Public Works Department-PWD has published Fabrication Of Prefabricated Structure Of Chief Minister Visitor Waiting Hall Near Ellerslie Main Building At Hp Sectt . Chotta Shimla. Submission Date for this Tender is 19-01-2021. Fabrication Work Tenders in Chotta Shimla Himachal Pradesh. Bidders can get complete Tender details and download the document.
Name of Work: Fabrication of prefabricated structure of Chief Minister Visitor waiting hall near Ellerslie main Building at H.P. Secretariat Chotta Shimla. | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Walls:-Supply and installation of walls will be made out of GI Steel - EPS - Steel composite sand coated in sulated sandwich panels both side 0.5MM GI sheet with toughen groove locking systems. The e.p.s used as the core will be of self-extinguishing type. The overall thickness of the panel will be 100mm in all floor level in all heights including carriage of materials in all leads and lifts. | 101 | 3905 | Per square feet |
2 | 2 | Roof:- Supply and installation of roof will constitute of Metallic color coated profiled sheet 0.6MM duly secured using SDST Screw of size-12/25and12/55 with epdm washers and further sealed with sil-icone rubber for added water protection. (Essar, Accial) in all floor level in all heights including carriage of materials in all leads and lifts. | 102 | 1150 | Per square feet |
3 | 3 | Insulation:-Supply and installation of roofing insulation bottom side will be made out of EPS/ Rockwool of 80mm fixed with GI strip in all floor level in all heights including carriage of materials in all leads and lifts. | 103 | 1150 | Per square feet |
4 | 4 | Mezzanine floor:-Supply and installation of Mezzanine floor will be made out of MS sections of size - (ISMC 150x75 box, Pipe100x100, Pipe 100x50, Pipe 80x40, ISMC 100x50 Base Plate 300mm x 300mm x 12mm, Foundation bolt 25mm Dia). Mezzanine floor coverd with fiber cement board 18MM. And all structure will be Redoxide Primer 2coat finish. (Make-Sale/Apollo/Jindal) in all floor level in all heights including carriage of materials in all leads and lifts. | 104 | 1446 | Per square feet |
5 | 5 | Superstructure :-Supply and installation Superstructure work for roofing structure comprising of MS Tubular rectangular and square 100x100, 80x40 sections with the systems of purling and portals. And all structure will be Redoxide Primer 2coat finish. (Make-Apollo/Jindal) in all floor level in all heights including carriage of materials in all leads and lifts. | 105 | 1150 | Per square feet |
6 | 6 | Electrical :-All electrical will be providing as per requirment. The switches will be of Anchor Modular type, pvc betton internal wiring insulated wire makes-RR/Polycab all MCBs make - C&S/L&T. Electrical fixtures like lights, lamps, exhaust fan and fans will be provided by the client in all floor level in all heights including carriage of materials in all leads and lifts. | 106 | 2521 | Per square feet |
7 | 7 | False Ceiling -Supply and installation of false ceiling will be gypsum plain ceiling supported of GI ceiling channels with structure pipes in all floor level in all heights including carriage of materials in all leads and lifts. | 107 | 2521 | Per square feet |
8 | 8 | Doors:- Supply and installation will be commercial 32mm wooden flush door with GI Door frame and enamel paint finish on it with accessories. (Make- Doorset/Godrej) Of size (7’x3’) 5nos, 7'x2.5'x2No. in all floor level in all heights including carriage of materials in all leads and lifts. | 108 | 8 | Per square feet |
9 | 9 | Windows:-Supply and installation windows will be made out of aluminum powder coated sliding type with all hardware’s 6No’s of size 4’x4’ with Sun shade in all floor level in all heights including carriage of materials in all leads and lifts. | 109 | 96 | Per square feet |
10 | 10 | Flooring:- Supply and fixing of floor will be made out of vitrified tiles size 600x600mm Make - Kajaria/ orient/ somany or equivalent (Base rate tile up to Rs. 45 to 55 per sq.ft.) the tiles will be fixed with cement and cores sand at one level with 4'' skatting all internal partition provosion and toilet floor antiskid tile 300mm x 300mm. in all floor level in all heights including carriage of materials in all leads and lifts. | 110 | 2500 | Per square feet |
11 | 11 | Wall Tile-Supply and fixing of toilet wall tile will be made out of size 450mm x 300mm Make - Kajaria/ orient/ somany will be fixed with cement and cores sand at one level. Up to 7’ height of the walls. (Base rate tile up to Rs 45 to 55 per sq.ft.) in all floor level in all heights including carriage of materials in all leads and lifts. | 111 | 325 | Per square feet |
12 | 12 | Toilet & Plumbing:- All internal plumbing work will be in our scope of work. Toilet will contain EWC, wash basin, Urinal 1nos economical range of Hind ware/Parry ware/Cera with required taps, shopdish, paper holder etc. External plumbing work will be not in our scope. in all floor level in all heights including carriage of materials in all leads and lifts. | 112 | 2 | Each |
13 | 13 | Finishing:-The building will be finished in stucco emboss rustic texture on the outside of the walls and plain paint with finishing of plastic emulsion will be provided on all the internal walls in all floor level in all heights including carriage of materials in all leads and lifts. | 113 | 9931 | Per square feet |
14 | 14 | Excavation in foundations, trenches etc. in all kinds of earth work including spade work, pick work, jumper work blasting work including where blasting is prohibited and chiselling/wedging out of rock etc. upto all lifts stacking the excavated soil not more than 3 metres clear from the edge of the excavation and then returning the stacked soil in 15cm layer when required into plinths, sides of foundation etc. consolidating each deposited layer by ramming and watering and then disposing of all surplus excavated earth within all leads and lifts as directed by Engineer-in-charge. | 114 | 129.47 | Per Cubic metre |
15 | 15 | Cutting in earth work in all heights / depths and in all kinds of soil such as kankar, moorum, shingle and decomposed or soft rock and hard rock including their intermediate classification and chiselling / wedging out rock where blasting is prohabited including saturated soil and filling in embankment etc., where necessary and disposal of all excavated un serviceable materials in all leads and lifts including through mechanical transporation, the disposal of unserviceable materials will be done in acquired width of the road or on approved dumping site. | 115 | 73.46 | Per cubic metre |
16 | 16 | Providing and laying cement concrete 1:6:12 (1 cement : 6 sand : 12 graded stone aggregate 40mm nominal size) and curing complete excluding cost of centring and shuttering including carriage of materials in all leads and lifts in foundations and plinth. | 116 | 12.76 | Per cubic metre |
17 | 17 | Providing and laying mechanically mixed and vibtared cement concrete 1:1.5:3 (1cement :1.5 sand :3 graded stone aggregate 20mm nominal size) and curing complete excluding cost of form work and reinforcement for feinforced concrete work :-(i) foundation footings bases of columns and the like and mass concrete in all floor level in all heights including carriage of materials in all leads and lifts. | 117 | 37.63 | Per Cubic metre |
18 | 17.01 | Columns pillars, posts and struts upt all floor level. | 118 | 17.89 | Per Cubic metre |
19 | 18 | Providing form work with steel plates 3.15mm (three point one five millimetre) thick welded with angle iron in frame 30mm x 30mm x 5mm, so as to give a fair finish including centring, shuttering, strutting and propping etc. with wooden / steel battens and ballies for all depth/ height of propping and centring below supporting floor to ceiling up to all heights and removal of the same for insitu-reinforced concrete and plain concrete work including carriage of materials within all leads and lifts and upto all floor levels:- (i) Foundation footing and basis of columns etc ansd mass concrete complete. | 119 | 102.59 | Per square metre. |
20 | 18.01 | Vertical surfaces such as walls (any thickness) partitions and the like including attached pillasters buttresses, plinth and string courses and the like. | 120 | 86.92 | Per square metre. |
21 | 19 | Providing mild steel/Tor steel reinforcement for R.C.C. work including bending, binding and placing in position complete upto floor all level in Tor steel including carriage of materials in all leads and lifts. | 121 | 12981.5 | Per kilogramme metre. |
22 | 20 | Providing and laying cement concrete 1:2:4 (1 cement:2 Sand:4 graded stone aggregate 20mm nominal size) and curing complete excluding cost of form work in foundation and plinth including carriage of materials in all leads and lifts and as directed by the Engineer in Charge. | 122 | 95.62 | Per cubic metre |
23 | 21 | Stone filling behind retaining wall per HP.PWD specification 1990 Volume - I and as per direction of the Engineer-in charge. | 123 | 30.43 | Per Cubic metre |
24 | 22 | Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 110mm dia PVC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7 including carriage of materials within all leads and lifts as per direction of Engineer-in-charge. | 124 | 38.4 | Per Running metre |