Rural Development And Panchayats Department has published Construction Of Foot Bridge At Upper Kumarpora , Panchayat Bohardar-B , Block Ramsoo , District Ramban . . ( Cd And Pyt . ) . Submission Date for this Tender is 07-12-2020. Foot Over Bridge Tenders in Ramban Jammu And Kashmir. Bidders can get complete Tender details and download the document.
Name of Work: Construction of Foot Bridge at Upper Kumarpora, Panchayat Bohardar-B, Block Ramsoo, District Ramban. | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | work in excavation by manual means over areas (exceeding 30cm in depth. 1.5m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 1 m and lift up to 1.5m,disposed earth to be levelled and neatly dressed. All kinds of soil : Including all leads, lift and carriage complete | BI01010001010000000000000515BI01000011113 | 263.24 | Cum |
2 | 2 | Providing and laying in position cement concrete 1 Cement: 5 fine sand: 10 graded stone aggregate 40 mm nominal size excluding the cost of centering and shuttering - All work up to plinth leve. Including all leads, lift and carriage complete | BI01010001010000000000000515BI0100001114 | 6.87 | Cum |
3 | 3 | Providing and laying in position RCC 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal size). Crushed excluding the cost of centering, shuttering, finishing and reinforcement, all work upto plinth level. Including all leads, lift and carriage complete | BI01010001010000000000000515BI01000011115 | 9.33 | Cum |
4 | 4 | Providing and laying in position cement concrete 1:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 20mm nominal size). Crushed, with 30 % boulders. excluding the cost of centering, shuttering, finishing and reinforcement, in walls any thickness , Columns, Pillars, Piers, Abutments, Posts and Struts. Including all leads, lift and carriage complete | BI01010001010000000000000515BI0100001116 | 102.28 | Cum |
5 | 5 | Providing and laying in position cement concrete 1:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 20mm nominal size). Crushed, excluding the cost of centering, shuttering, finishing and reinforcement, in walls any thickness , Columns, Pillars, Piers, Abutments, Posts and Struts. Including all leads, lift and carriage complete | BI01010001010000000000000515BI0100001125 | 11.25 | Cum |
6 | 6 | Providing and laying specified grade of reinforced cement concrete excluding the cost of centering, shuttering, finishing and reinforcement, all work upto plinth level. 1:1.5:3 (1 cement: 1.5 coarse sand : 3 graded stone aggregate 20mm nominal size). crushed.Including all leads, lift and carriage complete | BI01010001010000000000000515BI0100001117 | 1.5 | Cum |
7 | 7 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete . TMT bars.Including all leads, lift and carriage complete. Including all leads, lift and carriage complete | BI01010001010000000000000515BI0100001118 | 616 | Kg |
8 | 8 | Centering and shuttering including strutting, propping etc. and removal of formwork for Foundations, footings, bases of columns, etc. Including all leads, lift and carriage complete | BI01010001010000000000000515BI0100001119 | 15 | Sqm |
9 | 9 | Centering and shuttering including strutting, propping etc. and removal of formwork for Columns, Pillars, Piers, Abutments, Posts and Struts.Including all leads, lift and carriage complete | BI01010001010000000000000515BI0100001120 | 173.4 | Sqm |
10 | 10 | Centering and shuttering including strutting, propping etc. and removal of formwork for Edges of slabs and breaks in floors and walls above 20 cms wide.Including all leads, lift and carriage complete | BI01010001010000000000000515BI0100001121 | 14 | Sqm |
11 | 11 | Dry random Masonry Laid with hard stone in foundation and plinth: using nallah stone without bond stone.Including all leads, lift and carriage complete | BI01010001010000000000000515BI0100001122 | 36 | Cum |
12 | 12 | Dumping/ filling of stone boulder horiontal.Including all leads, lift and carriage complete | BI01010001010000000000000515BI0100001123 | 26.25 | Cum |
13 | 13 | Supply, Fabrication, Erection, Lunching, Railing and Painting two coats of synthetic enamal paint over a coat of approved steel primer of Steel foot bridge all complete.Including all leads, lift and carriage complete. | BI01010001010000000000000515BI0100001124 | 8.5 | Rmt |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy
For Tender Information Services Visit : TenderDetail