Public Works Department-PWD has published Budget Work 2019-20 - Chengannur Flood Relief- Re-Construction Of Various Roads In Thiruvanvandoor Grama Panchayath. Submission Date for this Tender is 23-04-2020. Road Work Tenders in Thiruvanvandoor Grama Panchayath Kerala. Bidders can get complete Tender details and download the document.
Work Name: Budget Work 2019-20 - Chengannur Flood Relief- Re-construction of various roads in Thiruvanvandoor Grama Panchayath | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | VALIYATHARAPADI ELECRICITY OFFICE ROAD (WARD NO 11) | BI01010001010000000000000515BI0100001113 | ||
2 | 1.01 | 3.18 : Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 | BI01010001010000000000000515BI0100001114 | 360 | cum |
3 | 1.02 | 4.12 : Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. | BI01010001010000000000000515BI0100001115 | 121.5 | cum |
4 | 1.03 | 4.1.B.1 : Construction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. <br>\nGrading-V - For sub base cum drainage layer - Mix in Place MethodConstruction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. Grading-V - For sub base cum drainage layer - Mix in Place Method | BI01010001010000000000000515BI0100001116 | 121.5 | cum |
5 | 1.04 | 55.4 : Supplying and stacking 36mm size hard broken stone in standard heaps for measurement.Supplying and stacking 36mm size hard broken stone in standard heaps for measurement. | BI01010001010000000000000515BI0100001117 | 18.4 | cum |
6 | 1.05 | 5.1.a : Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means.Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means. | BI01010001010000000000000515BI0100001118 | 810 | sqm |
7 | 1.06 | 55.8.a : Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 36mm departmental broken stone and compacting with power roller to get a compact surface.Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 36mm departmental broken stone and compacting with power roller to get a compact surface. | BI01010001010000000000000515BI0100001119 | 18.4 | cum |
8 | 1.07 | 5.2.a : Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. | BI01010001010000000000000515BI0100001120 | 2100 | sqm |
9 | 1.08 | od35243/2019_2020 : Mix Seal Surfacing Providing , Laying and rolling of close graded premix surfacing material of 20mm thickness composed of 11.2 mm to 0.9mm Type A aggregates using penetration grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base , including mixing in a suitable plant , laying and rolling with a three wheel 8-10 KN static roller and finishing to required level and grades as per Technical Specification Clause 509 of MORD (Usage of bitumen is 22.00kg/10m2) By Manual Means | BI01010001010000000000000515BI0100001121 | 2100 | sqm |
10 | 1.09 | 12.1.B.1 : Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. <br>\nOrdinary Soil - Depth upto 3m - Mechanical Means <br>Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. Ordinary Soil - Depth upto 3m - Mechanical Means | BI01010001010000000000000515BI0100001122 | 105 | cum |
11 | 1.1 | od35249/2019_2020 : Dry rubble masonary for the bed of foundation and superstructure including cost of material, labor etc. complete(Based Data on Standard Data Book) | BI01010001010000000000000515BI0100001123 | 267 | cum |
12 | 1.11 | 12.4 : Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. | BI01010001010000000000000515BI0100001124 | 62 | cum |
13 | 1.12 | 12.8.B : Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br>\nPCC Grade M20 (Without formwork) <br>Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications PCC Grade M20 (Without formwork) | BI01010001010000000000000515BI0100001125 | 38.5 | cm |
14 | 2 | MUTTANISERIPADI - VETTIKOTTIL KSHETRAM(WARD 6) | BI01010001010000000000000515BI0100001126 | ||
15 | 2.01 | 3.18 : Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 | BI01010001010000000000000515BI0100001127 | 180 | cum |
16 | 2.02 | 4.1.B.1 : Construction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. <br>\nGrading-V - For sub base cum drainage layer - Mix in Place MethodConstruction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. Grading-V - For sub base cum drainage layer - Mix in Place Method | BI01010001010000000000000515BI0100001128 | 90 | cum |
17 | 2.03 | 4.12 : Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. | BI01010001010000000000000515BI0100001129 | 90 | cum |
18 | 2.04 | 55.4 : Supplying and stacking 36mm size hard broken stone in standard heaps for measurement.Supplying and stacking 36mm size hard broken stone in standard heaps for measurement. | BI01010001010000000000000515BI0100001130 | 19.16 | cum |
19 | 2.05 | 55.8.a : Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 36mm departmental broken stone and compacting with power roller to get a compact surface.Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 36mm departmental broken stone and compacting with power roller to get a compact surface. | BI01010001010000000000000515BI0100001131 | 19.16 | cum |
20 | 2.06 | 5.1.a : Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means.Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means. | BI01010001010000000000000515BI0100001132 | 600 | sqm |
21 | 2.07 | 5.2.a : Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. | BI01010001010000000000000515BI0100001133 | 1350 | sqm |
22 | 2.08 | od35244/2019_2020 : Mix Seal Surfacing Providing , Laying and rolling of close graded premix surfacing material of 20mm thickness composed of 11.2 mm to 0.9mm Type A aggregates using penetration grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base , including mixing in a suitable plant , laying and rolling with a three wheel 8-10 KN static roller and finishing to required level and grades as per Technical Specification Clause 509 of MORD (Usage of bitumen is 22.00kg/10m2) By Manual Means | BI01010001010000000000000515BI0100001134 | 1350 | sqm |
23 | 2.09 | 3.6 : Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000mExcavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m | BI01010001010000000000000515BI0100001135 | 140 | cum |
24 | 2.1 | 12.4 : Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. | BI01010001010000000000000515BI0100001136 | 75 | cum |
25 | 2.11 | 12.8.B : Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br>\nPCC Grade M20 (Without formwork) <br>Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications PCC Grade M20 (Without formwork) | BI01010001010000000000000515BI0100001137 | 22.5 | cm |
26 | 2.12 | 12.8.A.1 : Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. <br>\nPCC Grade M15 <br>Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. PCC Grade M15 | BI01010001010000000000000515BI0100001138 | 14 | cum |
27 | 2.13 | 12.8.1.C.1 : Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br>\n RCC Grade M20 - Using Concrete Mixer <br>Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications RCC Grade M20 - Using Concrete Mixer | BI01010001010000000000000515BI0100001139 | 5 | cum |
28 | 2.14 | 12.40 : Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical SpecificationsSupply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications | BI01010001010000000000000515BI0100001140 | 0.4 | MT |
29 | 3 | KANAAL PADI - KOMBIKUZHI-VARIKOTTILPADI ROAD (WARD 11) | BI01010001010000000000000515BI0100001141 | ||
30 | 3.01 | 3.18 : Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 | BI01010001010000000000000515BI0100001142 | 103.5 | cum |
31 | 3.02 | 4.1.B.1 : Construction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. <br>\nGrading-V - For sub base cum drainage layer - Mix in Place MethodConstruction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. Grading-V - For sub base cum drainage layer - Mix in Place Method | BI01010001010000000000000515BI0100001143 | 90 | cum |
32 | 3.03 | 3.6 : Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000mExcavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m | BI01010001010000000000000515BI0100001144 | 135 | cum |
33 | 3.04 | 12.4 : Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. | BI01010001010000000000000515BI0100001145 | 90 | cum |
34 | 3.05 | 12.8.B : Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br>\nPCC Grade M20 (Without formwork) <br>Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications PCC Grade M20 (Without formwork) | BI01010001010000000000000515BI0100001146 | 45 | cm |
35 | 3.06 | 12.1.B.1 : Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. <br>\nOrdinary Soil - Depth upto 3m - Mechanical Means <br>Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. Ordinary Soil - Depth upto 3m - Mechanical Means | BI01010001010000000000000515BI0100001147 | 35 | cum |
36 | 3.07 | od35250/2019_2020 : Dry rubble masonary for the bed of foundation and superstructure including cost of material, labor etc. complete(Based Data on Standard Data Book) | BI01010001010000000000000515BI0100001148 | 102.5 | cum |
37 | 3.08 | 12.8.B.1 : Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br>\n PCC Grade M20<br>Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications PCC Grade M20 | BI01010001010000000000000515BI0100001149 | 2.5 | cum |
38 | 4 | VYDYANPADI - THOTTATHILVEETILPADI ROAD(WARD 8) | BI01010001010000000000000515BI0100001150 | ||
39 | 4.01 | 3.18 : Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 | BI01010001010000000000000515BI0100001151 | 1350 | cum |
40 | 4.02 | 3.6 : Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000mExcavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m | BI01010001010000000000000515BI0100001152 | 168.75 | cum |
41 | 4.03 | 12.4 : Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. | BI01010001010000000000000515BI0100001153 | 112.5 | cum |
42 | 4.04 | 12.8.B : Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br>\nPCC Grade M20 (Without formwork) <br>Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications PCC Grade M20 (Without formwork) | BI01010001010000000000000515BI0100001154 | 56.25 | cm |
43 | 4.05 | 12.1.B.1 : Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. <br>\nOrdinary Soil - Depth upto 3m - Mechanical Means <br>Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. Ordinary Soil - Depth upto 3m - Mechanical Means | BI01010001010000000000000515BI0100001155 | 216 | cum |
44 | 4.06 | od35251/2019_2020 : Dry rubble masonary for the bed of foundation and superstructure including cost of material, labor etc. complete(Based Data on Standard Data Book) | BI01010001010000000000000515BI0100001156 | 891 | cum |
45 | 4.07 | 12.8.B.1 : Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br>\n PCC Grade M20<br>Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications PCC Grade M20 | BI01010001010000000000000515BI0100001157 | 21 | cum |
46 | 5 | MANTHANAMADATHILPADI -THUNDITILPADI-MAZHUKEER KOVILAKAM PADI ROAD (WARD 6) | BI01010001010000000000000515BI0100001158 | ||
47 | 5.01 | 3.18 : Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 | BI01010001010000000000000515BI0100001159 | 22.5 | cum |
48 | 5.02 | 4.1.B.1 : Construction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. <br>\nGrading-V - For sub base cum drainage layer - Mix in Place MethodConstruction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. Grading-V - For sub base cum drainage layer - Mix in Place Method | BI01010001010000000000000515BI0100001160 | 22.5 | cum |
49 | 5.03 | 4.12 : Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. | BI01010001010000000000000515BI0100001161 | 22.5 | cum |
50 | 5.04 | 55.4 : Supplying and stacking 36mm size hard broken stone in standard heaps for measurement.Supplying and stacking 36mm size hard broken stone in standard heaps for measurement. | BI01010001010000000000000515BI0100001162 | 20.15 | cum |
51 | 5.05 | 55.8.a : Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 36mm departmental broken stone and compacting with power roller to get a compact surface.Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 36mm departmental broken stone and compacting with power roller to get a compact surface. | BI01010001010000000000000515BI0100001163 | 20.15 | cum |
52 | 5.06 | 5.1.a : Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means.Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means. | BI01010001010000000000000515BI0100001164 | 150 | sqm |
53 | 5.07 | 5.2.a : Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. | BI01010001010000000000000515BI0100001165 | 1950 | sqm |
54 | 5.08 | od35246/2019_2020 : Mix Seal Surfacing Providing , Laying and rolling of close graded premix surfacing material of 20mm thickness composed of 11.2 mm to 0.9mm Type A aggregates using penetration grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base , including mixing in a suitable plant , laying and rolling with a three wheel 8-10 KN static roller and finishing to required level and grades as per Technical Specification Clause 509 of MORD (Usage of bitumen is 22.00kg/10m2) By Manual Means | BI01010001010000000000000515BI0100001166 | 2275 | sqm |
55 | 5.09 | 3.6 : Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000mExcavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m | BI01010001010000000000000515BI0100001167 | 130 | cum |
56 | 5.1 | 12.4 : Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. | BI01010001010000000000000515BI0100001168 | 97.5 | cum |
57 | 5.11 | 12.8.B : Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br>\nPCC Grade M20 (Without formwork) <br>Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications PCC Grade M20 (Without formwork) | BI01010001010000000000000515BI0100001169 | 32.5 | cm |
58 | 6 | MRIGASUPATRI - KANAAL PADI ROAD(WARD 3) | BI01010001010000000000000515BI0100001170 | ||
59 | 6.01 | 4.1.B.1 : Construction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. <br>\nGrading-V - For sub base cum drainage layer - Mix in Place MethodConstruction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. Grading-V - For sub base cum drainage layer - Mix in Place Method | BI01010001010000000000000515BI0100001171 | 45 | cum |
60 | 6.02 | 4.12 : Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. | BI01010001010000000000000515BI0100001172 | 30 | cum |
61 | 6.03 | 55.4 : Supplying and stacking 36mm size hard broken stone in standard heaps for measurement.Supplying and stacking 36mm size hard broken stone in standard heaps for measurement. | BI01010001010000000000000515BI0100001173 | 19.7 | cum |
62 | 6.04 | 55.8.a : Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 36mm departmental broken stone and compacting with power roller to get a compact surface.Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 36mm departmental broken stone and compacting with power roller to get a compact surface. | BI01010001010000000000000515BI0100001174 | 19.7 | cum |
63 | 6.05 | 5.1.a : Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means.Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means. | BI01010001010000000000000515BI0100001175 | 300 | sqm |
64 | 6.06 | 5.2.a : Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. | BI01010001010000000000000515BI0100001176 | 1500 | sqm |
65 | 6.07 | od35247/2019_2020 : Mix Seal Surfacing Providing , Laying and rolling of close graded premix surfacing material of 20mm thickness composed of 11.2 mm to 0.9mm Type A aggregates using penetration grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base , including mixing in a suitable plant , laying and rolling with a three wheel 8-10 KN static roller and finishing to required level and grades as per Technical Specification Clause 509 of MORD (Usage of bitumen is 22.00kg/10m2) By Manual Means | BI01010001010000000000000515BI0100001177 | 1500 | sqm |
66 | 6.08 | 3.6 : Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000mExcavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m | BI01010001010000000000000515BI0100001178 | 60 | cum |
67 | 6.09 | 12.4 : Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. | BI01010001010000000000000515BI0100001179 | 45 | cum |
68 | 6.1 | 12.8.B : Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br>\nPCC Grade M20 (Without formwork) <br>Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications PCC Grade M20 (Without formwork) | BI01010001010000000000000515BI0100001180 | 15 | cm |
69 | 7 | B B C HALL - PALATRAPADI ROAD (WARD 10) | BI01010001010000000000000515BI0100001181 | ||
70 | 7.01 | 3.6 : Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000mExcavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m | BI01010001010000000000000515BI0100001182 | 300 | cum |
71 | 7.02 | 4.1.B.1 : Construction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. <br>\nGrading-V - For sub base cum drainage layer - Mix in Place MethodConstruction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. Grading-V - For sub base cum drainage layer - Mix in Place Method | BI01010001010000000000000515BI0100001183 | 150 | cum |
72 | 7.03 | 12.4 : Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. | BI01010001010000000000000515BI0100001184 | 150 | cum |
73 | 7.04 | 12.8.1.C : Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br>\n RCC Grade M20 - Using Concrete Mixer - (Without formwork) <br>Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications RCC Grade M20 - Using Concrete Mixer - (Without formwork) | BI01010001010000000000000515BI0100001185 | 75 | cum |