Public Health Engineering Department-PHED has published Providing Laying And Jointing Of Distribution /Rising Main Line Under Jal Jeevan Mission For Retrofitting Of Piped Water Supply Scheme At Village – 1.Tungni 2.Tajpur Ukala 3.Uchod 4. Rasalpur 5.Chouki Nasirabad 6. Shyampur Of Block – Shujalpur Distt. Shaj. Submission Date for this Tender is 05-11-2020. Rising Mains Tenders in SHAJAPUR Madhya Pradesh. Bidders can get complete Tender details and download the document.
Name of Work: Name of work : Providing laying and jointing of Distribution /rising main line Under Jal Jeevan Mission for Retrofitting of Piped Water Supply Scheme at Village – 1.TUNGNI 2.TAJPUR UKALA 3.UCHOD 4. RASALPUR 5.CHOUKI NASIRABAD 6. SHYAMPUR of Block – SHUJALPUR Distt. SHAJAPUR based oion of R.C.C.sump well ,providing and installation of pumps at under ground sources and sump, providing, laying &jointing of pumping main and distribution pipe lines, household tap connections and electric power connections including cost of all material &labouralongwith 90 days successful trial run of entire schemes as per detailed scope of work. | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Demolishing cement concrete manually / by mechanical means including disposal of material within 50 m lead as per direction of engineer-in- charge. Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) USOR. Item.no.16.15.1-P.no.209 | 360 | Cum | |
2 | 2 | Earth work in Excavation for pipe trench in all kinds of soil and WBM in areas including dressing, watering and ramming and disposal of Excavated earth lead upto 50 meters and lift upto 1.5m, disposal earth to be leveled, neatly dressed. USOR. Item.no. 16.4 -P.no. 207 | 5420 | Cum | |
3 | 3 | Installation of HDPE pipe by Horizontal Direction Driling Method including preparing and setting up the plant and equipment, making string of new pipe material, installing new pipe string and making the system ready for commissioning by HDD operation including drilling, stringing, reaming and pulling back the new pipe on the designed bore path alngmenet, proper diposal of drilling fluid, as per code of practice for horizontal directico drilling technique suiting indian conditions. Requirement pipes / specials and other civil work shall be paid separately in all tyes of soils. (This item shall be executed only after prior permission of Superintending Engineer)\n16.3 / 207 HDPE pipe of any class - 90 mm outer dia | 3300 | m | |
4 | 4 | Providing, Laying, Jointing & field testing of High Density Polyethylene pipes, (HDPE) confirming to IS 4984/ 14151/ 12786/ 13488 with necessary jointing material like mechanical connector of jointing pipes by heating to the ends of pipes with the help of Teflon coated electric mirror/ heater to the required temperature and then pressing the ends together against each other, to form a monolithic & leak proof joint by thermosetting process. It may be required to be done with Jack/Hydraulic Jacks/ Butt fusion machine. (50 mm & above fusion jointed & below 50mm mechanical jointed) 90 mm dia HDPE 6 Kg/cm² USOR.Item.no. 9.1 -P.no.122 | 13400 | R. Mtr | |
5 | 5 | 90 mm diameter, PN 10 | 3400 | R. Mtr | |
6 | 6 | Providing and laying HDPE Bend 90º confirming to IS specifications. 90 mm - 6 Kg /cm² USOR.Item.no.9.2 -P.no.121 | 152 | Each | |
7 | 7 | Providing and laying Equal HDPE Tee confirming to IS specification. 90 mm - 6 Kg /cm² USOR.Item.no.9.4 -P.no.123 | 69 | Each | |
8 | 8 | Providing and laying including testing End Cap confirming to IS\nspecifications.90 mm - 6 Kg /cm². | 97 | Each | |
9 | 9 | Provision for inter connection of old to new pipe line with excavation of trench as per requirement/ repairing of leakage of pipe line of any diameter & type of pipe line in muddy area i/c searching of leakage point, dewatering the trench, repairing the leakage laying & jointing of pipe and specials, back filling the trench i/c testing of joints cost of labour & specials such as Djoints couplers, solvent cement etc. complete Job work as per approved specification and as directed by Engineer in charge. 90 mm diaUSOR Item.no. 17.22 / 229 | 8 | Each | |
10 | 10 | Providing & fixing of following Ductile iron double flanged sluice valves as per I.S.:14846-2000 fitted with cap including jointing & testing with cost of jointing material such as bolts, nuts, rubber insertions etc. all complete 80mm dia USOR. Item.no.4.41-P.no. 71 | 62 | Each | |
11 | 11 | Providing & fixing following cast iron double flanged single door reflux (non return) valves including jointing & testing with cost of jointing material such as bolts,nuts and rubber insertion all complete as per IS :5312 (Part I) 80 mm USOR. Item.no.8.4 a -P.no 113 | 7 | Each | |
12 | 12 | Filling available excavated earth in trenches, lead up to 50m and lift upto 1.5 m in all kind of soil excluding watering and ramming. USOR. Item.no. 16.10b -P.no 208 | 5340 | Cum | |
13 | 13 | Providing and fixing of ISI marked PVC insulated three core flat copper cable. 4 SQ MM USOR.Item.no. 24.20.102 -P.no 262 | 2370 | Sq mm | |
14 | 14 | Providing and jointing of following galvanized Iron (MS) Pipes class medium with heavy duty seamless sockets for lowering of submersible pumps including testing of joints, cost of pipes & heavy duty sockets and jointing materials all complete. Pipes and sockets confirming to IS:1239-2011 Part-II. 50 mm dia, class medium with heavy duty seamless sockets 2 nd ADDENDUM OF UNIFIED SCHEDULE OF RATES (USOR) w.e.f. 03.07.2018 item no 17.38.1 page 3 | 1260 | R Mtr | |
15 | 15 | 65 mm dia class medium Amnd II I.no.17.38-P.no. 3 | 96 | R Mtr | |
16 | 16 | Supplying & Installation of Energy efficiant five star BEErating ISI Marked required capacity of Three Phase, 50 Hz,415V, deep well submersible pump Steel body, suitable for6"tube well with Control Panel Starter suitable for Submersible pump with dry run protection, single phase preventer, connections, including clamps, bore cap etc. as required as per specifications but excluding pipe andconnection cable.10 H.P. with 20 stages, Head Mt. 184-80 DischargeLPM 60-270 PHE USOR 24.20.106/267 | 11 | Each | |
17 | 17 | Supplying & Installation of Five star BEE rating ISI Marked required capacity of Three phase, 50 Hz, 415V, Open well Submersible pump, with Control Panel Starter with Dry Run Protection, single phase preventer, connections, etc. as required as per specifications but excluding pipe and connection cable. 5.0 H.P. Head Mt.15-24, Discharge LPM 930-420. (USOR. Item. No.24.20.112 (ii) - P.No. 268) | 8 | Each | |
18 | 18 | Providing and laying mechanically mixed cement concrete with crushed stone aggregate excluding centering and shuttering (with 20 mm nominal sizegraded stone aggregate) M-15 USOR. 16.23(a)iiI/217 | 360 | cum | |
19 | 19 | Construction of Brick masonry valve chamber ;ithr0 .. thick wall in t:6 C.M. with l2mm thick l:4 Cement plasterand base course [0 cm. thick in M-15. Inside Dimensions 110x80xl00cm with M-20 RCC chamber cover size l50cm x l20cm x liim including cost of materials, labour etc. complete. ENC Letter No. 254 Dated 06.08.2020 Item No. 17.45.1/7 | 62 | Each | |
20 | 20 | Provision for jointing of Rising Main to sump well / OHT and OHT to distribution pipe line with cost of material/ specials such as bends, MTA , FTA, Tee, Flange etc as per requirement of site with excavation, labour as per requirement complete as per approved specifications and as directed by Engineer incharge [ I-17.20/229] | 6 | Job | |
21 | 21 | Provision for jointing of TW to sump well / with cost of material/ specials such as bends, MTA , FTA, Tee, Flange etc as per requirement of site with excavation, labour as per requirement complete as per approved specifications and as directed by Engineer incharge [ I-17.19/229] | 6 | Job | |
22 | 22 | Providing and making Consumer Service Connection (Functional House Hold Taps Connection) from HDPE pipe with the help of electro fusion machine including all labour and material such as Electro fusion Saddle, brass ferrule (Not less than 100 gm in weight)/MDPE ferrule/flow control valve,double compression elbow, male/female threaded adopter with metal insert, sockets, MDPE union 20mm dia/GI union 15 mm dia (medium class), brass/SS tap etc all complete and all items/fittings shall be complying with the relevant BIS Codes. Rates also include excavation, cutting of road if required,refilling the trenches and restoration of road with minimum M20 (1:1.5:3) grade CC or equivalent grade of existing CC cutting for providing tap connection (whichever is richer), construction of Platform and grouting of circular post neat finished as per the drawing attached, testing all complete items.\n For connection with 15 mm dia GI Pipe upto 5 meter and CONCRETE ROAD CROSSING is necessary. 2nd ADDENDUM OF UNIFIED SCHEDULE OF RATES (USOR) w.e.f. 03.07.2018 item no 17.42 page 5 | 293 | Each | |
23 | 23 | Providing and making Consumer Service Connection (Functional House Hold Taps Connection) from HDPE pipe with the help of electro fusion machine including all labour and material such as Electro fusion Saddle, brass ferrule (Not less than 100 gm in weight)/MDPE ferrule/flow control valve,double compression elbow, male/female threaded adopter with metal insert, sockets, MDPE union 20mm dia/GI union 15 mm dia (medium class), brass/SS tap etc all complete and all items/fittings shall be complying with the relevant BIS Codes. Rates also include excavation, cutting of road if required,refilling the trenches and restoration of road with minimum M20 (1:1.5:3) grade CC or equivalent grade of existing CC cutting for providing tap connection (whichever is richer), construction of Platform and grouting of circular post neat finished as per the drawing attached, testing all complete items.\n For connection with 15 mm dia GI pipe upto 5 meter and road crossing is not required. (Distribution pipe line is on the same side of house). 2nd ADDENDUM OF UNIFIED SCHEDULE OF RATES (USOR) w.e.f. 03.07.2018 item no 17.42.3 page 5 | 292 | Each | |
24 | 24 | Providing and making Consumer Service Connection (Functional House Hold Taps Connection) from HDPE pipe with the help of electro fusion machine including all labour and material such as Electro fusion Saddle, brass ferrule (Not less than 100 gm in weight)/MDPE ferrule/flow control valve, double compression elbow, male/female threaded adopter with metal insert, sockets, MDPE union 20mm dia/GI union 15 mm dia (medium class), brass/SS tap etc all complete and all items/fittings shall be complying with the relevant BIS Codes. Rates also include excavation, cutting of road if required, refilling the trenches and restoration of road with minimum M20 (1:1.5:3) grade CC or equivalent grade of existing CC cutting for providing tap connection (whichever is richer), construction of Platform and grouting of circular post neat finished as per the drawing attached, testing all complete items\nitems. 2nd ADDENDUM OF UNIFIED SCHEDULE OF RATES (USOR) w.e.f. 03.07.2018 item no 17.41 page 4 | 349 | Each | |
25 | 25 | Providing and making Consumer Service Connection (Functional House Hold Taps Connection) from HDPE pipe with the help of electro fusion machine including all labour and material such as Electro fusion Saddle, brass ferrule (Not less than 100 gm in weight)/MDPE ferrule/flow control valve,double compression elbow, male/female threaded adopter with metal insert, sockets, MDPE union 20mm dia/GI union 15 mm dia (medium class), brass/SS tap etc all complete and all items/fittings shall be complying with the relevant BIS Codes. Rates also include excavation, cutting of road if required,refilling the trenches and restoration of road with minimum M20 (1:1.5:3) grade CC or equivalent grade of existing CC cutting for providing tap connection (whichever is richer), construction of Platform and grouting of circular post neat finished as per the drawing attached, testing all complete items.\nFor connection with 20 mm dia MDPE pipe upto 5 meter and road crossing is not required. (Distribution pipe line is on the same side of house)\n2nd ADDENDUM OF UNIFIED SCHEDULE OF RATES (USOR) w.e.f. 03.07.2018 item no 17.43.3 page 5 | 198 | Each | |
26 | 26 | Electrical Items - 11 KV line on 140 kg. 8.0 Mtrs. long PCC Poles with rabbit conductor average span of 70 mtr. in rural area Including labour Complete. (Schedule Ref. C-1.2 of MPPKVVCL SOR 2019-20) | 3.22 | Per Km | |
27 | 27 | 11 KV D.P. Structures on 140 kg. 8.0 mtr. long PCC poles for tapping DP Including labour Complete. (Schedule Ref. C-5.2 of MPPKVVCL SOR 2019-20) | 7 | Each | |
28 | 28 | 11 KV D.P. Structures on 140 kg. 8.0 mtr. long PCC poles for straight line Including labour Complete. (Schedule Ref. C-5.1 of MPPKVVCL SOR 2019-20) | 7 | Each | |
29 | 29 | 11/0.4 KV out-door type transformer sub-station. 25 KVA on 140 kg. 8.0 meter long PCC Pole Including labour Complete. (Schedule Ref. E-1.1 of MPPKVVCL SOR 2019-20) | 7 | Each | |
30 | 30 | L.T. Line 1 phase 3 wire on PCC support using Aerail Bunched XLPE cable with maximum span of 50 Meter. Including labour Complete. 2 x 35+ 1 x 16 sq. mm (Insulated nuetral massenger) (Schedule Ref. D-3.2 of MPPKVVCL SOR 2019-20) | 2.05 | Per Km | |
31 | 31 | Supply & errection of ready made mini pump house (control pannel box) GI sheet of 18 gauge of size 90cmx90cmx60cm with 40x40x5mm angle Iron frame to fix it 200 mm below ground level with hold fasts grouted in foundation and 300 mm above ground level for clearance suitable for fixing of conrol pannel, fuse unit, main switch etc. as per aproved specification. (USOR PHE Item No.17.18 P-No. 228) | 7 | Job | |
32 | 32 | Supply, delivery, erection and commissioning of the micro processor based water disinfection equipment using silver ionization process based on Oligodynamic technology as per detailed \nspecifications mentioned in the NIT, 5000LPH | 2 | Nos | |
33 | 33 | Supply, delivery, erection and commissioning of the micro processor based water disinfection equipment using silver ionization process based on Oligodynamic technology as per detailed specifications mentioned in the NIT, 10000LPH | 2 | Nos | |
34 | 34 | Design, Drawing, construction, testing and commissioning of GSR/ Sumpwell of following capacity with all necessary fitting and accessories as mentioned in relevant chapter of USOR, IS codes and departmental circulars. complete turnkey job for following -RASALPUR 75 KL (USOR Amndm - II, Itm-26.2.1 / Pg 17) | 1 | Nos | |
35 | 35 | Design, Drawing, construction, testing and commissioning of GSR/ Sumpwell of following capacity with all necessary fitting and accessories as mentioned in relevant chapter of USOR, IS codes and departmental circulars. complete turnkey job for following (USOR Amndm - II, Itm-26.2.1 / Pg 17) Tungni 40 KL, Shyampur-40KL | 2 | Nos | |
36 | 36 | Design, Drawing, construction, testing and commissioning of GSR/ Sumpwell of following capacity with all necessary fitting and accessories as mentioned in relevant chapter of USOR, IS codes and departmental circulars. complete turnkey job for following - (USOR Amndm - II, Itm-26.2.1 / Pg 17) Tajpur Ukala 50 kl | 1 | Nos | |
37 | 37 | Design, and construction of RCC framed brick masonary pump house over the sumpwell with all necessary fitting and requirements as mentioned in relevant chapter of USOR. IS codes and departmental guidelines complete turnkey job (USOR Amndm - II, Itm-26.3./ Pg 18) | 4 | Nos |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy