Madhyanchal Vidut Vitran Nigam Limited has published Schedule Of Quantum Of Works Involved In (1) Shifting/Construction Of Line For Giving 39Kw Industrial Connection To M/S Annpurna Floor Mill C/O Sri. Anoop Singh, Natveer Nagar, Lalganj Road, Bachhrawan (2) Construction Of Line For Giving Electrical Connec. Submission Date for this Tender is 29-10-2020. Transmission Line Tenders in UNDER EDD- MAHARAJGANJ Uttar Pradesh. Bidders can get complete Tender details and download the document.
Name of Work: SCHEDULE OF QUANTUM OF WORKS INVOLVED IN (1) SHIFFTING/CONSTRUCTION OF LINE FOR GIVING 39KW INDUSTRIAL CONNECTION TO M/S ANNPURNA FLOOR MILL C/O SRI. ANOOP SINGH, NATVEER NAGAR, LALGANJ ROAD, BACHHRAWAN (2) CONSTRUCTION OF LINE FOR GIVING ELECTRICAL CONNECTION TO KANHA PASHU GAUSALA, BANK OF CANAL, BACHHRAWAN (3) CONSTRUCTION OF LINE FOR GIVING ELECTRICAL CONNECTION TO EX ENGINEER, NALKOOP DIVISION FOR STW NO. 54RG AT VISHUNPUR, POST- JOHWASARKI, RAEBARELI (4) CONSTRUCTION OF LINE FOR GIVING ELECTRICAL CONNECTION TO EX ENGINEER, NALKOOP DIVISION FOR STW NO. 49RG AT AGHAURA, POST- TALA, RAEBARELI UNDER JURISDICTION OF ELECTRICITY DISTRIBUTION DIVISION-MAHARAJGANJ, RAEBARELI . | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | CARTAGE OF STORE ITEMS FORM ESC, RAEBARELI TO DUMP SITE AND DUMP SITE TO WORK SITE ALONG WITH LOADING, UN-LOADING AND PROPER STACKING | BI01010001010000000000000515BI0100001124 | ||
2 | 1.01 | 11 Mtr long ST Poles | BI01010001010000000000000515BI0100001113 | 2 | No. |
3 | 1.02 | 8.5 Mtr long PCC Poles | BI01010001010000000000000515BI0100001113 | 19 | No. |
4 | 1.03 | loose line material including ACSR WEASEL conductor Mtr. 2460.00 PVC Cable of size 25x4mm2 Mtr. 80.00 and other remanin items | BI01010001010000000000000515BI0100001113 | 4 | Job |
5 | 1.04 | Cortage of following T/F | BI01010001010000000000000515BI0100001124 | ||
6 | 1.05 | 25KVA T/F | BI01010001010000000000000515BI0100001113 | 1 | No. |
7 | 1.06 | 63KVA T/F | BI01010001010000000000000515BI0100001113 | 1 | No. |
8 | 2 | Errection | BI01010001010000000000000515BI0100001124 | ||
9 | 2.01 | Dismantling of existing line.(Approx. 60 Mtr.) | 1 | Job | |
10 | 2.02 | Eerrction of ST poles including digging of pits & fitting of accessories. | 2 | No | |
11 | 2.03 | Errection of PCC Pole including digging of Pits & fitting of accessories. | 11 | No. | |
12 | 2.04 | Errection of D/P by PCC Pole including digging of Pits & fitting of accessories. | 4 | No. | |
13 | 2.05 | Earthing of poles as per RESSPO norms. | 19 | No. | |
14 | 2.06 | Digging of pits, fixing nozzling & grouting of stay rods as per RESSPO norms including grouting materials. | 16 | No. | |
15 | 2.07 | Laying, stringing & sagging of 3Ø 3 wire HT line by ACSR weasel conductor including all associated works & making clearance of road with joints/jumpers & binding on insulators as required. | 785 | Mtr. /Length of line | |
16 | 2.08 | Laying of PVC Cable of size 25x4mm2.complete in all respect as per RESSPO norms | 80 | Mtr. /Length of line | |
17 | 2.09 | Stringing and sagging of 2 wire of 6SWG G.I. Wire for guarding and making lacing at 1 meter a part in all the spans . | 2 | Span | |
18 | 2.1 | Mounting/Errection of 11KV TPMO set. Complete in all respect as per RESSPO norms. | 2 | Set | |
19 | 2.11 | Mounting of 25 KVA T/F transformer on D/P including all associated works as required. | 1 | No | |
20 | 2.12 | Mounting of 63 KVA T/F transformer on D/P including all associated works as required. | 1 | No |