Upgradation Of 66 Kv Substation Sulthan Bathery Construction Of Column Foundation And Cable Trench Earthwork Excavation Pcc Rcc 1 1 . 5 3 Centering Shuttering Steel Reinforcement Laterite Masonry Brick Work Plastering Structural Steel Work Filling P, Sulthan Bathery Wayanad-Kerala

Kerala State Electricity Board-KSEB has published Upgradation Of 66 Kv Substation Sulthan Bathery Construction Of Column Foundation And Cable Trench Earthwork Excavation Pcc Rcc 1 1 . 5 3 Centering Shuttering Steel Reinforcement Laterite Masonry Brick Work Plastering Structural Steel Work Filling P. Submission Date for this Tender is 05-08-2020. Substation Tenders in Sulthan Bathery Wayanad Kerala. Bidders can get complete Tender details and download the document.




Tender Notice

24786460
Corrigendum : Upgradation Of 66 Kv Substation Sulthan Bathery Construction Of Column Foundation And Cable Trench Earthwork Excavation Pcc Rcc 1 1 . 5 3 Centering Shuttering Steel Reinforcement Laterite Masonry Brick Work Plastering Structural Steel Work Filling P
Open Tender
Indian
Kerala
Sulthan Bathery Wayanad
05-08-2020

Tender Details

Upgradation Of 66 Kv Substation Sulthan Bathery Construction Of Column Foundation And Cable Trench Earthwork Excavation Pcc Rcc 1 1 . 5 3 Centering Shuttering Steel Reinforcement Laterite Masonry Brick Work Plastering Structural Steel Work Filling Placing Of Cover Slab

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 13-Jul-2020 Time of completion of work Other 27-07-2020
2 28-Jul-2020 Time extension Notice Date 05-08-2020

Key Value

Document Fees
INR 5900 /-
EMD
INR 85000.0 /-
Tender Value
INR 33.96 Lakhs /-

BOQ Items

Name of Work: Upgradation of 66kV substation Sulthan Bathery-Construction of column foundation and cable trench
Sl. No. Item Description Item Code / Make Quantity Units
1 1 Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50m. in All kinds of soil. 350 m3
2 2 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:3:6 (1 Cement : 3 coarse sand (zone-III): 6 graded stone aggregate 40 mm nominal size) 55 m3
3 3 Providing and laying in position specified grade of Reinforced Cement concrete, excluding the cost of centering,shuttering,finishing and reinforcement-All work upto plinth level. 1:1.5:3(1cement:1.5coarse sand:3graded stone aggregate 20mm nominal size) 100 m3
4 4 Centering and shuttering including strutting,propping etc. and removal of form for foundations,footings, base of column etc. for mass concrete. 400 m2
5 5 Centering and shuttering including strutting, propping etc. and removal of form for all heights :Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. 52 m2
6 6 Steel reinforcement for RCC work including strightening,cutting, bending,placing in position and binding all complete upto plinth level.Thermo-Mechanically Treated bars 7000 kg
7 7 Laterate masonry with neatly dressed laterate stone of size 40X20X15cm or nearest size in cement mortar 1:6 for foundation and basement including all cost of materials, labour charges etc 130 m3
8 8 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:2:4 (1 Cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 40 mm nominal size) 10 m3
9 9 Brick work with common burnt clay modular bricks of class designation 7.5 in foundation and plinth in:Cement mortar 1:4 (1 cement : 4 coarse sand) 7 m3
10 10 12 mm cement plaster of mix :1:4 (1 cement: 4 fine sand) 1200 m2
11 11 Plastering using 9mm cement of mix 1:3(1cement,3 fine cement) including all cost of materials,labour charges etc.complete 85 m2
12 12 Sructural steel work in single section,fixed with or without connecting plate,including cutting,hoisting,fixing in position all complete using departmentally supplied angles across cable trench for carrying cables.(labour charges only) 4500 kg
13 13 Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50m and lift upto 1.50m. 31 m3
14 14 Lifting, loading and proper placing of precast RCC slabs of various sizes (Thickness up to 10cm) by manual conveyance from casting yard to the trenches wherever necessary, safely without causing any damages to cables and slabs, placing neatly by levelling, aligning, removing waste particles from trench etc complete including hire charges for necessary tools etc complete as per direction of departmental officers at site. 400 m2
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail