Southern Railway-SR has published Podanur- Shoranur Section-Ancillary Works In Connection With Deepscreening Of Ballast For A Total Length Of 30.700Km (With Bcm For A Length Of 29.700 Km And By Manual For A Length Of 1.000Km) Including Destressing Of Lwr (Location As Per Annexure). Submission Date for this Tender is 02-11-2020. Ballast Tenders in Kerala. Bidders can get complete Tender details and download the document.
0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
---|---|---|---|---|---|---|---|---|---|
0 | S.No. | Item\rCode | Item Qty | Qty Unit | Unit Rate | Basic Value | Escl.(%) | Amount | Bidding\rUnit |
1 | Schedule B-PTJ-SRR section: Ancillary works in connection with BCM | 17631076.00 | |||||||
2 | 1 | NS1 | 30700.00 | Per Track\rMetre | 66.00 | 2026200.00 | AT Par | 2026200.00 | Rs. |
3 | Description:- Screening of left over ballast after BCM working in the shoulder portion of track and putting back\rthe screened ballast in tamping zone, spreading evenly to achieve uniform profile including boxing of ballast\rdisposing the muck as directed for repair of cess/ slopes of bank/ leading outside cutting and deposited in such\raway that it would not come back to track/side drain/ catch water drain during rainy season, lowering / cutting of\rcess where ever required with all contractors labour, tools, plant, implements with all lead lift / descent as directed\rby the Engineer in charge at site. | ||||||||
4 | 2 | NS2 | 29200.00 | Per Track\rMetre | 2.60 | 75920.00 | AT Par | 75920.00 | Rs. |
5 | Description:- Removal of deep screened muck thrown by BCM lying by side of Track on cess/on slopes of\rcutting, leveling to profile in bank including leading and making up cess where ever required to desired level with\rall contractors labour, tools, plant, implements with all lead lift / descent as directed by the Engineer in charge at\rsite. | ||||||||
6 | 3 | NS3 | 1500.00 | Per Track\rMetre | 39.00 | 58500.00 | AT Par | 58500.00 | Rs. |
7 | Description:- Removal of deep screened muck from cuttings, platforms and station yards including leading and\rdumping away from the track in such a way that it would not come back to track/side drain during rainy season\rwith all contractors labour, tools, plant, implements with all lead lift / descent as directed by the Engineer in\rcharge at site. | ||||||||
8 | 4 | NS4 | 123.00 | Per Unit | 5753.00 | 707619.00 | AT Par | 707619.00 | Rs. |
9 | Description:- Assisting\rBCMfordaytodayroutineworklikegreasing,oiling,providing/removingcutter\rbar,opening of track,putting back ballast,removal of obstructions, working behind BCM including providing labour\rfor cleaning dust and dirt, muck etc accumulated in track machines, carrying of tools and equipments from/ to\rmachine to satation yard, daily for all days of BCM machine working and on maintenance day till the departure of\rtrack machines after completion of deep screening work in the section with all contractors labour, tools, plant with\rall lead lift / descent as directed by the Engineer in charge at site.The contractor has to arrange labour for one\rBCM Group of machines. (One BCM group means 1 BCM, 1 Tamping machine and 1 DTS machine.) NOTE: Unit\rof this item is "PER DAY FOR EACH BCM" |