Km 7/2 - 11/4 Shifting Of Existing 11 Kv Ht/Lt Oh Lines And Double Pole Structure Along With Distribution Transformers From Km 7/2 To 11/4 To Extreme Edge Of Row In Respect Of South / Sunguvarchathiram Section Of Sriperumbudur Division In Chengalpattu Edc, Sunguvarchathiram-Tamil Nadu

Ministry Of Road Transport And Highways has published Km 7/2 - 11/4 Shifting Of Existing 11 Kv Ht/Lt Oh Lines And Double Pole Structure Along With Distribution Transformers From Km 7/2 To 11/4 To Extreme Edge Of Row In Respect Of South / Sunguvarchathiram Section Of Sriperumbudur Division In Chengalpattu Edc. Submission Date for this Tender is 10-11-2020. Distribution Transformer Tenders in Sunguvarchathiram Tamil Nadu. Bidders can get complete Tender details and download the document.




Tender Notice

25818113
Km 7/2 - 11/4 Shifting Of Existing 11 Kv Ht/Lt Oh Lines And Double Pole Structure Along With Distribution Transformers From Km 7/2 To 11/4 To Extreme Edge Of Row In Respect Of South / Sunguvarchathiram Section Of Sriperumbudur Division In Chengalpattu Edc
Open Tender
Indian
Tamil Nadu
Sunguvarchathiram
10-11-2020

Tender Details

Km 7/2 - 11/4 Shifting Of Existing 11 Kv Ht/Lt Oh Lines And Double Pole Structure Along With Distribution Transformers From Km 7/2 To 11/4 To Extreme Edge Of Row In Respect Of South / Sunguvarchathiram Section Of Sriperumbudur Division In Chengalpattu Edc

Key Value

Document Fees
Refer document
EMD
INR 51300.0 /-
Tender Value
Refer document

BOQ Items

Name of work : Accompany schedule for the work of Shifting of Existing 11 KV HT/LT OH Lines and Double Pole Structure along with Distribution Transformers from Km 7/2 – 11/4 to extreme edge of ROW in Respect of South / Sunguvarchathiram Section of Sriperumbudur Division in Chengalpattu EDC for the work of Widening of Walajabad – Sunguvarchathiram – Keelachery Road (Double Lane to Four Lane) from Km 0/0 -18/4.
Sl. No. Item Description Item Code / Make Quantity Units
1 1 Supply and fixing of RSJ pole 42' 250mm x 125 mm with Base plate including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 14 each
2 2 Supply and fixing of 11 KV AB switch with PT Insulater including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 7 set
3 3 Supply and fixing of 11 KV HG Fuse unit W/O Insulater including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 7 each
4 4 Supply and fixing of 11 KV LAS including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 21 each
5 5 Supply and fixing of 11 KV Structural Material including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 7 set
6 6 Supply and fixing of Structural Clamp including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 7 set
7 7 Supply and fixing of Stay set complete with guy including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 28 set
8 8 Supply and fixing of ACSR 7/4.09 mmraccon conductor busbar arrangement including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 140 mtr
9 9 Supply and fixing of Jumpering Materialsincluding cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 7 loc
10 10 Supply and fixing of Structure Earthing including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 7 loc
11 11 Supply and fixing of Structure Concreting including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 7 loc
12 12 Supply and fixing of M.S. Bolts & Nuts including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 14 loc
13 13 Supply and fixing of RSJ pole 42' 200mm x 100 mm with Base plate including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 49 each
14 14 Supply and fixing of RSJ pole 36' 200mm x 100 mm with Base plate including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 41 each
15 15 Supply and fixing of RCC 9.14 mtr with Pole Base plate including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 78 each
16 16 Supply and fixing of RCC 9.14 mtr pole as stud pole including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 7 each
17 17 Supply and fixing of 11 KV Tapping channel Cross arm including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., completed 31 each
18 18 Supply and fixing of V-cross arm '4-6’ including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 62 each
19 19 Supply and fixing of open type fuse unit including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 14 each
20 20 Supply and fixing of LT LAS including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 21 each
21 21 Supply and fixing of LT 2x9 KVAR Fixed Capacitor including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 7 set
22 22 Supply and fixing of LT Three phase channel cross arm including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 215 each
23 23 Supply and fixing of 11 KV HT TI Fitting including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 83 each
24 24 Supply and fixing of LT TI Fitting including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 9 each
25 25 Supply and fixing of RSJ pole Back clamp including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 242 each
26 26 Supply and fixing of RCC pole Back clamp mtr)including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 115 each
27 27 Supply and fixing of 11KV strain Disc with Metal parts including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 147 set
28 28 Supply and fixing of LT Pin Insulator with pin including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 297 each
29 29 Supply and fixing of LT Shackle with metal parts including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 368 set
30 30 Supply and fixing of LT Pin Insulator with pin including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 343 each
31 31 Supply and fixing of Aluminium knob including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 231 each
32 32 Supply and fixing of ACSR 7/4.09 mm Raccoon Conductor 11 KV HT OH line including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 8305 mtr
33 33 Supply and fixing of AAAC 7/3.35 mm Conductor for LT OH line including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 25560 mtr
34 34 Supply and fixing of Guarding Cross arm including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 46 each
35 35 Supply and fixing of GI 8 SWG for lacing (300m) including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 1380 kg
36 36 Supply and fixing of GI 6 SWG for lacing (180m) including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 1242 kg
37 37 Supply and fixing of Pole Earthing including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 168 loc
38 38 Supply and fixing of Pole Concreting including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 168 loc
39 39 Supply and fixing of M.S. Bolts & Nuts including cost and conveyance of materials and storage at section store including labour, transporting and shifting charges and all other incidental charges etc., complete 280 loc
40 40 Labour & Transport charges for re-erection of dismantled old material at new site (for loadin from old site, unloading at new site @ 10% and erection at 10% of materials at new location total 20% ( appendix A ) 1 loc
41 41 Transport Charges on this scrap materials to be devoulted to stores ( appendix D ) 1 Cubic Metre
42 42 Calculation of SubTotal, GST and Total carried out by system automatically
43 43 Sub Total Amount for above all items (excluding GST) 1 subtotal
44 44 GST 12% for above SubTotal Amount 1 gst
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail