Public Works Department-PWD has published Erection And Dismantling Of Pantoon Bridge On Ganga River At Bachchalpur Ghat Between Semara Sherpur And Rewatipur Rampur. Submission Date for this Tender is 26-10-2020. Bridge Work Tenders in Ghazipur Uttar Pradesh. Bidders can get complete Tender details and download the document.
Name of Work: Erection & Dismentalling of Pantoon Bridge on Ganga River at Bachchalpur Ghat Between Semara Sherpur and Rewatipur Rampur(2020-21) | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Supply of wooden anchors made of Euqiliptis ballies of standerd design of size 2.80 x 1.80 x 1.80 M. with dofferent size of ballies. Mallahi, nails and i/c cost of cartage labour and T&P etc. complete.(as per schedule pg 27 item no 29) | 90 | Nos | |
2 | 2 | Supply of 28 mm. dia garware Garphy poly propline ISI mark rope for anchoring of pantoons i/c cost of materials its loading , unloading cartage upto Bachchalpur ghat store ..(as per schedule pg 28 item 39) | 7000 | Kg | |
3 | 3 | S/O sand filled plastic E.C. bags (Valume 1 Cft ) i/c cost of sand , bags labour stiching with sutly complete and cartage upto place of anchoring . (as per schedule pg 27 item no.2) | 22000 | Nos | |
4 | 4 | S/O malahi nails 15cm to 30cm long of approved make and good quality . (as per schedule pg 27 item no 11) | 5 | Qtl | |
5 | 5 | S/O Euqiliptis ballies of dia150mm i/c cost of materials cartage upto site and loading , unloading etc. at Bachchalpur ghat store .(as per schedule pg 28 item no 35(a)) | 50 | Rm | |
6 | 6 | S/O Euqiliptis ballies of dia120mm i/c cost of materials cartage upto site and loading , unloading etc. at Bachchalpur ghat store .(as per schedule pg 28. | 50 | Rm | |
7 | 7 | S/O Euqiliptis ballies of dia100mm i/c cost of materials cartage upto site and loading , unloading etc. at Bachchalpur ghat store .(as per schedule pg 28. | 50 | Rm | |
8 | 8 | S/O nut bolts of 300x30 mm size i/c cost of all materials cartage upto site etc. complete .as per page no.27 | 8 | Qtl | |
9 | 9 | S/O nut bolts of 150x30 mm size i/c cost of all materials cartage upto site etc. complete .as per page no.27 | 7 | Qtl | |
10 | 10 | S/O nut bolts of 300x16 mm size i/c cost of all materials cartage upto site etc. complete .as per page no.27 | 2 | Qtl | |
11 | 11 | Supply of railing wire clamp i/c cost of all materials cartage upto site etc complete. (as per schedule pg 27 item no 10) | 10 | Nos | |
12 | 12 | S/O wire rope (Steel coated) 20 mm dia i/c cost of all materials cartage upto site etc. complete for railing post .(as per schedule pg 28 item no 40) | 90 | Rm | |
13 | 13 | S/O wire rope (Steel coated) 10 mm dia i/c cost of all materials cartage upto site etc. complete for railing post .(as per schedule pg 28 | 500 | Rm | |
14 | 14 | S/O U clamp for clamping chequred plates i/c cost of all materials cartage upto site etc. complete .(as per schedule pg 27 item no 9) | 750 | Nos | |
15 | 15 | Carrying of pantoon pairs from the place of anchoring (down steram side of the bridge) top the alignment of bridge in water and fixing the same with other pantoon pair and refixing the same and bridge alignment.(as per schedule pg 25 item no 3a) | 53 | Pair | |
16 | 16 | Cartage of the R.S. Joist from Bachchalpur ghat store to bridge site and laying fixing them on bridge and approaches .(as per schedule pg 29 item no 9) | 192 | Nos | |
17 | 17 | Cartage of the Nut bolts from Bachchalpur ghat store to bridge site and laying fixing them on bridge and approaches .(as per schedule pg 29 | 30 | Qtl | |
18 | 18 | Cartage of the Coir rope / PP rope from Bachchalpur ghat store to bridge site and laying fixing them on bridge and approaches .(as per schedule pg 29 | 70 | Qtl | |
19 | 19 | Cartage of the Chequered plates from Bachchalpur ghat store to bridge site and laying fixing them on bridge and approaches .(as per schedule pg 29 | 856 | Nos | |
20 | 20 | Cartage of the Railing post from Bachchalpur ghat store to bridge site and laying fixing them on bridge and approaches .(as per schedule pg 29 | 600 | Nos | |
21 | 21 | Carrying of wooden anchor from store to site.(as per schedule pg 25 item no 12) | 90 | Nos | |
22 | 22 | Laying of wooden anchor in the river on the up stream and down stream side of pantoon bridge i/c their weaving and packing with sand filled bags average 90 bags before laying and fixing the pantoon with sisal / coire rope as directed by E/I. (as per schedule pg 25 item no 6) | 80 | Nos | |
23 | 23 | Levelling and dressing (4 cm.) deep of road before laying chequred plate. | 6000 | Sqm | |
24 | 24 | Relaying of chequred plates after making camber by spreading of local sand (as per schedule pg 25 item no 13) | 856 | Nos | |
25 | 25 | Cartage the Sal sleeper from Bachchalpur ghat store to Bachchalpur ghat pantoon bridge and laying / fixing indecking of bridge etc. complete .(as per schedule pg 25 item no 9) | 2248 | Nos | |
26 | 26 | Cartage the Sal edging from Bachchalpur ghat store to Bachchalpur ghat pantoon bridge and laying / fixing indecking of bridge etc. complete .(as per schedule pg 25 item no 9) | 500 | Nos | |
27 | 27 | Carrying and spreading kansa poola on the bridge way and filling 2" kapsa soil over it i/c ramming dressing the surface complete .(as per schedule pg 26 item no 15) | 2140 | Sqm | |
28 | 28 | fixing of 20 mm. dia wire rope stay complete all as directed by E/I. | 4 | Nos | |
29 | 29 | Clamping of Chequared plates with U clamp and nut bolts all as directed by E/I. Labour Only | 428 | Pair | |
30 | 30 | Fixing of 10 mm. wire rope in railing post . | 2880 | Rm | |
31 | 31 | Earth work in cutting or embankment in ordinary soil excavated to be in the form regulers pits not exceeding 50 cm. in depth work and earth work in 20 cm. layers i/c ramming dressing the surface to be required levels and slopes and also i/c 1.20 ft. and 30 leads as per direction of E/I. | 1100 | cum | |
32 | 32 | Disposal of local sand / earth from Rampur side i/c loading unloading 2 km. cartage and duly stacked along chequred plate as per direction by E/I. | 100 | cum | |
33 | 33 | Extraction of railing wire from railing post and making rolles etc .(as per schedule pg 29 item no 3) | 2800 | Rm | |
34 | 34 | Desmenteling and carrying railing post fixed in position i/c opening of 300 x 16 mm. nut bolts loading unloading cartege and dully stacked at store yard of Bachchalpur ghat Pantoon Bridge aprox lead 3 km. (as per schedule pg 29 item no 5) | 600 | Nos | |
35 | 35 | Dismenteling and carrying sal edging fix over sleepers i/c loading unloading cartege and duly stacked at store yard of Bachchalpur ghat Pantoon Bridge approx lead 3 km. (as per schedule pg 29 item no 6) | 500 | Nos | |
36 | 36 | Dismenteling of sal sleepers in decking over the bridge i/c cleaning of kapsa soil and kansa loading unloading carrige and duly stacked at store yard of Bachchalpur ghat Pantoon Bridge aprox lead 3 km. (as per schedule pg 29 item no 7) | 1800 | Nos | |
37 | 37 | Carrying the R.S. joists (Spliced ) 5-10 m. between two pantoon after dismentelint of pantoon paires i/c loading unloading cartege and duly stacked at store yard of Bachchalpur ghat Pantoon Bridge approx lead 3 km. (as per schedule pg 29 item no 8) | 192 | Nos | |
38 | 38 | Dismenteling of chequared plates from the bridge and approch i/c loading in truck and cartage unloading and dully stacked at store yard of Bachchalpur ghat Pantoon Bridge approx lead 3 km. | 800 | Nos | |
39 | 39 | Carrying the pantoon paires after dismenteling to the safe bank of the river in water and anchoring them properly all as directed by E.I. aprox lead 3 km. (as per schedule pg 25 item no 3a) | 53 | Pair | |
40 | 40 | Cartege of different materials after dismenteling such as nut bolts , rope and railing wire etc. aprox lead 3 km. (as per schedule pg 29 item no 11) | 15 | Qtl | |
41 | 41 | Opening of U claimp from chequred plate .(as per schedule pg 27 item no 19) | 400 | Pair |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy