Rural Development And Panchayats Department has published Renovation Of Mi Tank And Ponds Under State Finance Commission Grant In Marungapuri Block In Tiruchirappalli District For The Year 2019-20 Package No . 49. Submission Date for this Tender is 01-03-2021. Irrigation Work Tenders in Tiruchirappalli Tamil Nadu. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 13-Jun-2020 | Date Corrigendum | Date | 19-06-2020 |
2 | 19-Jun-2020 | Date Corrigendum2 | Date | 26-06-2020 |
3 | 26-Jun-2020 | Date2 | Date | 02-07-2020 |
4 | 02-Jul-2020 | Date3 | Date | 10-07-2020 |
5 | 10-Jul-2020 | Date4 | Date | 17-07-2020 |
6 | 17-Jul-2020 | Date5 | Date | 24-07-2020 |
7 | 24-Jul-2020 | Date6 | Date | 30-07-2020 |
8 | 30-Jul-2020 | Date7 | Date | 05-08-2020 |
9 | 05-Aug-2020 | Date Ext | Date | 12-08-2020 |
10 | 11-Aug-2020 | Date9 | Date | 19-08-2020 |
11 | 19-Aug-2020 | Date Extension | Date | 26-08-2020 |
12 | 26-Aug-2020 | Date10 | Date | 04-09-2020 |
13 | 04-Sep-2020 | Date11 | Date | 09-09-2020 |
14 | 09-Sep-2020 | Date12 | Date | 11-09-2020 |
15 | 11-Sep-2020 | Date13 | Date | 15-09-2020 |
16 | 15-Sep-2020 | Date14 | Date | 17-09-2020 |
17 | 17-Sep-2020 | Date15 | Date | 22-09-2020 |
18 | 22-Sep-2020 | Date16 | Date | 28-09-2020 |
19 | 28-Sep-2020 | Date17 | Date | 05-10-2020 |
20 | 05-Oct-2020 | Date18 | Date | 12-10-2020 |
21 | 12-Oct-2020 | Date19 | Date | 16-10-2020 |
22 | 16-Oct-2020 | Date20 | Date | 23-10-2020 |
23 | 23-Oct-2020 | Date21 | Date | 03-11-2020 |
24 | 20-Nov-2020 | Date24 | Date | 30-11-2020 |
25 | 29-Nov-2020 | Date25 | Date | 07-12-2020 |
26 | 06-Dec-2020 | Date26 | Date | 14-12-2020 |
27 | 13-Dec-2020 | Date27 | Date | 21-12-2020 |
28 | 20-Dec-2020 | Date28 | Date | 28-12-2020 |
29 | 28-Dec-2020 | Date29 | Date | 04-01-2021 |
30 | 03-Jan-2021 | Date30 | Date | 11-01-2021 |
31 | 11-Jan-2021 | Date31 | Date | 25-01-2021 |
32 | 25-Jan-2021 | Date32 | Date | 08-02-2021 |
33 | 08-Feb-2021 | Date33 | Date | 15-02-2021 |
34 | 14-Feb-2021 | Date34 | Date | 22-02-2021 |
35 | 21-Feb-2021 | Date35 | Date | 01-03-2021 |
Name of Scheme : State Finace Commission Grant 2019-20 | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | REJUVENATION OF PULAVAN KULAM MI TANK IN UTHUKULI PANCHAYAT IN MARUNGAPURI BLOCK Clearing the Scrub jungle | 10254.6 | M2 | |
2 | 2 | Earth work in all soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100 metre deploying earth moving machineries and tippers including benching, formation of bunds, breaking clods,sectioning extra watering and consolidation by power roller including hire chages etc., complete. SOR 2019-20 86(1)+71(B) | 5924.12 | M3 | |
3 | 3 | Earth work deploying earth moving machinery for desilting channel and forming bund on either side and depositing the earth on banks including jungle clearance etc complete SOR 2019-20 89 (a) | 358.88 | M3 | |
4 | 4 | Re-Construction of Sluice: Dismantling,Clearing away and carefully stacking materials useful for re-use for any thickness of walls Brick /Stone masonry in cement mortar walls under 3 m high | 35.87 | M2 | |
5 | 5 | Dismantling,Clearing away and carefully stacking materials useful for re-use for any thickness of walls Plain Cement Concrete | 11.5 | M2 | |
6 | 6 | Dismantling,Clearing away and carefully stacking materials useful for re-use for any thickness of walls Reinforced Cement Concrete | 5.2 | M3 | |
7 | 7 | Earth work excavation and depositingon bank with all lead andlift in all classes of soil such as hard stiff claystiff black cotton hard red earth shales murrams, hard gravellyetc except sand and rock requiring blasting all incidental charges etc complete for Box cutting/ foundation asper SS 20B | 18.9 | M3 | |
8 | 8 | Cement concrete in C M 1:4:8 mix using40mm ISS HBG metal including cost and conveyanceof all materials to siteand labour charges, for mixing laying and raming, curing the concrete etc., | 20.44 | M3 | |
9 | 9 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 176.85 | M2 | |
10 | 10 | Plain Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 42.55 | M3 | |
11 | 11 | Plain Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 2.22 | M3 | |
12 | 12 | Reinforced Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 5.36 | M3 | |
13 | 13 | Suplying and fabricating and placing in position of m.s rods (or) RTS for all RCC works as per design given including bending typing and cost of bending tying and cost of binding wire etc.,Suplying and fabricating and placing in position of m.s rods (or) RTS for all RCC works as per design given including bending typing and cost of bending tying and cost of binding wire etc., | 0.35 | MT | |
14 | 14 | Rough stone dry packing for aprons and revetment including palls for filling and wedging using good quality of new rough stones from approved quarry including conveyance charges including stacking them for premeasurement etc.complete complying with standard specificatios and as directed by the departmental officers. | 30 | M3 | |
15 | 15 | Fabiricating, Suppling and fixing of 50mm dia screw rod made up M.S round duly machined and fully threaded to suit the head assembly and provided with required holes. Conveying and leading the screw rod to the work site. Fixing the screw rod to the shutter guest plate with req bolt and nuts in proper alignment to the head set including dismantiling the existing damaged screw rod conveying and stocking the section store the screw rod should be painted with two coats ac black paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 2.5 | NO | |
16 | 16 | Fabiricating, Suppling and fixing of Head set assembly medium duty with hexagonal nut (apporxmate 50 kg) made up of cast iron including moulding machining and the hexagonal nut threading to suit the screw rod providing with the threast bearing for smooth opration conveying and leading the head set assembly to the work site fixing the head set assembly to the tob beam by using requied bolt and nut in proper alignment including dismantiling the existing damaged screw rod conveying and stocking the section store the head set assembly supplyed with operating key and the both should be painting with two coat of ac block paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 1 | No | |
17 | 17 | Parches and fixing the guest plate for hold the wooden plug fabricated 8mm MS plate including fabrication oc 40X40 mm L angle with 32 mm dia of length welded with 3/4" in bolt with plate rod etc complete | 1 | No | |
18 | 18 | Parches and fixing after reshaping country wood into plug cost including machinary to concocal shap fixing with guest plate etc complete | 1 | NO | |
19 | 19 | Parches and fixing bottom catch plate for the wooden plug 6 mm MS plate 10mm dia with fabrication and fixing the wooden plug etc complete | 1 | No | |
20 | 20 | Repairs Sluice : Earth work excavation and depositingon bank with all lead andlift in all classes of soil such as hard stiff claystiff black cotton hard red earth shales murrams, hard gravellyetc except sand and rock requiring blasting all incidental charges etc complete for Box cutting/ foundation asper SS 20B | 3.75 | M3 | |
21 | 21 | Cement concrete in C M 1:4:8 mix using40mm ISS HBG metal including cost and conveyanceof all materials to siteand labour charges, for mixing laying and raming, curing the concrete etc., | 1.88 | M3 | |
22 | 22 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 36.81 | M2 | |
23 | 23 | Plain Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 6.75 | M3 | |
24 | 24 | Pointing the RR masandry with cm 1:3 mixincluding cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 27.44 | M2 | |
25 | 25 | Plastering with cement mortar 1:4mix to 20mm thick including cost and conveyance of all materials to site and all labour charges etc | 6.71 | M3 | |
26 | 26 | Plain Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 0.76 | M3 | |
27 | 27 | Rough stone dry packing for aprons and revetment including palls for filling and wedging using good quality of new rough stones from approved quarry including conveyance charges including stacking them for premeasurement etc.complete complying with standard specificatios and as directed by the departmental officers. | 30 | M3 | |
28 | 28 | Fabiricating, Suppling and fixing of 50mm dia screw rod made up M.S round duly machined and fully threaded to suit the head assembly and provided with required holes. Conveying and leading the screw rod to the work site. Fixing the screw rod to the shutter guest plate with req bolt and nuts in proper alignment to the head set including dismantiling the existing damaged screw rod conveying and stocking the section store the screw rod should be painted with two coats ac black paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 2 | m | |
29 | 29 | Fabiricating, Suppling and fixing of Head set assembly medium duty with hexagonal nut (apporxmate 50 kg) made up of cast iron including moulding machining and the hexagonal nut threading to suit the screw rod providing with the threast bearing for smooth opration conveying and leading the head set assembly to the work site fixing the head set assembly to the tob beam by using requied bolt and nut in proper alignment including dismantiling the existing damaged screw rod conveying and stocking the section store the head set assembly supplyed with operating key and the both should be painting with two coat of ac block paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 1 | No | |
30 | 30 | Parches and fixing the guest plate for hold the wooden plug fabricated 8mm MS plate including fabrication oc 40X40 mm L angle with 32 mm dia of length welded with 3/4" in bolt with plate rod etc complete | 1 | No | |
31 | 31 | Parches and fixing after reshaping country wood into plug cost including machinary to concocal shap fixing with guest plate etc complete | 1 | NO | |
32 | 32 | Parches and fixing bottom catch plate for the wooden plug 6 mm MS plate 10mm dia with fabrication and fixing the wooden plug etc complete | 1 | No | |
33 | 33 | Provision for silt removing charges complete | 1 | No | |
34 | 34 | Repairs Sluice : Earth work excavation and depositingon bank with all lead andlift in all classes of soil such as hard stiff claystiff black cotton hard red earth shales murrams, hard gravellyetc except sand and rock requiring blasting all incidental charges etc complete for Box cutting/ foundation asper SS 20B | 3.75 | M3 | |
35 | 35 | Cement concrete in C M 1:4:8 mix using40mm ISS HBG metal including cost and conveyanceof all materials to siteand labour charges, for mixing laying and raming, curing the concrete etc., | 1.88 | M3 | |
36 | 36 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 36.81 | M2 | |
37 | 37 | Plain Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 6.75 | M3 | |
38 | 38 | Pointing the RR masandry with cm 1:3 mixincluding cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 27.44 | M2 | |
39 | 39 | Plastering with cement mortar 1:4mix to 20mm thick including cost and conveyance of all materials to site and all labour charges etc | 6.71 | M3 | |
40 | 40 | Plain Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 0.76 | M3 | |
41 | 41 | Rough stone dry packing for aprons and revetment including palls for filling and wedging using good quality of new rough stones from approved quarry including conveyance charges including stacking them for premeasurement etc.complete complying with standard specificatios and as directed by the departmental officers. | 30 | M3 | |
42 | 42 | Fabiricating, Suppling and fixing of 50mm dia screw rod made up M.S round duly machined and fully threaded to suit the head assembly and provided with required holes. Conveying and leading the screw rod to the work site. Fixing the screw rod to the shutter guest plate with req bolt and nuts in proper alignment to the head set including dismantiling the existing damaged screw rod conveying and stocking the section store the screw rod should be painted with two coats ac black paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 2 | m | |
43 | 43 | Fabiricating, Suppling and fixing of Head set assembly medium duty with hexagonal nut (apporxmate 50 kg) made up of cast iron including moulding machining and the hexagonal nut threading to suit the screw rod providing with the threast bearing for smooth opration conveying and leading the head set assembly to the work site fixing the head set assembly to the tob beam by using requied bolt and nut in proper alignment including dismantiling the existing damaged screw rod conveying and stocking the section store the head set assembly supplyed with operating key and the both should be painting with two coat of ac block paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 1 | No | |
44 | 44 | Parches and fixing the guest plate for hold the wooden plug fabricated 8mm MS plate including fabrication oc 40X40 mm L angle with 32 mm dia of length welded with 3/4" in bolt with plate rod etc complete | 1 | No | |
45 | 45 | Parches and fixing after reshaping country wood into plug cost including machinary to concocal shap fixing with guest plate etc complete | 1 | NO | |
46 | 46 | Parches and fixing bottom catch plate for the wooden plug 6 mm MS plate 10mm dia with fabrication and fixing the wooden plug etc complete | 1 | No | |
47 | 47 | Provision for silt removing charges complete | 1 | No | |
48 | 48 | Construction of Weir :Earth work excavation and depositingon bank with all lead andlift in all classes of soil such as hard stiff claystiff black cotton hard red earth shales murrams, hard gravellyetc except sand and rock requiring blasting all incidental charges etc complete for Box cutting/ foundation asper SS 20B | 50.42 | M3 | |
49 | 49 | Cement concrete in C M 1:4:8 mix using40mm ISS HBG metal including cost and conveyanceof all materials to siteand labour charges, for mixing laying and raming, curing the concrete etc., | 14.93 | M3 | |
50 | 50 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 57 | M2 | |
51 | 51 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 104.36 | M3 | |
52 | 52 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 53.3 | M3 | |
53 | 53 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete . | 18.75 | M3 | |
54 | 54 | Plain Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for | 4.02 | M3 | |
55 | 55 | Provision for weep holes charges | 1 | No | |
56 | 56 | Provision for Name board charges | 1 | No | |
57 | 57 | REJUVENATION OF KOTTA PALUVANJI KULAM MI TANK IN PALUVANJI PANCHAYAT IN MARUNGAPURI BLOCK Clearing the Scrub jungle | 11292 | M2 | |
58 | 58 | Earth work in all soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100 metre deploying earth moving machineries and tippers including benching, formation of bunds, breaking clods,sectioning extra watering and consolidation by power roller including hire chages etc., complete. | 7317.92 | M3 | |
59 | 59 | Earth work deploying earth moving machinery for desilting channel and forming bund on either side and depositing the earth on banks including jungle clearance etc complete SOR 2019-20 89 (a) | 268.43 | M3 | |
60 | 60 | Re-Construction of Sluice: Dismantling,Clearing away and carefully stacking materials useful for re-use for any thickness of walls Brick /Stone masonry in cement mortar walls under 3 m high | 34.97 | M2 | |
61 | 61 | Dismantling,Clearing away and carefully stacking materials useful for re-use for any thickness of walls Plain Cement Concrete | 10.9 | M2 | |
62 | 62 | Dismantling,Clearing away and carefully stacking materials useful for re-use for any thickness of walls Reinforced Cement Concrete | 4.8 | M3 | |
63 | 63 | Earth work excavation and depositingon bank with all lead andlift in all classes of soil such as hard stiff claystiff black cotton hard red earth shales murrams, hard gravellyetc except sand and rock requiring blasting all incidental charges etc complete for Box cutting/ foundation asper SS 20B | 21.06 | M3 | |
64 | 64 | Cement concrete in C M 1:4:8 mix using40mm ISS HBG metal including cost and conveyanceof all materials to siteand labour charges, for mixing laying and raming, curing the concrete etc., | 20.56 | M3 | |
65 | 65 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 180.3 | M2 | |
66 | 66 | Plain Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 43.38 | M3 | |
67 | 67 | Plain Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 2.15 | M3 | |
68 | 68 | Reinforced Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 4.95 | M3 | |
69 | 69 | Suplying and fabricating and placing in position of m.s rods (or) RTS for all RCC works as per design given including bending typing and cost of bending tying and cost of binding wire etc.,Suplying and fabricating and placing in position of m.s rods (or) RTS for all RCC works as per design given including bending typing and cost of bending tying and cost of binding wire etc., | 0.35 | MT | |
70 | 70 | Rough stone dry packing for aprons and revetment including palls for filling and wedging using good quality of new rough stones from approved quarry including conveyance charges including stacking them for premeasurement etc.complete complying with standard specificatios and as directed by the departmental officers. | 30 | M3 | |
71 | 71 | Fabiricating, Suppling and fixing of 50mm dia screw rod made up M.S round duly machined and fully threaded to suit the head assembly and provided with required holes. Conveying and leading the screw rod to the work site. Fixing the screw rod to the shutter guest plate with req bolt and nuts in proper alignment to the head set including dismantiling the existing damaged screw rod conveying and stocking the section store the screw rod should be painted with two coats ac black paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 2.5 | NO | |
72 | 72 | Fabiricating, Suppling and fixing of Head set assembly medium duty with hexagonal nut (apporxmate 50 kg) made up of cast iron including moulding machining and the hexagonal nut threading to suit the screw rod providing with the threast bearing for smooth opration conveying and leading the head set assembly to the work site fixing the head set assembly to the tob beam by using requied bolt and nut in proper alignment including dismantiling the existing damaged screw rod conveying and stocking the section store the head set assembly supplyed with operating key and the both should be painting with two coat of ac block paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 1 | No | |
73 | 73 | Parches and fixing the guest plate for hold the wooden plug fabricated 8mm MS plate including fabrication oc 40X40 mm L angle with 32 mm dia of length welded with 3/4" in bolt with plate rod etc complete | 1 | No | |
74 | 74 | Parches and fixing after reshaping country wood into plug cost including machinary to concocal shap fixing with guest plate etc complete | 1 | NO | |
75 | 75 | Parches and fixing bottom catch plate for the wooden plug 6 mm MS plate 10mm dia with fabrication and fixing the wooden plug etc complete | 1 | No | |
76 | 76 | Construction of Weir :Earth work excavation and depositingon bank with all lead andlift in all classes of soil such as hard stiff claystiff black cotton hard red earth shales murrams, hard gravellyetc except sand and rock requiring blasting all incidental charges etc complete for Box cutting/ foundation asper SS 20B | 50.42 | M3 | |
77 | 77 | Cement concrete in C M 1:4:8 mix using40mm ISS HBG metal including cost and conveyanceof all materials to siteand labour charges, for mixing laying and raming, curing the concrete etc., | 14.93 | M3 | |
78 | 78 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 57 | M2 | |
79 | 79 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 104.36 | M3 | |
80 | 80 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 53.3 | M3 | |
81 | 81 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete . | 18.75 | M3 | |
82 | 82 | Plain Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for | 6.03 | M3 | |
83 | 83 | Provision for weep holes charges | 1 | No | |
84 | 84 | Provision for Name board charges | 1 | No | |
85 | 85 | REJUVENATION OF EDAYAN KULAM MI TANK IN UTHUKULI PANCHAYAT IN MARUNGAPURI BLOCK Clearing the Scrub jungle | 7605 | M2 | |
86 | 86 | Earth work in all soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100 metre deploying earth moving machineries and tippers including benching, formation of bunds, breaking clods,sectioning extra watering and consolidation by power roller including hire chages etc., complete. SOR 2019-20 86(1)+71(B) | 5608.6 | M3 | |
87 | 87 | Earth work deploying earth moving machinery for desilting channel and forming bund on either side and depositing the earth on banks including jungle clearance etc complete SOR 2019-20 89 (a) | 358.88 | M3 | |
88 | 88 | Re-Construction of Sluice: Dismantling,Clearing away and carefully stacking materials useful for re-use for any thickness of walls Brick /Stone masonry in cement mortar walls under 3 m high | 34.97 | M2 | |
89 | 89 | Dismantling,Clearing away and carefully stacking materials useful for re-use for any thickness of walls Plain Cement Concrete | 10.9 | M2 | |
90 | 90 | Dismantling,Clearing away and carefully stacking materials useful for re-use for any thickness of walls Reinforced Cement Concrete | 4.8 | M3 | |
91 | 91 | Earth work excavation and depositingon bank with all lead andlift in all classes of soil such as hard stiff claystiff black cotton hard red earth shales murrams, hard gravellyetc except sand and rock requiring blasting all incidental charges etc complete for Box cutting/ foundation asper SS 20B | 13.5 | M3 | |
92 | 92 | Cement concrete in C M 1:4:8 mix using40mm ISS HBG metal including cost and conveyanceof all materials to siteand labour charges, for mixing laying and raming, curing the concrete etc., | 18.04 | M3 | |
93 | 93 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 155.1 | M2 | |
94 | 94 | Plain Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 37.71 | M3 | |
95 | 95 | Plain Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 2.15 | M3 | |
96 | 96 | Reinforced Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 4.95 | M3 | |
97 | 97 | Suplying and fabricating and placing in position of m.s rods (or) RTS for all RCC works as per design given including bending typing and cost of bending tying and cost of binding wire etc.,Suplying and fabricating and placing in position of m.s rods (or) RTS for all RCC works as per design given including bending typing and cost of bending tying and cost of binding wire etc., | 0.35 | MT | |
98 | 98 | Rough stone dry packing for aprons and revetment including palls for filling and wedging using good quality of new rough stones from approved quarry including conveyance charges including stacking them for premeasurement etc.complete complying with standard specificatios and as directed by the departmental officers. | 30 | M3 | |
99 | 99 | Fabiricating, Suppling and fixing of 50mm dia screw rod made up M.S round duly machined and fully threaded to suit the head assembly and provided with required holes. Conveying and leading the screw rod to the work site. Fixing the screw rod to the shutter guest plate with req bolt and nuts in proper alignment to the head set including dismantiling the existing damaged screw rod conveying and stocking the section store the screw rod should be painted with two coats ac black paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 2.5 | NO | |
100 | 100 | Fabiricating, Suppling and fixing of Head set assembly medium duty with hexagonal nut (apporxmate 50 kg) made up of cast iron including moulding machining and the hexagonal nut threading to suit the screw rod providing with the threast bearing for smooth opration conveying and leading the head set assembly to the work site fixing the head set assembly to the tob beam by using requied bolt and nut in proper alignment including dismantiling the existing damaged screw rod conveying and stocking the section store the head set assembly supplyed with operating key and the both should be painting with two coat of ac block paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 1 | No | |
101 | 101 | Parches and fixing the guest plate for hold the wooden plug fabricated 8mm MS plate including fabrication oc 40X40 mm L angle with 32 mm dia of length welded with 3/4" in bolt with plate rod etc complete | 1 | No | |
102 | 102 | Parches and fixing after reshaping country wood into plug cost including machinary to concocal shap fixing with guest plate etc complete | 1 | NO | |
103 | 103 | Parches and fixing bottom catch plate for the wooden plug 6 mm MS plate 10mm dia with fabrication and fixing the wooden plug etc complete | 1 | No | |
104 | 104 | Repairs Sluice : Earth work excavation and depositingon bank with all lead andlift in all classes of soil such as hard stiff claystiff black cotton hard red earth shales murrams, hard gravellyetc except sand and rock requiring blasting all incidental charges etc complete for Box cutting/ foundation asper SS 20B | 1.8 | M3 | |
105 | 105 | Cement concrete in C M 1:4:8 mix using40mm ISS HBG metal including cost and conveyanceof all materials to siteand labour charges, for mixing laying and raming, curing the concrete etc., | 0.9 | M3 | |
106 | 106 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 18.81 | M2 | |
107 | 107 | Plain Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 4.05 | M3 | |
108 | 108 | Pointing the RR masandry with cm 1:3 mixincluding cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 27.44 | M2 | |
109 | 109 | Plastering with cement mortar 1:4mix to 20mm thick including cost and conveyance of all materials to site and all labour charges etc | 6.71 | M3 | |
110 | 110 | Plain Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 0.46 | M3 | |
111 | 111 | Rough stone dry packing for aprons and revetment including palls for filling and wedging using good quality of new rough stones from approved quarry including conveyance charges including stacking them for premeasurement etc.complete complying with standard specificatios and as directed by the departmental officers. | 30 | M3 | |
112 | 112 | Fabiricating, Suppling and fixing of 50mm dia screw rod made up M.S round duly machined and fully threaded to suit the head assembly and provided with required holes. Conveying and leading the screw rod to the work site. Fixing the screw rod to the shutter guest plate with req bolt and nuts in proper alignment to the head set including dismantiling the existing damaged screw rod conveying and stocking the section store the screw rod should be painted with two coats ac black paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 2 | m | |
113 | 113 | Fabiricating, Suppling and fixing of Head set assembly medium duty with hexagonal nut (apporxmate 50 kg) made up of cast iron including moulding machining and the hexagonal nut threading to suit the screw rod providing with the threast bearing for smooth opration conveying and leading the head set assembly to the work site fixing the head set assembly to the tob beam by using requied bolt and nut in proper alignment including dismantiling the existing damaged screw rod conveying and stocking the section store the head set assembly supplyed with operating key and the both should be painting with two coat of ac block paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 1 | No | |
114 | 114 | Parches and fixing the guest plate for hold the wooden plug fabricated 8mm MS plate including fabrication oc 40X40 mm L angle with 32 mm dia of length welded with 3/4" in bolt with plate rod etc complete | 1 | No | |
115 | 115 | Parches and fixing after reshaping country wood into plug cost including machinary to concocal shap fixing with guest plate etc complete | 1 | NO | |
116 | 116 | Parches and fixing bottom catch plate for the wooden plug 6 mm MS plate 10mm dia with fabrication and fixing the wooden plug etc complete | 1 | No | |
117 | 117 | Provision for silt removing charges complete | 1 | No | |
118 | 118 | Construction of Weir :Earth work excavation and depositingon bank with all lead andlift in all classes of soil such as hard stiff claystiff black cotton hard red earth shales murrams, hard gravellyetc except sand and rock requiring blasting all incidental charges etc complete for Box cutting/ foundation asper SS 20B | 50.42 | M3 | |
119 | 119 | Cement concrete in C M 1:4:8 mix using40mm ISS HBG metal including cost and conveyanceof all materials to siteand labour charges, for mixing laying and raming, curing the concrete etc., | 14.93 | M3 | |
120 | 120 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 57 | M2 | |
121 | 121 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 104.36 | M3 | |
122 | 122 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 53.3 | M3 | |
123 | 123 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete . | 18.75 | M3 | |
124 | 124 | Plain Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for | 4.02 | M3 | |
125 | 125 | Provision for weep holes charges | 1 | No | |
126 | 126 | Provision for Name board charges | 1 | No | |
127 | 127 | REJUVENATION OF KATTAYAN KULAM MI TANK IN UTHUKULI PANCHAYAT IN MARUNGAPURI BLOCK Clearing the Scrub jungle | 4830.6 | M2 | |
128 | 128 | Earth work in all soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100 metre deploying earth moving machineries and tippers including benching, formation of bunds, breaking clods,sectioning extra watering and consolidation by power roller including hire chages etc., complete. SOR 2019-20 86(1)+71(B) | 3185.36 | M3 | |
129 | 129 | Earth work deploying earth moving machinery for desilting channel and forming bund on either side and depositing the earth on banks including jungle clearance etc complete SOR 2019-20 89 (a) | 358.88 | M3 | |
130 | 130 | Repairs Sluice : Earth work excavation and depositingon bank with all lead andlift in all classes of soil such as hard stiff claystiff black cotton hard red earth shales murrams, hard gravellyetc except sand and rock requiring blasting all incidental charges etc complete for Box cutting/ foundation asper SS 20B | 1.8 | M3 | |
131 | 131 | Cement concrete in C M 1:4:8 mix using40mm ISS HBG metal including cost and conveyanceof all materials to siteand labour charges, for mixing laying and raming, curing the concrete etc., | 0.9 | M3 | |
132 | 132 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 18.81 | M2 | |
133 | 133 | Plain Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 4.05 | M3 | |
134 | 134 | Pointing the RR masandry with cm 1:3 mixincluding cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 27.44 | M2 | |
135 | 135 | Plastering with cement mortar 1:4mix to 20mm thick including cost and conveyance of all materials to site and all labour charges etc | 6.71 | M3 | |
136 | 136 | Plain Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 0.46 | M3 | |
137 | 137 | Rough stone dry packing for aprons and revetment including palls for filling and wedging using good quality of new rough stones from approved quarry including conveyance charges including stacking them for premeasurement etc.complete complying with standard specificatios and as directed by the departmental officers. | 24 | M3 | |
138 | 138 | Fabiricating, Suppling and fixing of 50mm dia screw rod made up M.S round duly machined and fully threaded to suit the head assembly and provided with required holes. Conveying and leading the screw rod to the work site. Fixing the screw rod to the shutter guest plate with req bolt and nuts in proper alignment to the head set including dismantiling the existing damaged screw rod conveying and stocking the section store the screw rod should be painted with two coats ac black paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 2 | m | |
139 | 139 | Fabiricating, Suppling and fixing of Head set assembly medium duty with hexagonal nut (apporxmate 50 kg) made up of cast iron including moulding machining and the hexagonal nut threading to suit the screw rod providing with the threast bearing for smooth opration conveying and leading the head set assembly to the work site fixing the head set assembly to the tob beam by using requied bolt and nut in proper alignment including dismantiling the existing damaged screw rod conveying and stocking the section store the head set assembly supplyed with operating key and the both should be painting with two coat of ac block paint over one coat of red oxide primer. the rate including cost of materials labours charges for all fabricating and hoisting equipements conveyance charges for labour and other including all other taxes etc complete | 1 | No | |
140 | 140 | Parches and fixing the guest plate for hold the wooden plug fabricated 8mm MS plate including fabrication oc 40X40 mm L angle with 32 mm dia of length welded with 3/4" in bolt with plate rod etc complete | 1 | No | |
141 | 141 | Parches and fixing after reshaping country wood into plug cost including machinary to concocal shap fixing with guest plate etc complete | 1 | NO | |
142 | 142 | Parches and fixing bottom catch plate for the wooden plug 6 mm MS plate 10mm dia with fabrication and fixing the wooden plug etc complete | 1 | No | |
143 | 143 | Provision for silt removing charges complete | 1 | No | |
144 | 144 | Construction of Weir :Earth work excavation and depositingon bank with all lead andlift in all classes of soil such as hard stiff claystiff black cotton hard red earth shales murrams, hard gravellyetc except sand and rock requiring blasting all incidental charges etc complete for Box cutting/ foundation asper SS 20B | 50.42 | M3 | |
145 | 145 | Cement concrete in C M 1:4:8 mix using40mm ISS HBG metal including cost and conveyanceof all materials to siteand labour charges, for mixing laying and raming, curing the concrete etc., | 14.93 | M3 | |
146 | 146 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 57 | M2 | |
147 | 147 | Centering and Shuttering charges for Rcc works inclusing cost and conveyance of materials to site and all labour charges etc., complete | 104.36 | M3 | |
148 | 148 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks | 53.3 | M3 | |
149 | 149 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete . | 18.75 | M3 | |
150 | 150 | Plain Cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for | 4.02 | M3 | |
151 | 151 | Provision for weep holes charges | 1 | No | |
152 | 152 | Provision for Name board charges | 1 | No | |
153 | 153 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}\n | BI01010001010000000000000515BI01000011120 | 1 | No |