12.40) BI01010001010000000000000515BI0100001118 1548.06 P.M.T. (Per Metric Tonne)
7 7 Providing and laying reinforced cement concrete M-35 grade minimum with cememt content 350 kg per cum for construction of Abutment, piers, dirt wall, pier caps, return wall and bracket etc. concrete using Ordinary Portland Cement of grade 43 appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, centering, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel, complete as per clause No. 1100,1500,1700 and 2200 of MoRT&H Specifications 5th revision 2013).\nHeight upto 5 met.\n(A) The scope of work in the item includes\n(1) The cost of all incidental work required including providing, placement and removal, shifting of shuttering, cleaning, oiling & maintenance, rection & removal of staging, scaffolding and form liner etc, for piers, pier caps, bearing pedestals and other works as stated in other parts of the tender document.\n(2) The cost of casting of a mock pier at casting yard true to line, level and shape as per the direction of the Engineer-in-charge.\n(3) The cost of casting of pier, pier caps, abutment, abutment caps etc. including providing and mixing all ingredients and admixtures etc. in batching plant, transportation, placement, compacting, finishing and curing, placing in position inserts with pier/pedestals as per specification and the direction of the Engineer-in-charge.\n(4) The cost of disposal of all spoils and to keep the work area neat and tidy during the work and thereafter.\n(5) The cost of barricading and all safety requirements as mentioned elsewhere in the tender documents.\n(6) Installation of any fixtures into pier/pier cap etc (cost of fixtures in any, to be paid separately.\n(7) The cost of all incidentals, labour, material, equipment and works required for the executions of the job as per the direction of Engineer-in-charge.\n(8) The cost of testing all materials involved in the execution of the item as per QAP.\n(9) The cost of working for all leads, lifts, pumping / bailing out water, labour, material and equipment etc.\n(B) Mode of measurement:\n(1) Measurement shall be made for the finished volume of concrete only and will be restricted to the dimensions shown in the approved drawing.\n(2) Reinforcement steel shall be measured & paid separately.\n BI01010001010000000000000515BI0100001119 136.05 P.Cum (per cubic metre)
8 8 Providing and laying reinforced cement concrete M-35 grade minimum with cememt content 350 kg per cum for construction of Abutment, piers, dirt wall, pier caps, return wall and bracket etc. concrete using Ordinary Portland Cement of grade 43 appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, centering, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel, complete as per clause No. 1100,1500,1700 and 2200 of MoRT&H Specifications 5th revision 2013).\n\nHeight 5 to 10 met. BI01010001010000000000000515BI0100001120 513.35 P.Cum (per cubic metre)
9 9 Providing and laying reinforced cement concrete M-40 grade minimum with cement content 360 kg per cum for construction of bearing pedstal, sesmic stopper etc. concrete using Ordinary Portland Cement of grade 43 appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, centering, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel, complete as per clause No. 1100,1500,1700 and 2200 of MoRT&H Specifications 5th revision 2013). BI01010001010000000000000515BI0100001121 61.69 P.Cum (per cubic metre)
10 10 Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to IRC:83 (Part-II), Section-IX and clause 2005 of MORT&H specifications complete including all accessories as per drawing and Technical specifications The bearing shall be of SANFIELD, METCO, MAGEBA and M/S STEEL AUTO INDUSTRIES. BI01010001010000000000000515BI0100001122 2.3112e+06 (per centimetre cube) cm3
11 11 Providing and laying reinforced cement concrete M-35 grade minimum with cememt content 350 kg per cum for construction of Girders, cross girders etc. concrete using Ordinary Portland Cement of grade 43 appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, centering, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel, complete as per clause No. 1100,1500,1700 and 2300 of MoRT&H Specifications 5th revision 2013).) The item also includes cost of transportations of precast RCC girders up to 40 mtr span to site, launching and other operations with respect to launching thereof and putting in place, if required. BI01010001010000000000000515BI0100001123 1017.75 P.Cum (per cubic metre)
12 12 Providing and laying reinforced cement concrete M-35 grade minimum with cememt content 350 kg per cumfor construction of RCC deck slab, etc. concrete using Ordinary Portland Cement of grade 43 appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, centering, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel, complete as per clause No. 1100,1500,1700 and 2300 of MoRT&H Specifications 5th revision 2013).) BI01010001010000000000000515BI0100001124 774.03 P.Cum (per cubic metre)
13 13 Providing laying and fixing in position reinforced cement concrete Crash Barrier at the edges of the road, approaches to bridge structure and medians, constructed with M-40 grade minimum with cememt content 360 kg per cumconcrete (Including reinforcement ), including centering shuttering and form work etc. conforming to IRC:21 and dowel bars 25mm dia, 450mm long at expansion joints filled with pre-moulded asphalt filler board keyed to the structure on which it is built and installed as design given in the enclosure to MOST Circular No. RW/NH-33022/1/94-DO III dt. 24th June 1994, as dimensions in the approved drawing and at locations directed by the Engineer as per clause No. 811 of MORT&H specification-2013.\n\n(A) The scope of work in the item includes:\n(1) The item includes the cost of preparation, fabrication, casting, fixture, placing and fixing in position using fastnersand pickling.\n(2) The item includes the cost of painting alongwith one coat of anticorrosive primer.\n(3) The item includes the cost of testing of all materials involved in the execution of the items as per QAP.\n(4) The items includes all other incidental expenditure for completing the jobs as per direction of Engineer-in-charge.\nMode of measurement\nMeasurement shall be made in running meter complete as per dimention shown in approved drawing.\n BI01010001010000000000000515BI0100001125 1229.22 Rmt (per running metre)
14 14 Providing and fixing hand rail 65 mm dia GI pipe over the crash barrier kerb consisting of MS base plate, embedded fasterner and nuts. MS vertical plates and pipes etc, as shown in the drawings and as per specifications and painting the same with 3 or more coats of paints. All the railling components as mentioned above to be hot dip galvanised with a zinc coating of at least 175 gm/sqm. Item to include all incidental works required to complete the work as per the directions of the Engineer-in-charge. (N.S) BI01010001010000000000000515BI0100001126 1229.22 Rmt(Per running metre)
15 15 Providing and installing single strip seal expansion joints of SANFIELD ,METCO,MAGEBA and M/s steel auto industrial with a total allowable maximum movement 80mm as per Clause 2606 of MORTH specifications for Road and Bridge Works (5th Revision) 2013 supplemented with manufacturer’s recommendations. Entire installation is to be carried out strictly in the presence of manufacturer's representative only, at all times. The seal of the expansion joint shall be such as not to permit any dust collection at all times.A) The scope of work in the item includes:\n\n(A) The scope of work in the item includes:\n(1) Cost of all materials, labours, equipment and other incidental charges for execution of this item. Supervision during installation by the manufacturer is also included.\n(2) Installation & fixing of expansion joints as per manufacturers specifications and design / drawing approved by the engineer-in-charge including chipping of concrete, cleaning of concrete and reinforcement bars, leveling, necessary shuttering, pre-setting, welding etc.\n(3) Item to included necessary provision and filling of recess for the expansion joints at no extra cost.\n(4) The item includes the cost of testing of all the materials involved in the execution of the item as per QAP and testing of completed and installed joints as per the acceptnce criteria of MoRT&H.\n(B) Mode of measurement:\n(1) The expansion joints shall be measured in running meters. The length payable is the actual length provided at site including vertical parts of kerbs / crash barriers, footpath etc.\n BI01010001010000000000000515BI0100001127 176.4 Rmt(Per running metre)
16 16 Providing and laying tack coat with bitumen VG-10 grade pressure distributor at the rate of 0.25 kg. per sqm. On the prepared bitumen/granular surface cleaned with mechanical broom including cost of bitumen as per clause No.503 (5th edition) 2013 as per MoRT&H specification (N.S.) BI01010001010000000000000515BI0100001128 9884.12 P.Sqm (Per square metre)
17 17 Providing and fixing in position 20mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans not exceeding 10 m to cater for a horizontal movement upto 20 mm covered with sealant complete as per drawing and technical specification clause No.2604 (MoRT&H 14.18 (iii)) BI01010001010000000000000515BI0100001129 31.8 Rmt(Per running metre)
18 18 Providing & Laying 40 mm thick compacted Bituminous Concrete (BC) in one layer with 100-120 TPH batch type hot mix plant and with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with appropriate rollers to achieve the desired compaction as per clause No. 507 MoRT&H specification (5th Revision) 2013 for road and bridge works (5th Revision)2013 using minimum 5.4% to bitumen grade CRMB-55 as binder content by weight of total mix, complete in all respects including cost of bitumen instruction issued from time to time by MoRT&H regarding machinery & bitumen will be followed strictly. The use of self propelled mechanical paver fitted with electronic sensor device conforming to MoRT&H specification in mandatory. \n\nIf bitumen required more than 5.4% as per job mix formula no extra payment will be made, extra bitumen required will be considered as incidental to work.\nNote: - Before carrying out bituminous work, coating & stripping of bitumen aggregate mix is to be performed in accordance with IS – 6241. If coating and stripping of bitumen aggregate mix is less than 95%, anti-stripping agent will be used by contractor. The anti – stripping agent should conform to the requirement as stipulated in IS 14982:2017. The cost so incurred will be considered as incidental to work and nothing extra shall be payable. The type and brand of anti-stripping agent along with procedure shall be approved by SE-in-charge in writing before start of work. A proper record of results be maintained and same shall be submitted along with bills by the contractor. \nNote: - Where there is only BC on existing black top, cracks shall be sealed as MoRT&H specification 5th revision clause No. 3004.3, which may consists of (i) Fog seal/ or (ii) crack filling and or (iii) patch work repair as required at site in accordance with clause No. 3004.3.2, 3004.3.3 and 3004.2 of MoRT&H specification 5th revision respectively. Proper measurement and consumption shall be entered in MB for cracks sealed but no payment on this account shall be made as crack filling is incidental to work\n BI01010001010000000000000515BI0100001130 216.04 P.cum (per cubic metre)
19 19 Providing and laying 25mm thick mastic asphalt wearing course with paving grade bitumen VG-40 meeting the requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the surface, including providing antiskid surface with bitumen precoated fine-grained hard stone chipping of 13.2 mm nominal size at the rate of 0.005 cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surfaces not less than 100OC, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 516 of MoRT&H Specifications 5th revision 2013 BI01010001010000000000000515BI0100001131 3106.5 Sqm. (per square metre)
20 20 Drainage System: Providing and laying PVC drain pipes, spouts, GI steel gratings over formed holes in deck slab, fixing 150mm dia G.I. pipe runner pipes and 150 mm dia PVC down take pipes of approved quality and ISI mark at every pier etc. as per approved drawings including bends, collars, clamps, fasteners, threading etc., complete as per clause No. 2705 of MoRT&H Specifications 5th revision 2013.\n\nA)The scope of work in the item includes\n1)The providing, placing, joining and fixing the drainage pipes with all necessary fittings, tools and tackles etc., complete as per the approved drawing.\n \n2)The cost of works to make taping all points to be leak proof, tested etc. including all couplers, materials, manpower and tool and tackle etc. complete as per the direction of Engineer-in-charge.\nB) Mode of Measurement :\n1) The measurement shall be made in numbers for the drainage port supplied and installed at site. The payment for the pipes will be made in Running meters. The quantity will be restricted to the length as shown in the approved drawings.\n\na) 150 dia drainage spout with GI greeting.\n BI01010001010000000000000515BI0100001132 168 Nos (each)
21 21 Providing & Marking center line / side line 2.5mm thick (minimum) with hot applied thermo-plastic road marking paint 10 cms wide/ 15cm wide complete in all respect such as furnishing all labour, materials, tolls equipments including all incidental costs necessary for carrying out in work at site confirming to the technical specification as clause No. 803 of MORT&H specification for road and bridge works (5th revision) of 2013/ Latest edition. Each container of the thermoplastic material shall have the name trademark or other means of identification of manufacturer, batch number, date of manufacture color maximum application temperature and maximum heating temperature. The thermoplastic paint material shall be of Asian Paint-Apcomark/Berger-Sigmarc/Prismo. The glass beads shall be of Potters/Sovitec/Fleolite. The thermoplastic material shall be sampled and tested in accordance with appropriate ASTM/BS method. The contractor shall furnish to the Engineer-in-Charge a copy of certified test reports from the manufacturer of the thermoplastic material meet all requirement of the specifications. The reflector zing glass beads shall meet the requirement of clause 803.4.2 and test methods mentioned in clause 803.4.2.4 shall be meticulously followed. The minimum thickness specified is exclusive of surface of glass beads the method of thickness measurement shall be in accordance with appendix B and C of BS:3262 (part-3). \n\nNote: - Before start of work the contractor shall give brand, batch number, manufacturing date of the material to be used along with a photocopy of bill duly signed by the contractor and get approved the same from Engineer-In-Charge before use. BI01010001010000000000000515BI0100001133 256.76 Sqm (per square metre)
22 22 Providing and laying plain cement concrete M 15 grade minimum with cememt content 240 kg per cum (aggregate 20mm nominal size) below Approach slab using Ordinary Portland Cement of grade 43, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel). The rate shall include the cost of all labour, material etc complete job including bailing out water to keep the area dry as per instruction of Engineer-in-Charge. Payment shall be made based on approved plan dimensions for PCC as per clause No. 1500, 1700, 2100 & 2700 of MoRT&H Specifications 5th revision 2013. BI01010001010000000000000515BI0100001134 5.03 cum (per cubic metre)
23 23 Providing and laying reinforced cement concrete M-35 grade minimum with cememt content 350 kg per cum concrete in Approch slab using Ordinary Portland Cement of grade 43, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, centering, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (including the cost of reinforcement steel) as per clause No. 1500,1600,1700 & 2704 of MoRT&H Specifications 5th revision 2013 BI01010001010000000000000515BI0100001135 30.87 cum (per cubic metre)
24 24 Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces as per clause 803 of MoRT&H specification (MoRT&H no. 8.8) BI01010001010000000000000515BI0100001136 2836.74 Sqm(Per square metre)
25 25 Providing and applying 2 coats of water based cement paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ 1 litre for 2 sqm (MoRT&H 14.16) BI01010001010000000000000515BI0100001137 9980.4 Sqm(Per square metre)
26 26 RCC Retaining wall\n\nEarth work in excavation for Retaining Wall in all type of soils, weathered rock, existing footings, removal of boulders, concrete, ballast, stone etc including protecting the excavated sides, if required, till concreting, bailing out water to keep the area clean and dry during placement of reinforcement and concrete till the concrete sets finally. The item includes the cost of disposal of all spoils, dismantled materials, surplus earth for all leads and lifts as per clause No. 304 of MoRT&H Specifications 5th revision 2013 and to keep the work area neat and tidy during the work and thereafter. Payment shall be made based on approved plan dimensions for PCC below pile cap. The cost of backfilling around the pile cap and restoration of road, if required shall be included (MORT&H 304). BI01010001010000000000000515BI0100001138 5980.01 cum (per cubic metre)
27 27 Sand filling in foot path complete as per drawing and technical specification (Based on MoRT&H 12.3) BI01010001010000000000000515BI0100001139 1278.66 cum (per cubic metre)
28 28 Providing and laying 200/250/500mm th. granular sub base consisting of uniform layer confirming to Table 400.1 Grading –VI of MoRT&H 5th edition, mixing in a mechanical mix plant at OMC, carriage of mix material to the site of work, spreading in uniform layer with motor grader on prepared surface and compacting with vibratory power roller to achieve desired density complete as per clause No. 401 of MoRT&H specifications. Note: - 1. Only crushed metal material should be used. No local earth sand shall be used. The material finer than 425 micron shall have zero Plasticity Index (PI). 2. Material and operation manufacturing shall be approved by engineer. BI01010001010000000000000515BI0100001140 1425.99 cum (per cubic metre)
29 29 Providing and laying plain cement concrete M15 grade minimum with cememt content 240 kg per cum(aggregate 20mm nominal size) in open foundation, (Retaining Wall) using Ordinary Portland Cement of grade 43, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel). The rate shall include the cost of all labour, material etc complete job including bailing out water to keep the area dry as per instruction of Engineer-in-Charge. Payment shall be made based on approved plan dimensions for PCC as per clause No. 1500 and 1700, 2100 of MoRT&H Specifications 5th revision 2013. BI01010001010000000000000515BI0100001141 311.25 cum (per cubic metre)
30 30 Providing and laying reinforced cement concrete M-35 grade minimum with cememt content 350 kg per cum for construction of open foundation (Retaining Wall) etc. using Ordinary Portland Cement of grade 43, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering, scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, level at site using appropriate method all complete (excluding the cost of reinforcement steel). As per MoRT&H Specification for road and bridges works – 2013 (Vth revision)/ latest edition) (MORT&H 1000,1500,1700 & 2100) BI01010001010000000000000515BI0100001142 926.74 cum (per cubic metre)
31 31 Providing and laying reinforced cement concrete M-35 grade minimum with cememt content 350 kg per cum for construction of Sub Structure (Retaining Wall) etc. using Ordinary Portland Cement of grade 43, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering, scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, level at site using appropriate method all complete (excluding the cost of reinforcement steel). As per MoRT&H Specification for road and bridges works – 2013 (Vth revision)/ latest edition) (MOR T&H 1000,1500,1700 & 2100) BI01010001010000000000000515BI0100001143 1336.81 cum (per cubic metre)
32 32 Providing and laying of filter media with granular materials / stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2 of MORTH specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and technical specification as per clause 710.1.4 of IRC:78 and 2200 of MoRT&H specification (MoRT&H no. 13.10) BI01010001010000000000000515BI0100001144 459.87 Cum. (per cubic metre)
33 33 Providing weep holes in brick masonry / Plain / Reinforced concrete abutment, wing wall/Wing wall with 100 mm dia PVC pipe, extending through the full width of the structure with slope of IV :20H towards outer face. Complete as per drawing and technical specifications as per clause 2706 & 2200 of MoRT&H specification (MoRT&H no.13.8) BI01010001010000000000000515BI0100001145 1228 Nos.
34 34 Providing and fixing in position 20mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans not exceeding 10 m to cater for a horizontal movement upto 20 mm covered with sealant complete as per drawing and technical specification (MORT&H 14.18 (iii)) BI01010001010000000000000515BI0100001146 220.15 Mtr. (Per Running Metre)
35 35 APPROACH ROAD\n\nDismantling of Cement Concrete Pavement\n\nDismantling of cement concrete pavement by mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials upto all lead and lifts stacking serviceable and unserviceable materials separately. as per clause 202 of MORT&H specifications(MoRT&H No. 2.6) BI01010001010000000000000515BI0100001147 940.18 Cum. (per cubic metre)
36 36 E/Work in embankment with soil of minimum CBR of 8% obtained from borrow pit with all lead and lift transporting to site, spreading, grading to required slope and compacted to meet requirement of table 300-2 of MoRT&H specification Clause No. 305. The finished road surface will be as per X-section approved by Engineer-in-Charge. NSL for a block of 100 mtr will be worked as mean of 6 levels taken on 20 m center to center length of road. These six levels are at three locations each, one at centre and remaining two at both side edges. In case the quantity of earth work calculated with NSL and finished level is found to be less than 2629.67 cum, then actual quantity (less than 2629.67 cum) will be paid. In case quantity worked out is more than 2629.67 cum, then only 2629.67 cum will be paid. Excess quantity shall be incidental to work and nothing extra will be paid.\n\nNote: If soil of CBR 8% is not available then the agency will do appropriate stabilization as per IRC-SP—89-2010 as approved by SE-In-Charge and nothing extra shall be paid on this account and it will be incidental to work. No earth work will be allowed from PWD land. BI01010001010000000000000515BI0100001148 2629.67 Cum. (per cubic metre)
37 37 Construction of sub grade and earthern shoulders with soil of minimum CBR of 8% obtained from borrow pits with all lifts and leads transporting to site, spreading, grading to required slope and compacted to meet requirement of table 300-2 as per clause 305 of morth specifications (MORT&H 3.18) BI01010001010000000000000515BI0100001149 1563.2 Cum. (per cubic metre)
38 38 Providing, laying 150/250 mm thick spreading and compacting ( in two layers 75+75 mm/125+125 mm) graded stone aggregate to Wet Mix Macadam (WMM) specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base/base course on well prepared surface and compacting with vibratory roller to achieve the desired density as per MoRT&H specification for road & bridge (5th Revision) of 2013 as per drawing and design directed by the Engineer complete in all respects as per clause No.406. (N.S.) Note: - 1.Only crushed stone metal material should be used. No local earth/ natural occurring sand shall be used. The material finer than 425 micron shall have zero Plasticity Index (PI). 2. Materials to be used and operations of manufacturing shall be approved by engineer. BI01010001010000000000000515BI0100001150 906.87 cum (per cubic metre)
39 39 Providing & Laying 115 mm thick compacted Dense Graded Bituminous Macadam (DBM) in two layer with 100-120 TPH batch type hot mix plant and with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with appropriate rollers to achieve the desired compaction as per clause No. 505 MoRT&H specification for road and bridge works (5th edition) 2013 using minimum 4.50% to bitumen grade VG-30 as binder content by weight of total mix, complete in all respect including cost of bitumen instruction issued from time to time by MoRT&H regarding machinery & bitumen will be followed strictly. The use of self propelled mechanical paver fitted with electronic sensor device conforming to MoRT&H specification (5th edition) 2013 in mandatory.\n\nIf bitumen required more than 4.50% as per job mix formula no extra payment will be made, extra bitumen required will be considered as incidental to work.(NS)\n\nNote: - Before carrying out bituminous work, coating & stripping of bitumen aggregate mix is to be performed in accordance with IS – 6241. If coating and stripping of bitumen aggregate mix is less than 95%, anti-stripping agent will be used by contractor. The anti – stripping agent should conform to the requirement as stipulated in IS 14982:2017. The cost so incurred will be considered as incidental to work and nothing extra shall be payable. The type and brand of anti-stripping agent along with procedure shall be approved by SE-in-charge in writing before start of work. A proper record of results be maintained and same shall be submitted along with bills by the contractor.\n\nNote: - Where there is DBM on existing black top , cracks shall be sealed as MoRT&H specification 5th revision clause No. 3004.3, which may consists of (i) Fog seal/ or (ii) crack filling and or (iii) patch work repair as required at site in accordance with clause No. 3004.3.2, 3004.3.3 and 3004.2 of MoRT&H specification 5th revision respectively. Proper measurement and consumption shall be entered in MB for cracks sealed but no payment on this account shall be made as crack filling is incidental to work. BI01010001010000000000000515BI0100001151 211.09 cum (per cubic metre)
40 40 Providing and applying primer coat with bitumen emulsion (S.S grade - I) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.60 Kg/Sqm using mechanical means as per MoRT&H specification for road & bridge (5th Revision) of 2013 as per drawing and design directed by the Engineer complete in all respects as per clause No. 502. BI01010001010000000000000515BI0100001152 1835.56 Sqm(Per square metre)
41 41 Service Road.\n\nConstruction of dry lean cement concrete Sub-base over a prepared sub-grade with coarse and fine aggregate conforming to IS:383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/cum, optimum moisture content to be determined during trial length construction, concrete strenght not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonne vibratory roller, finishing and curing as per 601 of MoRT&H specification (MoRT&H 6.1) BI01010001010000000000000515BI0100001153 223.99 cum (per cubic metre)
42 42 Providing and laying 80mm thick ISI mark interlocking paver blocks confirming to IS 15658: 2006/ IRC SP 63-2004 of all shapes and collors in design mix cement M40 over a bed of 30 mm thick fine sand complete in all respect. (As per HSR 10.159 ) BI01010001010000000000000515BI0100001154 2986.5 Sqm(Per square metre)
43 43 Construction of cement concrete kerb with top and bottom width 115 and 165 mm respectively, 250 mm high in M20 grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 408 (MoRT&H 8.1 B) BI01010001010000000000000515BI0100001155 1153 Rmt(Per running metre)
44 44 Drain\n\nEarth work in excavation for drain in all type of soils, weathered rock, existing footings, removal of boulders, concrete, ballast, stone etc including protecting the excavated sides, if required, till concreting, bailing out water to keep the area clean and dry during placement of reinforcement and concrete till the concrete sets finally. The item includes the cost of disposal of all spoils, dismantled materials, surplus earth for all leads and lifts as per clause No. 304 of MoRT&H Specifications 5th revision 2013 and to keep the work area neat and tidy during the work and thereafter. Payment shall be made based on approved plan dimensions for PCC below pile cap. The cost of backfilling around the pile cap and restoration of road, if required shall be included (MORT&H 304). BI01010001010000000000000515BI0100001156 1494.54 cum (per cubic metre)
45 45 Providing and laying plain cement concrete M15 grade minimum with cement content 240 kg per cum(aggregate 20mm nominal size) in open foundation of drain etc using Ordinary Portland Cement of grade 43, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel). The rate shall include the cost of all labour, material etc complete job including bailing out water to keep the area dry as per instruction of Engineer-in-Charge. Payment shall be made based on approved plan dimensions for PCC as per clause No. 1500 and 1700 of MoRT&H Specifications 5th revision 2013. BI01010001010000000000000515BI0100001157 129.96 cum (per cubic metre)
46 46 Providing and laying reinforced cement concrete M-25 grade minimum with cememt content 330 kg per cum for construction of drain etc. using Ordinary Portland Cement of grade 43, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering, scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, level at site using appropriate method all complete (excluding the cost of reinforcement steel). As per MoRT&H Specification for road and bridges works – 2013 (Vth revision)/ latest edition) (MORT&H 1000,1500,1700 & 2100) BI01010001010000000000000515BI0100001158 693.12 cum (per cubic metre)
47 47 Rain Water Harvesting\n\nEarth work in excavation for foundation of structures , in all type of soils, weathered rock, existing footings, removal of boulders, concrete, ballast, stone etc including protecting the excavated sides, if required, till concreting, bailing out water to keep the area clean and dry during placement of reinforcement and concrete till the concrete sets finally. The item includes the cost of disposal of all spoils, dismantled materials, surplus earth for all leads and lifts as per clause No. 304 of MoRT&H Specifications 5th revision 2013 and to keep the work area neat and tidy during the work and thereafter. Payment shall be made based on approved plan dimensions for PCC below pile cap. The cost of backfilling around the pile cap and restoration of road, if required shall be included (MORT&H 304). BI01010001010000000000000515BI0100001159 472.21 cum (per cubic metre)
48 48 Providing and laying plain cement concrete M15 grade minimum with cememt content 240 kg per cum(aggregate 20mm nominal size) in open foundation of drain, etc using Ordinary Portland Cement of grade 43, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel). The rate shall include the cost of all labour, material etc complete job including bailing out water to keep the area dry as per instruction of Engineer-in-Charge. Payment shall be made based on approved plan dimensions for PCC as per clause No. 1500 ,1700 and 2100 of MoRT&H Specifications 5th revision 2013. BI01010001010000000000000515BI0100001160 13.99 cum (per cubic metre)
49 49 Providing and laying reinforced cement concrete M-35 grade minimum with cement content 350 kg per cum for construction of open foundation etc. using Ordinary Portland Cement of grade 43, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel). As per MORT&H specification for road and bridges works (5th revision) / latest edition as per clause No. 1500, 1700 & 2100 of MoRT&H Specifications - 2013 BI01010001010000000000000515BI0100001161 131.38 cum (per cubic metre)
50 50 Brick Masonry work in cement mortar 1:3 in foundation conplete excluding pointing and plastering, as per drwaing and technical specifications (MoRT&H 12.5) BI01010001010000000000000515BI0100001162 4.09 cum (per cubic metre)
51 51 Boring for hand-pump in clay, fitting strainer and pipe (b) above 75 mm dia bore, but not exceeding 100 mm dia (i) from 0 to 15 meter (As per HSR 26.10 (b) (i)) BI01010001010000000000000515BI0100001163 60 Rmt(Per running metre)
52 52 Boring for hand-pump in clay, fitting strainer and pipe (b) above 75 mm dia bore, but not exceeding 100 mm dia (i) from 0 to 15 meter (As per HSR 26.10 (b) (ii)) BI01010001010000000000000515BI0100001164 32 Rmt(Per running metre)
53 53 Providing & fixing PVC Rain water pipe 6 kg. pressure of ISI mark (b) 150 mm dia PVC pipe 6 kg. pressure, Supreme, phinolex, Prince (HSR 13.89 b) BI01010001010000000000000515BI0100001165 19.9 Rmt(Per running metre)
54 54 Providing & fixing PVC sloted pipe ISI mark. 150 mm dia Supreme, phinolex, Prince etc (N.S) BI01010001010000000000000515BI0100001166 24.32 Rmt(Per running metre)
55 55 Providing 150mm dia cowl over 150mm dia PVC pipe at the top (N.S) BI01010001010000000000000515BI0100001167 4 No (each)
56 56 Providing and placing in horizontal layers filtring media screened, washed and cleaned as described below (As per HSR 28.50)\n\na) Top layer: Filter media coarse sand 1.5 mm to 2 mm BI01010001010000000000000515BI0100001168 20 cum (per cubic metre)
57 56.1 b) Second layer: Filter media fine graded 2 mm to 4 mm BI01010001010000000000000515BI0100001169 20 cum (per cubic metre)
58 56.2 c) Third layer : Filter media course gravel 4 mm to 8 mm BI01010001010000000000000515BI0100001170 20 cum (per cubic metre)
59 56.3 d) Fourth layer : Filter media boulders 50 mm to 75 mm BI01010001010000000000000515BI0100001171 53.2 cum (per cubic metre)
60 57 Providing and fixing SFRC manhole covers and frames markd with IS: 12592 including setting the same to correct lines and levels in 1:2 cement sand mortar over manhole including carriage loading, unloading stacking, handling, re-handling etc. complete in all respect to the satisfaction of engineer-in-charge. Type: Extra heavy duty set (MD-10) 560 mm clear opening. (As per HSR 29.94) BI01010001010000000000000515BI0100001172 4 No (each)
61 58 Stair case \n\nEarth work in excavation for stair case in all type of soils, weathered rock, existing footings, removal of boulders, concrete, ballast, stone etc including protecting the excavated sides, if required, till concreting, bailing out water to keep the area clean and dry during placement of reinforcement and concrete till the concrete sets finally. The item includes the cost of disposal of all spoils, dismantled materials, surplus earth for all leads and lifts as per clause No. 304 of MoRT&H Specifications 5th revision 2013 and to keep the work area neat and tidy during the work and thereafter. Payment shall be made based on approved plan dimensions for PCC below pile cap. The cost of backfilling around the pile cap and restoration of road, if required shall be included (MORT&H 304). BI01010001010000000000000515BI0100001173 151 cum (per cubic metre)
62 59 Providing and laying plain cement concrete M15 grade minimum with cement content 240 kg per cum (aggregate 20mm nominal size) in open foundation of stair case etc using Ordinary Portland Cement of grade 43, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel). The rate shall include the cost of all labour, material etc complete job including bailing out water to keep the area dry as per instruction of Engineer-in-Charge. Payment shall be made based on approved plan dimensions for PCC as per clause No. 1500, 1700 and 2100 of MoRT&H Specifications 5th revision 2013. BI01010001010000000000000515BI0100001174 13.73 cum (per cubic metre)
63 60 Providing and laying reinforced cement concrete M-35 grade minimum with cement content 350 kg per cum for construction of open foundation etc. using Ordinary Portland Cement of grade 43, appropriate sand, aggregate, water, admixtures in suitable proportions as per approved mix design, as per approved drawings supplied by the Engineer-in-charge, including all types of shuttering, staging, centering scaffolding, necessary tools, plants, machinery, and all related operations as required to complete the work with all leads, lifts and depths true to line, level and position all complete (excluding the cost of reinforcement steel). As per MORT&H specification for road and bridges works (5th revision) / latest edition as per clause No. 1500, 1700 & 2100 of MoRT&H Specifications - 2013 BI01010001010000000000000515BI0100001175 232.11 cum (per cubic metre)
64 61 Providing, fitting and fixing mild steel railing complete as per drawing and technical specification as per MORT&H Specification clause 2703.2 and 1900. (MoRT&H 14.8) BI01010001010000000000000515BI0100001176 163.74 Rmt(Per running metre)
65 62 Precast chequered tiles of 20 mm thickness in ordinary grey cement without chips laid on 20 mm thick bed of cement coarse sand mortar 1:3 with neat cement slurry between joints and over the base in floors, treas of steps and landing (HSR 14.45 + Note) Note: In case colour chequered tiles in flooring are used, increase the throught rate of HSR item no. 14.45 by 10% BI01010001010000000000000515BI0100001177 322.8 Sqm(Per square metre)
66 63 Steel work, fixed independently without connecting plates, including cutting, hoisting and fixing in position in:- tees, angles and channels (HSR 18.1) (c) BI01010001010000000000000515BI0100001178 25.74 Qtl (per quintal )
67 64 Pavement marker Cat eye molded shank raised pavement markers made of plycarbonate and ABS moulded body and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face and shall support a load of 16000 kg tested in accordance to ASTM D 4280 Type H and complying to specifications of category A of MORTH Circular NO. W/NH/33023/10-97-DO III dt. 11.06.1997. The Height, width and length shall not exceed 50mm, 100mm, and 100mm and with min reflective area of 13 Sqcm on each side and the slope of the base shall be 35 +/- 5 degree. the strength of detachment of integrated cylindrical shanks, (of dia not less than 19 +/- 2mm and heigth not less than 30 +/- 2mm) from the bosy is to minimum value of 500 kg. Fixing will be by drilling holes on the road for the shanks to gp inside, without nails and using epoxy resin based adhesive as per manufacture recommendation and complete as directed by the engineer (of reputed make such as Avery Dennison/3M/etc) 3m c/c on ROB carriage way BI01010001010000000000000515BI0100001179 645 No (each)
68 65 Retro-Reflectorised traffic Signs\n\nProviding and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of high intensity grade sheeting vide Clouse 801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by mean of properly designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing.\n\na) 60 cm Circular BI01010001010000000000000515BI0100001180 9 No (each)
69 65.1 b) 90 cm equilateral triangle BI01010001010000000000000515BI0100001181 3 No (each)
70 65.2 c) Chevron sign board (50 cm x 60 cm rectangular) BI01010001010000000000000515BI0100001182 109 No (each)
71 66 Providing and errecting Overhead Signs including Gantry using non-metallic micro prismatic Retro Reflective sheet conforming to IRC:67-2012 Type IV specification fixed on 4mm thick Aluminium composite panels as base board with pressure-sensitive adhesive having 0.5mm thick aluminium on both sides supported by M.S. pipe structure complete as per drawings, Technical specifications and as directed by Engineer-in-Charge. (Overhead Sign Gantry (Single sided) Size (15000x1500) BI01010001010000000000000515BI0100001183 2 No (each)
72 67 Removal and disposal of garbage in all lift and lead away from site including, loading & unloading. Complete in all respects as per direction of the Engineer-in-Chief (N.S) BI01010001010000000000000515BI0100001184 6000 cum (per cubic metre)
73 68 Removal of slush/sludge from the pond approximatly 3-4 metre deep including loading/unloading and disposal of the same away from the site in all lift and lead complete in all respect as per direction on the Engineer-in-Chief. (N.S) BI01010001010000000000000515BI0100001185 6000 cum (per cubic metre)
74 69 Extra for bailing/ pumping out standing water of pond caused by spring, sub soil water, canal or river seepage and roken water mains or drains expect rain water collected in the trenches or foundation before laying concrete work. Pumping out water caused by springs, tidal or river seepage, broken water mains or drains and the like complete dewatering wherever required including pond etc BI01010001010000000000000515BI0100001186 1 Lump sum fixed
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail