Uttar Pradesh Power Transmission Corporation Limited-UPPTCL has published Replacement Of Damaged Conductor Of 132Kv Muradnagar-Dasna Line And 132Kv Muradnagar-Faridnagar Lines At Gantry Of The Substation Under Electricity Transmission Division , Muranagar . . Submission Date for this Tender is 25-07-2020. Conductor Tenders in MODINAGAR Uttar Pradesh. Bidders can get complete Tender details and download the document.
Name of Work: FFOR REPLACEMENT OF DAMAGED CONDUCTOR OF 132kV MURADNAGAR-DASNA LINE AND 132kV MURADNAGAR-FARIDNAGAR LINES AT GANTRY OF THE SUBSTATION UNDER ELECTRICITY TRANSMISSION DIVISION, MURANAGAR. | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Replacement of damaged R & B phase conductor of 132kV Muradnagar-Dasna line at gantry of the 132kV Dasna bay ( between tower No. 01 and Gantry of the substation, approx. 70 meter). work includes lowering down the conductor after removing of jumper at tension tower, tension fitting hook, removing of the jumper from line to PT, LA, removing of jumper from line to isolator after removing of suspension fitting etc. laying of new conductor of proper length after marking of the conductor pressing of tension fitting at both end of the conductor, connecting of string after cleaning, lifting of the conductor hanging it on cross arm and gantry of the bay and connecting of jumper at tension tower, connecting of the jumper from line to PT, LA ( Replace the jumper if required by new panther conductor). | 2 | Job | |
2 | 2 | Replacement of jumper from gantry to isolator by panther conductor after marking of the jumper and pressing of jumper cone at one end, connecting suspension fitting, lifting of jumper and connect one end at tension fitting, at gantry with suspension fitting and isolator string etc. | 2 | No | |
3 | 3 | Replacement of damaged R, Y & B phase conductor of 132kV Muradnagar-Faridnagar line at gantry of the 132kV Faridnagar bay ( between tower No. 01 and Gantry of the substation, approx. 70 meter). work includes lowering down the conductor after removing of jumper at tension tower, tension fitting hook, removing of the jumper from line to PT, LA, removing of jumper from line to isolator after removing of suspension fitting etc. laying of new conductor of proper length after marking of the conductor pressing of tension fitting at both end of the conductor, connecting of string after cleaning, lifting of the conductor hanging it on cross arm and gantry of the bay and connecting of jumper at tension tower, connecting of the jumper from line to PT, LA ( Replace the jumper if required by new panther conductor). | 3 | Job | |
4 | 4 | Replacement of jumper from gantry to isolator by panther conductor after marking of the jumper and pressing of jumper cone at one end, connecting suspension fitting, lifting of jumper and connect one end at tension fitting, at gantry with suspension fitting and isolator string etc. | 3 | No |