Contract Notice High Voltage Installation WorkUtilitiesDescription The Sa2 Project Is The Connection Of A New 66 Kv Indoors Substation At Varmahl And A New Indoors Substation At Sau rkr kur Town By A 23 Km Long 66 Kv Underground Cables Also The Connection Of The Existing Overhead Line Sa1 To The New Substations In Varmahl And Sau rkr kur With Underground Cables In Total Of 2 Km Please See Tender Documents For Further Information Time Limit For Receipt Of Tenders Or Requests To Participate Date 13 08 2019 Local Time 11 00
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.