State Infrastructure And Industrial Development Corporation Of Uttarakhand Limited-SIIDCUL has published Annual Operation & Maintenance Of Electrical Infrastructure Of Street Lights And Water Supply At Iie-Selaqui. Submission Date for this Tender is 25-08-2020. Coats and Jackets Tenders in Selaqui Dehradun Uttarakhand. Bidders can get complete Tender details and download the document.
Name of Work: Annual Operation & Maintenance of Electrical Infrastructure of Street Lights and Water Supply at IIE-Selaqui | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Street Light Maintenance, Pump House Maintenance with AMC of Electrical Items | |||
2 | 1.01 | Lifting Vehical / Hydra required for Overhead street lights Maintenance purpose ( On hire Basis) (02days /month) | item1 | 16 | Days |
3 | 1.02 | Repair of 60Watt LED street lights by replacement of damaged/diffused drivers 60Watt Make-C&S., Phillips, Havells, Bajaj ( as per the site requirement) including material charges but excluding labour charges , for Pharma City Selaqui. DLP 6 Months | item2 | 30 | Nos |
4 | 1.03 | Repair of 60Watt LED street lights by replacement of damaged/diffused PCB plates 60Watt Make-C&S., Phillips, Havells, Bajaj ( as per the site requirement) including material charges but excluding labour charges for Pharma City, Selaqui. DLP 6 Months. | item3 | 7 | Nos |
5 | 1.04 | Repair of 90Watt LED street lights by replacement of damaged/diffused drivers 90Watt Make-C&S., Phillips, Havells, Bajaj ( as per the site requirement) including material charges but excluding labour charges for SIDC Selaqui. DLP 6 Months. | item4 | 48 | Nos |
6 | 1.05 | Repair of 90Watt LED street lights by replacement of damaged/diffused PCB plates 90Watt Make-C&S., Phillips, Havells, Bajaj ( as per the site requirement) including material charges but excluding labour charges. DLP 6 Months. | item5 | 24 | Nos |
7 | 1.06 | Repair of 150Watt LED High Mast Lights by replacement of damaged /diffused drivers 150watt Make -C&S., Phillips, Havells, Bajaj ( as per the site requirement ) including material charges but excluding labour. DLP 6 Months | item6 | 9 | Nos |
8 | 1.07 | Repair of LED High Mast Lights replacing damaged/diffused PCB plates 150Watt Make -C&S., Phillips, Havells, Bajaj ( as per the site requirement ) including material charges but excluding labour. DLP 6 Months. | item7 | 4 | Nos |
9 | 1.08 | Repairing of street lights / High Mast Electrical Control panel replacing 3Pole power contactor 100Amp including material charges but excluding labour. One in each, total 02 panels ( as per the requirement raised by Engineer-IN charge) | item8 | 2 | Nos |
10 | 1.09 | Repairing of street lights / High Mast Electrical Control panel replacing Timer Auto Light, including material charges but excluding labour. One in each, total 02 panels ( as per the requirement raised by Engineer-IN charge) | item9 | 2 | Nos |
11 | 1.1 | Repairing of street lights / High Mast Electrical Control panel replacing 3pole MCCB,100Amp including material charges but excluding labour. One in each, total 02 panels ( as per the requirement raised by Engineer-IN charge) | item10 | 2 | Nos |
12 | 1.11 | Repairing of street lights / High Mast Electrical Control panel replacing Isolator 02 way 40 Amps including material charges but excluding labour. 02 in each, total 02 panels ( as per the requirement raised by Engineer-IN charge) | item11 | 4 | Nos |
13 | 1.12 | Replacing the burnt/damage pvc 1.5 sqmm single core wire by required size of FRLS copper cable excluding labour. | item12 | 508 | RM |
14 | 1.13 | Supply of PVC xlpe power cable 1.1 kv grade armoured size 4x 16 sqmm excluding labour | item13 | 325 | RM |
15 | 1.14 | Laying of one number PVC insulated & PVC sheatehed/ xlpe power cable 1.1 kv grade upt o 35sqmm size direct in ground inclduing excavation sand cushioning protective covering and refilling the trench extra as required. | item14 | 325 | RM |
16 | 1.15 | Erection of STEEL TUBLER OR RAIL POLE strut in cement concrete 1:3:6 foundation i(aggregate 40mm nominal size) including excavation and refilling and secured with holding clamps, bolts, nuts etc required ( DSR 11.4) | item15 | 6 | Nos |
17 | 1.16 | Supply and Fixing of pre-fab water proof street light pole boxes( powder coated chocolate colour ) size 300mm X 00MM X150MM mada of CRCA sheet of thickness 1.6mm with arrangement /connection of 3phase incoming and outgoing supply and 01 nos 06amp B-curve MCB complete in all respect | item16 | 10 | Nos |
18 | 1.17 | Wages /Labour charges paid to Electricians deputed at respective Industrial estates of SIIDCUL for O&M work (for 8months) | item17 | 1 | Nos |
19 | 1.18 | Wages /Labour charges paid to Helpers deputed at respective Industrial estates of SIIDCUL for O&M work( for 8 Months) | item18 | 1 | Nos |
20 | 1.19 | Annual Maintenance of Main supply Transformer for Street Lights inclduing Dehydration of transformer Oil, OTI / WTI Calibration etc.( once in year ) | item19 | 1 | Job |
21 | 1.2 | Service charges of DG sets (50KVA) installed at SIIDCUL offices / Back Up Projects of Street Lights inclduing material and Labour. ( 02 services per year ) | item20 | 2 | Nos |
22 | 1.21 | Repairing and Rewinding of 35HP motor submersibile tubewell complete in all respect including lowering and lifting upto 150 meter , labour & Material ( as per requirement ) | item21 | 1 | Nos |
23 | 1.22 | Repairing of 35HP/10 stage submersibile pump by repair/ replacement of pump-bush, sleeves, necking etc. complete in all respect inclduing labour & material. ( as per requirement) | item22 | 1 | Nos |
24 | 1.23 | Repairing of submersibile motor control Electrical panel by replacing 01 no ML4 contactor including material & excluding labour ( as per the requirement raised by Engineer-IN charge) | item23 | 1 | Nos |
25 | 1.24 | Repairing of submersibile motor control Electrical panel replacing 01 no 200Amp Kit Kat switch complete in all respect including material & excluding labour. ( as per the requirement raised by Engineer-IN charge) | item24 | 1 | Nos |
26 | 1.25 | Repairing of submersibile motor control Electrical panel by replacing 200Amp TPN SFU complete in all respect including material & excluding labour. ( as per the requirement raised by Engineer-IN charge) | item25 | 1 | Nos |
27 | 1.26 | Replacement of power cable (3x6sqmm ) for supply to submersibile motor pump complete in all respect including material & labour charges. ( as per requirement) | item26 | 32 | Nos |
28 | 1.27 | Rewinding & Repairing of 15HP water supply Motor with taking out and fixing in position complete in all respect inclduing material and Labour charges. | item27 | 1 | Nos |
29 | 1.28 | Repairing of Water Supply motor control Electrical panel replacing 01 no 200Amp Kit Kat switch complete in all respect including material & excluding labour. ( as per the requirement raised by Engineer-IN charge) | item28 | 1 | Nos |
30 | 1.29 | Repairing of Water supply motor control Electrical panel by replacing 200Amp TPN SFU complete in all respect including material & excluding labour. ( as per the requirement raised by Engineer-IN charge) | item29 | 1 | Nos |